April 2008 Print E-mail
Solid Waste Program

This month's Denali Commission Solid Waste Program project developments are as follows:

  • Hooper Bay - Work on the equipment repair project is essentially complete.
  • Bethel - Equipment purchase project has been completed.  Project savings of approximately $5,900 will be recycled in the program.
  • Valley Recycling - A new electric forklift arrived in Anchorage on June 25, 2008 and will be delivered to Palmer on July 1.
  • Shishmaref - Signs, totes, and burn units are in transit via barge.
  • Tanana - Fencing for the landfill is at barge yard.
  • Tyonek - The Kenai Peninsula borough has approved a proposed project plan and issued 'request for quote' to Tyonek for work to be performed.
  • Selawik - Dozer parts and tools currently in transit, via barge and US mail.
  • Nightmute - To date, approximately 850 hours of clean-up labor has been performed burning, separating, and bagging solid waste.
  • Akiachak, Nunapitchuk, and New Stuyahok burn unit manufacture for those projects is on target for August.