skip navigation links 
 
Index | Site Map | FAQ | Facility Info | Reading Rm | New | Help | Glossary | Contact Us blue spacer  
secondary page banner Return to NRC Home Page

NRC Seal NRC NEWS
U. S. NUCLEAR REGULATORY COMMISSION
Office of Public Affairs Telephone: 301/415-8200
Washington, DC 20555-001 E-mail: opa@nrc.gov

                                 

No. 96-76                                   FOR IMMEDIATE RELEASE
                                         (Thursday, May 30, 1996)


          NRC ESTABLISHES INDEPENDENT SAFETY ASSESSMENT
               TEAM TO EVALUATE MAINE YANKEE PLANT

     The Nuclear Regulatory Commission today established an Independent Safety Assessment
(ISA) team to take a comprehensive look at the Maine Yankee nuclear power plant's performance
in connection with its operating license.
     
     Concerns have been raised about Maine Yankee's analyses and the NRC's review of a
computer code used in calculating the safety of the plant in the event of a small break, loss-of-coolant accident.  The NRC's Inspector General (IG) on May 8 issued a report that identified
deficiencies in the staff's handling of some past licensing and regulatory matters at Maine Yankee. 
The NRC's Office of Investigations has a separate investigation of the licensee.
     
     The ISA team is a follow on to the IG investigation and is responsive to a request from
Chairman Shirley Ann Jackson, who also requested the NRC staff to assess its own policies and
practices in light of the IG's findings.  The ISA team, which will report to the Chairman with a
Commission-approved charter, is also responsive to concerns raised by the Governor of Maine.

     The team will take a broader look at the licensing basis and operational safety performance
of Maine Yankee.  All told, the team is expected to complete its evaluation and submit a report to
the Chairman in about 16 weeks.

     
     The ISA team will be headed by Edward L. Jordan, the NRC's Director of the Office for
Analysis and Evaluation of Operational Data.  AEOD was formed in 1979 to conduct independent
safety evaluations of power reactor operational data.  

     Mr. Jordan is directed to develop a detailed charter, team composition and work plan by
June 9.  The team will include expert contract support from the national laboratories and
independent consultants.  In addition to specialists from the NRC, there will also be
representatives from the State of Maine.  

     By order of the NRC, Maine Yankee currently is restricted to 90 percent of its approved
power level of 2700 Mwt.  The plant is ten miles north of Bath, Maine.

                                #