Index | Site Map | FAQ | Facility Info | Reading Rm | New | Help | Glossary | Contact Us |
Fact Sheet on Decommissioning Nuclear Power PlantsBackgroundWhen a power company decides to close its nuclear power plant permanently, the facility must be decommissioned by safely removing it from service and reducing residual radioactivity to a level that permits release of the property and termination of the operating license. The Nuclear Regulatory Commission has strict rules governing nuclear power plant decommissioning, involving cleanup of radioactively contaminated plant systems and structures and removal of the radioactive fuel. These requirements protect workers and the public during the entire decommissioning process and the public after the license is terminated. DiscussionLicensees may choose from three alternative decommissioning strategies: DECON, SAFSTOR, or ENTOMB.
To be acceptable, decommissioning must be completed within 60 years of the plant ceasing operations. A time beyond that would be considered only when necessary to protect public health and safety in accordance with NRC regulations. RegulationsThe requirements for decommissioning a nuclear power plant are set out in NRC regulations (Title 10 of the Code of Federal Regulations, part 20 subpart E, and parts 50.75, 50.82, 51.53, and 51.95). In August 1996, a revised rule went into effect that redefined the decommissioning process and required owners to provide the NRC with early notification of planned decommissioning activities. The rule allows no major decommissioning activities to be undertaken until after certain information has been provided to the NRC and the public. Before a nuclear power plant begins operations, the licensee must establish or obtain a financial mechanism – such as a trust fund or a guarantee from its parent company – to ensure that there will be sufficient money to pay for the ultimate decommissioning of the facility. Licensees must update the NRC on the status of these mechanisms every two years (annually within five years of the planned end of plant operations). This requirement provides the public reasonable assurance that funds will be available when needed to clean up a plant site and avoid costly legacy sites that must be cleaned up at taxpayer expense. Public InvolvementSeveral opportunities are provided for public involvement during the decommissioning process. A public meeting is held in the vicinity of the facility after submittal of a post-shutdown decommissioning activities report (PSDAR) to the NRC. Another public meeting is held when NRC receives the license termination plan (LTP). An opportunity for a public hearing is provided prior to issuance of a license amendment approving the LTP or any other license amendment request. In addition, when NRC holds a meeting with the licensee, members of the public are allowed to observe the meeting (except when the discussion involves proprietary, sensitive, safeguards, or classified information). Improving the Decommissioning ProgramSeveral nuclear power plants completed decommissioning in the 1990s without a viable option for disposing of their spent nuclear fuel, because the federal government did not construct a geologic repository as planned. Accordingly, the NRC implemented regulations allowing licensees to sell off part of their land that meets regulatory requirements while maintaining a small parcel under license for storing the spent fuel. These stand-alone facilities, called “independent spent fuel storage installations” (ISFSIs), remain under license and NRC regulation, and the licensees are responsible for security and for maintaining insurance and funding for eventual decommissioning. As more facilities complete decommissioning, the NRC is implementing “lessons learned” in order to improve the program and focus on the prevention of future legacy sites. Applications for new reactors must now describe how design and operations will minimize contamination during the plant’s operating life and facilitate eventual decommissioning. The agency is developing new regulations that will require plant operators to be more vigilant in preventing contamination during operations, and cleaning up and monitoring any contamination that does occur. Phases of DecommissioningThe requirements for power reactor decommissioning activities may be divided into three phases: (1) initial activities; (2) major decommissioning and storage activities; and (3) license termination activities. (1) Initial ActivitiesWhen a nuclear power plant licensee shuts down the plant permanently, it must submit a written certification of permanent cessation of operations to the NRC within 30 days. When radioactive nuclear fuel is permanently removed from the reactor vessel, the owner must submit another written certification to the NRC, surrendering its authority to operate the reactor or load fuel into the reactor vessel. This eliminates the obligation to adhere to certain requirements needed only during reactor operation. Within two years after submitting the certification of permanent closure, the licensee must submit a post-shutdown decommissioning activities report (PSDAR) to the NRC. This report provides a description of the planned decommissioning activities, along with a schedule for accomplishing them, and an estimate of the expected costs. The PSDAR must discuss the reasons for concluding that environmental impacts associated with the site-specific decommissioning activities have already been addressed in previous environmental analyses. Otherwise, the licensee must request a license amendment for approval of the activities and submit to the NRC a report on the additional impacts of decommissioning on the environment. After receiving a PSDAR, the NRC publishes a notice of receipt in the Federal Register, makes the report available for public review and comment, and holds a public meeting in the vicinity of the plant to discuss the licensee’s intentions. (2) Major Decommissioning ActivitiesNinety days after the NRC receives the PSDAR, the owner can begin major decommissioning activities without specific NRC approval. These activities could include permanent removal of such major components as the reactor vessel, steam generators, large piping systems, pumps, and valves. However, decommissioning activities conducted without specific prior NRC approval must not:
If any decommissioning activity does not meet these terms, the licensee is required to submit a license amendment request, which would provide an opportunity for a public hearing. Initially, the owner can use up to 3 percent of its funds set aside for decommissioning planning. An additional 20 percent can be used 90 days after submittal of the PSDAR. The remaining decommissioning trust funds are then available when the owner submits a detailed site-specific cost estimate to the NRC. (3) License Termination ActivitiesThe owner is required to submit a LTP within two years of the expected license termination. The plan addresses each of the following: site characterization, identification of remaining site dismantlement activities, plans for site remediation, detailed plans for final radiation surveys for release of the site, method for demonstrating compliance with the radiological criteria for license termination, updated site-specific estimates of remaining decommissioning costs, and a supplement to the environmental report that describes any new information or significant environmental changes associated with the owner's proposed termination activities. Most plans envision releasing the site to the public for unrestricted use, meaning any residual radiation would be below NRC’s limits of 25 millirem annual exposure and there would be no further regulatory controls by the NRC. Any plan proposing release of a site for restricted use must describe the site's end use, documentation on public consultation, institutional controls, and financial assurance needed to comply with the requirements for license termination for restricted release. The LTP requires NRC approval of a license amendment. Before approval can be given, an opportunity for hearing is published and a public meeting is held near the plant site. The NRC uses a standard review plan (NUREG-1700, "Standard Review Plan for Evaluating Nuclear Power Reactor License Termination Plans)" to ensure high quality and uniformity of LTP reviews. The standard review plan is available to the public so that NRC's review process is understood clearly. If the remaining dismantlement has been performed in accordance with the approved LTP and the termination survey demonstrates that the facility and site are suitable for release, the NRC issues a letter terminating the operating license. Permanently Shutdown Nuclear Power PlantsThere are currently 13 nuclear power plant units that have permanently shut down and are in some phase of the decommissioning process. These are:
These are described in greater detail in the material that follows. Ten nuclear power plants have completed the decommissioning process and have had their operating license terminated. These are:
January 2008
|
Reactor |
Type |
Thermal Power |
Location |
Shutdown |
Status |
Fuel Onsite |
---|---|---|---|---|---|---|
Big Rock Point |
BWR |
67 MW |
Charlevoix, MI |
8/97 |
ISFSI Only |
Yes |
CVTR |
Pressure Tube, Heavy Water |
65 MW |
Parr, SC |
1/67 |
License Terminated |
No |
Dresden I |
BWR |
700 MW |
Morris, IL |
10/31/78 |
SAFSTOR |
Yes |
Fermi I |
Fast Breeder |
200 MW |
Monroe Co., MI |
9/22/72 |
SAFSTOR/DECON |
No |
Fort St. Vrain |
HTGR |
842 MW |
Platteville, CO |
8/18/89 |
License Terminated |
Yes |
GE VBWR |
BWR |
50 MW |
Alameda Co., CA |
12/9/63 |
SAFSTOR |
No |
Haddam Neck |
PWR |
1825 MW |
Haddam Neck, CT |
7/22/96 |
ISFSI Only |
Yes |
Humboldt Bay 3 |
BWR |
200 MW |
Eureka, CA |
7/02/76 |
DECON |
Yes |
Indian Point I |
PWR |
615 MW |
Buchanan, NY |
10/31/74 |
SAFSTOR |
Yes |
LaCrosse |
BWR |
165 MW |
LaCrosse, WI |
4/30/87 |
SAFSTOR |
Yes |
Main Yankee |
PWR |
2772 MW |
Bath, ME |
12/96 |
ISFSI Only |
Yes |
Millstone I |
BWR |
2011 MW |
Waterford, CT |
11/04/95 |
SAFSTOR |
Yes |
N.S. Savannah |
PWR |
80 MW |
Norfolk, VA |
1970 |
SAFSTOR |
No |
Pathfinder |
Superheat BWR |
190 MW |
Sioux Falls, SD |
9/16/67 |
DECON NRC Part 30 |
No |
Peach Bottom I |
HTGR |
115 MW |
York Co., PA |
10/31/74 |
SAFSTOR |
No |
Rancho Seco |
PWR |
2772 MW |
Sacramento, CA |
6/7/89 |
DECON |
Yes |
San Onofre I |
PWR |
1347 MW |
San Clemente, CA |
11/30/92 |
DECON |
Yes |
Saxton |
PWR |
28 MW |
Saxton, PA |
5/72 |
License Terminated |
No |
Shoreham |
BWR |
2436 MW |
Suffolk Co., NY |
6/28/89 |
License Terminated |
No |
Three Mile Island 2 |
PWR |
2772 MW |
Middletown, PA |
3/28/79 |
SAFSTOR* |
No |
Trojan |
PWR |
3411 MW |
Portland, OR |
11/9/92 |
ISFSI Only |
Yes |
Yankee Rowe |
PWR |
600 MW |
Franklin Co., MA |
10/1/91 |
ISFSI Only |
Yes |
Zion 2 |
PWR |
3250 MW |
Zion, IL |
2/98 |
SAFSTOR |
Yes |
Zion I |
PWR |
3250 MW |
Zion, IL |
2/98 |
SAFSTOR |
Yes |
* Post-defueling monitored storage (PDMS).
Note: An independent spent fuel storage installation (ISFSI) is a stand-alone facility within the plant boundary constructed for the interim storage of spent nuclear fuel.
|