TRAINING: |
No special training requirements have been identified for any documents issued with this change notice. |
|
REMARKS: |
IMC 2515 |
(Reactor Inspection Program - Operations Phase) has been revised to redefine
the backshift coverage policy. This change was prompted by the adoption
of a flexible work schedule by many licensees. The manual chapter was also
revised to reflect the suspension of SALP, which occurred September 15,
1998. |
IP 57050 |
(Visual Testing Examination) |
IP 57060 |
(Liquid Penetrant Testing Examination) |
IP 57070 |
(Magnetic Particle Testing Examination) |
IP 57080 |
(Ultrasonic Testing Examination) |
|
These inspection procedures have been revised as part of the
triennial review process for inspection program documents. As a result of
this review the documents have been revised to change the emphasis from
new plant construction to inservice inspection in addition to a general
update of content and references. |
|
|
DISTRIBUTION: |
Standard |