Click on the State of Alaska icon to view an interactive map of all Denali Commission projects by funding year, location, and program area.
April 2008 |
|
|
This month's Denali Commission Solid Waste Program project developments are as follows:
- Hooper Bay - Work on the equipment repair project is essentially complete.
- Bethel - Equipment purchase project has been completed. Project savings of approximately $5,900 will be recycled in the program.
- Valley Recycling - A new electric forklift arrived in Anchorage on June 25, 2008 and will be delivered to Palmer on July 1.
- Shishmaref - Signs, totes, and burn units are in transit via barge.
- Tanana - Fencing for the landfill is at barge yard.
- Tyonek - The Kenai Peninsula borough has approved a proposed project plan and issued 'request for quote' to Tyonek for work to be performed.
- Selawik - Dozer parts and tools currently in transit, via barge and US mail.
- Nightmute - To date, approximately 850 hours of clean-up labor has been performed burning, separating, and bagging solid waste.
- Akiachak, Nunapitchuk, and New Stuyahok burn unit manufacture for those projects is on target for August.
|