Skip to contentUnited States Department of Transportation - Federal Highway Administration Go to TFHRC homeGo to FHWA websiteFeedback

  NDE Center logo.

FHWA NDE CENTER RESEARCH & DEVELOPMENT

Feasibility of Strengthening Concrete Beams Using Bonded Composite Laminate

Federal Highway Administration (FHWA) Nondestructive Evaluation (NDE) Center in collaboration with New York State DOT (NYSDOT) is conducting a test program to evaluate the effectiveness of carbon fiber laminate repairs on deteriorated prestressed box girders. The objectives of the project are as follows:

  1. Determine the actual load carrying capacity of the deteriorated box beams, and test the accuracy of models developed by NYSDOT and FHWA.
  2. Evaluate the effectiveness of bonded carbon fiber laminates for increasing the load carrying capacity of severely deteriorated box girder.
  3. Evaluate existing NDE technologies for the evaluation of deteriorated box girders and bonded carbon fiber laminate installations.
  4. Develop design and construction guidelines for using bonded composite laminates for strengthening prestressed concrete box girders in the State of New York.

This research will ultimately help in reducing the number of prestressed concrete bridges rated as structurally deficient, consistent with the strategic goals of the FHWA.

Background

Five prestressed box beams were salvaged from a bridge replacement project in 1997 in up-state New York. The purpose of salvaging these girders was twofold. The first was to provide the FHWA NDE Center with unique specimens containing corroded and broken prestressed stands, spalling etc.. The unique specimens will provide a test-bed for the development and evaluation of nondestructive techniques for prestressed concrete structures. The second purpose was to perform load test on several salvaged box girders to assist NYSDOT in research concerning the use of bonded carbon laminates.

Picture of Box Beams in place in NY State prior to bridge replacement.
Figure 1. Box Beams in place in NY State prior
to bridge replacement

Test Plan Summary

To evaluate the strength of the existing girders, two load tests were preformed on the salvaged prestressed box girders in their natural state. Following these tests, composite laminates were installed on a third girder, and the girder was tested to failure. Finally three girders will be placed in fall 2000 on on-site test bridge (Geosynthetic Reinforced Soil (GRS) abutments) that will allow for the evaluation of load rating techniques for detection of corroded and broken strands. A test summary and schedule is shown below:

Test 1. Load Test of deteriorated box girder

Goal: This load test will determine the elastic limit of the girders to be used in the final test bridge configuration, and validate models to predict the strength of deteriorated girders. It will also provide the necessary data for the design of carbon laminate installation.

Test Date: October 19, 1999.

Status: Test completed, data analysis ongoing

Figure 2. Test Setup
Picture of the test setup.

Test 2: Load test of intact girder

Goal: Test 2 will be used to determine the actual strength of a girder that which appears to be intact. The data will be used to evaluate the effectiveness of the composite installation, and to validate models.

Test Date: December 9, 1999

Status: Test completed, data analysis ongoing.

Test 3: Load test of composite laminate reinforced girder

Goal: This test will be used to evaluate the effectiveness of carbon bonded overlay for use as a strengthening tool in prestressed girders. The test will also be used to validate design procedures and models, and to develop guidelines for use in the State of New York.

Test Date: August 1, 2000

Status: Test completed, data analysis ongoing.

Picture of test 3 at failure load.
Figure 3. Test 3 at Failure Load

Test 4: Load test of on-site test bridge

Goal: Test 4 will evaluate the load carrying capacity of an on-site test bridge, to provide loading for a test of the GRS abutments, and the loading rating tools developed through the NDE program.

Test Date: Fall 2000.

 

For more information, please contact either by e-mail or telephone.

Frank Jalinoos  (202) 493-3082

frank.jalinoos@fhwa.dot.gov

Back to the top

FHWA NDE Center Home | Research & Development | Facilities | Publications | Newsletter | Links | Contacts | DOT Home



http://www.tfhrc.gov/hnr20/nde/nysdotbridge.htm

FHWA
TFHRC Home | FHWA Home | Feedback

United States Department of Transportation - Federal Highway Administration