Location of Projected New Nuclear Power Reactors |
Bell Bend |
Bellefonte, Units 3 & 4 |
Callaway, Unit 2 |
Calvert Cliffs, Unit 3 |
Comanche Peak Units, 3 & 4 |
Fermi, Unit 3 |
Grand Gulf, Unit 3 |
Levy County, Units 1 & 2 |
Nine Mile Point, Unit 3 |
North Anna, Unit 3 |
River Bend Station, Unit 3 |
Shearon Harris, Units 2 & 3 |
South Texas Project, Units 3 & 4 |
Victoria County Station, Units 1 & 2 |
Virgil C. Summer, Units 2 & 3 |
Vogtle, Units 3 & 4 |
William States Lee III, Units 1 & 2 |
|
Home > Nuclear Reactors > New Reactors > Combined License Applications > North Anna, Unit 3 Application
North Anna, Unit 3 Application
|
Who: |
Dominion Virginia Power (Dominion)
|
What: |
Application for a combined license (COL) for an Economic Simplified Boiling Water Reactor (ESBWR) designated as North Anna, Unit 3
|
When: |
November 27, 2007 (date of application submittal)
|
Where: |
Dominion's North Anna site near Richmond in Louisa County, Virginia |
|
On this page:
Some links on this page are to documents in our our Agencywide Documents Access and Management System (ADAMS). For additional information, see our Plugins, Viewers, and Other Tools.
Reference Documents
Applicant Documents
Some combined license applications were submitted with hyperlinks to various reference documents. Currently, the hyperlinks in those applications are not active. These hyperlinks represent an advanced feature that could be activated when the agency upgrades to web-based ADAMS, at which point these applications and documents such as the Design Control Documents would be linked together. In the interim, and for those applications that do not have the hyperlink feature, the reference documents may be viewed under the Reference Documents section of the combined license application page. In addition, DVDs of the various documents are available by contacting the Public Document Room staff.
Date |
Description |
12/12/08 |
Dominion transmittal letter for North Anna Unit 3 COLA - Revision #1
- Part 1 - General and Administrative Information
- Part 2 - Final Safety Analysis Report (FSAR)
- Part 3 - Environmental Report
- Part 4 - Technical Specifications
- Part 5 - Emergency Plan
- Part 6 - Part not used in this application
- Part 7 - Departures Report
- Part 8 - Security Plan
- Part 9 - Part not used in this application
- Part 10 - Tier 1/Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC)
|
04/24/08 |
Dominion Application for Order and Conforming Amendments for Transfer of North Anna Early Site Permit
|
11/27/07 |
Dominion transmittal letter for North Anna Unit 3 COLA
- Part 1 - General and Administrative Information
- Part 2 - Final Safety Analysis Report (FSAR)
- Part 3 - Environmental Report
- Part 4 - Technical Specifications
- Part 5 - Emergency Plan
- Part 6 - Part not used in this application
- Part 7 - Departures (Variances, Supplemental Information) from the ESBWR Design Control Document (DCD)
- Part 8 - Security Plan [This Part contains safeguards information which is withheld from public availability]
- Part 9 - Part not used in this application
- Part 10 - Tier 1/Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC)
|
Application Review Schedule
Key Milestones |
Completion Date Actual - A Target - T |
Application Tendered |
11/27/07 - A |
Acceptance Review |
Acceptance Review Start |
12/03/07 - A |
Docketing Decision Letter Issued/Acceptance Review Complete |
01/28/08 - A |
Review Schedule Established/Schedule Letter Issued to Applicant |
02/27/08 - A |
Safety Review |
Phase 1 - Requests for Additional Information (RAIs) Issued to Applicant |
08/29/08 - A |
Phase 2 - SER with Open Items (incorporating COLA Rev 1) issued |
07/24/09 - T |
Phase 3 - ACRS Review of SER with Open Items Complete |
11/04/09 - T |
Phase 4 - Advanced SER with no Open Items Issued |
09/10 - T |
Phase 5 - ACRS Review of SER with no Open Items Complete |
12/10 - T |
Phase 6 - Final SER Issued |
02/11 - T |
Environmental Review |
Phase 1 - Environmental impact statement (EIS) summary report issued |
09/05/08 - A |
Phase 2 - Draft EIS issued to EPA |
12/19/08 - A |
Phase 3 - Response to public comments on draft EIS issued |
06/09 - T |
Phase 4 - Final EIS issued to EPA |
12/09 - T |
Hearing |
Commission or ASLB hold mandatory hearing |
|
License |
Commission decision on issuance of COL application |
|
Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.
NRC Documents
Date |
Description |
02/25/09 |
Updated Combined License Application Review Schedule
|
10/30/08 |
Order Approving Transfer of Early Site Permit No. ESP-003 And Conforming Amendment
|
09/04/08 |
Environmental Scoping Summary Report
|
07/17/08 |
Correction and Supplement to Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process
|
02/29/08 |
Federal Register Notice for Hearing and Opportunity to Petition for Leave to Intervene for North Anna Unit 3
|
02/27/08 |
Combined License Application Review Schedule
|
01/28/08 |
COLA Acceptance for Docketing and Federal Register Notice
|
12/06/07 |
Acknowledgement of Receipt of Application and Federal Register Notice
|
Draft Environmental Impact Statement
- See NUREG-1917, "Supplemental Environmental Impact Statement for the Combined License (COL) for North Anna Power Station Unit 3" (December 2008)
Requests for Additional Information
Category |
RAI Date |
RAI Letter No. and Subject |
Applicant Response |
Safety |
03/20/08 |
RAI Letter No. 01 SRP Section 12.02
|
04/28/08
|
03/28/08 |
RAI Letter No. 02 SRP Section 2.3.2.3
|
04/25/08
|
04/01/08 |
RAI Letter No. 03 SRP Section 2.3.4.3
|
05/12/08
|
05/19/08 |
RAI Letter No. 04 SRP Sections 11.02, 11.04, and 11.05
|
06/30/08
|
06/04/08 |
RAI Letter No. 05 SRP Sections 17.04, 17.06, and 19
|
07/14/08
|
06/05/08 |
RAI Letter No. 06 SRP Sections 06.02.01, 06.02.04, 10.03.06, and 14.02
|
07/14/08
|
06/11/08 |
RAI Letter No. 07 SRP Sections 09.03.02, 11.02, 11.03, 11.04, 11.05, and 13.05.02.01
|
07/23/08
|
06/11/08 |
RAI Letter No. 08 SRP Section 09.05.01
|
07/23/08
|
06/13/08 |
RAI Letter No. 09 SRP Section 08.02
|
07/28/08
|
06/17/08 |
RAI Letter No. 10 SRP Sections 2.05.04 and 02.05.05
|
07/14/08
|
06/19/08 |
RAI Letter No. 11 SRP Sections 02.05.04, 08.03.02, 09.02.05, 12.02, 13.01.02-13.01.03
|
08/04/08
|
06/23/08 |
RAI Letter No. 12 SRP Sections 05.02.05, 10.04.05, and 14.02
|
08/07/08
|
06/24/08 |
RAI Letter No. 13 SRP Sections 09.01.04, 09.01.05, 09.05.04, and 17.5
|
08/04/08
|
06/27/08 |
RAI Letter No. 14 SRP Sections 03.07.01, 03.07.02, and 05.02.04
|
08/12/08
|
07/07/08 |
RAI Letter No. 15 SRP Section 13.03
|
Rescheduled |
07/09/08 |
RAI Letter No. 16 SRP Sections 08.02, 09.05.04, and 12.02
|
08/21/08
|
07/15/08 |
RAI Letter No. 17 SRP Sections 02.01.02, 02.03.01, 02.03.02, 02.03.05, 09.02.01, and 14.02
|
08/28/08
|
07/18/08 |
RAI Letter No. 18 SRP Sections 13.03 and 14.03.10
|
Rescheduled |
07/21/08 |
RAI Letter No. 19 SRP Sections 02.03.05, 03.09.03, 05.03.01, and 14.03.10
|
09/03/08
|
07/27/08 |
RAI Letter No. 20 SRP Sections 09.05.01, 11.04
|
09/04/08
|
07/28/08 |
RAI Letter No. 21 SRP Sections 05.02.01.01, 05.02.01.02, 13.01.01, 13.01.02-13.01.03, 13.02.01, 13.02.02, 13.05.02.01, and 14.02
|
09/11/08
|
08/01/08 |
RAI Letter No. 22 SRP Sections 03.09.06 and 03.11
|
09/11/08 |
08/06/08 |
RAI Letter No. 23 SRP Sections 03.02.01 and 03.02.02
|
09/17/08 |
08/08/08 |
RAI Letter No. 24 SRP Sections 02.04.12, 12.02, 12.03-12.04, 12.05, 14.02, and 14.03.03
|
09/19/08 |
08/12/08 |
RAI Letter No. 25 SRP Sections 02.02.03, 03.05.01.05, 12.02, and 15.06.05
|
12/29/08
10/20/08
10/17/08
09/26/08
|
08/19/08 |
RAI Letter No. 26 SRP Sections 02.04.13, 03.09.02, 05.03.02, and 11.05
|
10/02/08 |
08/21/08 |
RAI Letter No. 27 SRP Sections 12.01 and 12.03-12.04
|
10/03/08 |
08/21/08 |
RAI Letter No. 28 SRP Sections 01 and 02.04.02
|
09/29/08
09/16/08
|
10/16/08 |
RAI Letter No. 29 SRP Section 08.02
|
12/01/08 |
10/20/08 |
RAI Letter No. 30 SRP Sections 02.03.01, 06.02.04, 09.05.04, 11.03, 12.02, 12.03-12.04
|
12/03/08 |
01/12/09 |
RAI Letter No. 31 SRP Sections 02.03.01, 06.02.04, 09.05.04, 11.03, 12.02, 12.03-12.04
|
|
02/18/09 |
RAI Letter No. 032 SRP Sections 08.02, 11.04, 11.05, 13.01.02-13.01.03, 14.03.06
|
|
03/09/09 |
RAI Letter No. 033 SRP Sections 2.2.3, 2.4.2, 8.2, 12.2, and 14.3.7
|
|
Environmental |
06/18/08 |
RAI Letter Regarding the Environmental Review of the Combined License Application
|
07/17/08
|
Public Meetings
Date |
Description |
02/03/09 |
Draft Supplemental EIS Public Meeting
|
04/16/08 |
Environmental Scoping
|
12/13 - 14/07 |
Meeting regarding the technical content of the North Anna 3 COLA
|
11/29/07 |
North Anna 3 COLA Orientation
|
10/24/07 |
Public Outreach Meeting
|
Contacts
Contacts for the North Anna COL Application |
Safety Project Manager |
Thomas Kevern |
Environmental Project Manager |
Alicia Williamson |
Contact a Public Affairs Officer |
|