Sec. 61.274  Initial report.

    (a) The owner or operator of each storage vessel to which this 
subpart applies and which has a design capacity greater than or equal to 
38 cubic meters (10,000 gallons) shall submit an initial report 
describing the controls which will be applied to meet the equipment 
requirements of Sec. 61.271 or Sec. 61.270(g). For an existing storage 
vessel or a new storage vessel for which construction and operation 
commenced prior to September 14, 1989, this report shall be submitted 
within 90 days of September 14, 1989 and can be combined with the report 
required by Sec. 61.10. For a new storage vessel for which construction 
or operation commenced on or after September 14, 1989, the report shall 
be combined with the report required by Sec. 61.07 or 40 CFR 65.5(b). 
In the case where the owner or operator seeks to comply with Sec. 
61.271(c), with a control device other than a flare, this information 
may consist of the information required by Sec. 61.272(c)(1).

[[Page 179]]

    (b) The owner or operator of each storage vessel seeking to comply 
with Sec. 61.271(c) with a flare, shall submit a report containing the 
measurements required by 40 CFR 60.18(f) (1), (2), (3), (4), (5), and 
(6). For the owner or operator of an existing storage vessel not seeking 
to obtain a waiver or a new storage vessel for which construction and 
operation commenced prior to September 14, 1989, this report shall be 
combined with the report required by paragraph (a) of this section. For 
the owner or operator of an existing storage vessel seeking to obtain a 
waiver, the reporting date will be established in the response to the 
waiver request. For the owner or operator of a new storage vessel for 
which construction or operation commenced after September 14, 1989, the 
report shall be submitted within 9O days of the date the vessel is 
initially filled (or partially filled) with benzene.