Printable version of this report (.pdf, 12 mb) Utah Demonstration ProjectRapid Removal and Replacement of the 4500 South Bridge over I-215 in Salt Lake City
|
1. Report No. | 2. Government Accession No. | 3. Recipient's Catalog No. | |
4. Title and Subtitle Utah Demonstration Project: Rapid Removal and Replacement of the 4500 South Bridge over I-215 in Salt Lake City |
5. Report Date April 2009 |
||
6. Performing Organization Code | |||
7. Author(s) Ahmad Ardani, P.E., Jagannath Mallela, Gary Hoffman, P.E., R.L.S. |
8. Performing Organization Report No. | ||
9. Performing Organization Name and Address Applied Research Associates, Inc. 100 Trade Centre Drive, Suite 200 Champaign, IL 61820 |
10. Work Unit No.(TRAIS) C6B | ||
11. Contract or Grant No. | |||
12. Sponsoring Agency Name and Address Office of Infrastructure Federal Highway Administration 1200 New Jersey Avenue, SE Washington, DC 20590 |
13. Type of Report and Period Covered Draft Final Report May 2007–March 2009 |
||
14. Sponsoring Agency Code | |||
15. Supplementary Notes Contracting Officers Technical Representatives: Byron Lord, Mary Huie |
|||
16. Abstract
As part of a national initiative sponsored by the Federal Highway Administration under the Highways for LIFE program, the Utah Department of Transportation (UDOT) was awarded a $1 million grant to demonstrate the use of proven, innovative technologies for accelerated bridge removal and replacement. This report documents accelerated bridge construction (ABC) techniques used to remove and replace the 4500 South Bridge on State Route 266 over Interstate 215 in Salt Lake City over a weekend. This report includes construction details of the bridge superstructure built offsite on temporary abutments and prefabricated and cast-in-place bridge components and substructure built under the existing bridge without interfering with traffic flow. It also discusses use of a self-propelled modular transporter (SPMT) to remove the old bridge and to replace it with a new one. Under conventional construction, the impact of this project on the traveling public was estimated at 120 days, but with the use of accelerated construction techniques, the impact was reduced to a single weekend for I-215 and 10 days for SR 266. Using an SPMT and other ABC techniques added approximately $0.81 million to the initial construction cost of the project. However, a more comprehensive economic analysis including user cost savings shows that the project saved road users about $3.24 million (or approximately 36 percent of the total project costs). Because of the success of this project, UDOT has decided to use ABC techniques more routinely on future projects and has set a goal of making ABC standard practice for all bridges by 2010. |
|||
17. Key Words Highways for LIFE, accelerated bridge construction, construction manager general contracting, self-propelled modular transporter, SPMT, innovative construction, economic analysis, prefabricated bridge elements and systems, full lane closure |
18. Distribution Statement No restriction. This document is available to the public through http://www.fhwa.dot.gov/hfl/. |
||
19. Security Classify. (of this report) Unclassified |
20. Security Classify. (of this page) Unclassified |
21. No. of Pages 60 |
22. Price Free |
Form DOT F 1700.7 (8-72) Reproduction of completed page authorized
The project team would like to acknowledge the invaluable insights and guidance of Federal Highway Administration (FHWA) Highways for LIFE Team Leader Byron Lord and Program Coordinators Mary Huie and Kathleen Bergeron, who served as the technical panel on this demonstration project. Their vast knowledge and experience with the various aspects of construction, technology deployment, and technology transfer helped immensely in developing both the approach and the technical matter for this document. The team also is indebted to Utah Department of Transportation engineers Jim McMinimee, Shana Lindsey, Lisa Wilson and Daniel Hsiao and FHWA Division Administrator Butch Waidelich and ITS and Structural Engineer Russ Robertson for their tireless advice, assistance, and coordination during this project.
AASHTO | American Association of State Highway and Transportation Officials |
---|---|
ABC | Accelerated Bridge Construction |
ADT | Average Daily Traffic |
CIP | Cast-in-Place |
CMGC | Construction Manager General Contracting |
dB(A) | A-Weighted Decibels |
DOT | Department of Transportation |
FHWA | Federal Highway Administration |
FY | Fiscal Year |
HfL | Highways for LIFE |
Hz | Hertz |
IRI | International Roughness Index |
OBSI | On-board Sound Intensity |
OSHA | Occupational Safety and Health Administration |
PIC | Public Involvement Coordinator |
PIM | Public Information Manager |
SAFETEA-LU | Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users |
SI | Sound Intensity |
SPMT | Self-propelled Modular Transporter |
SR | State Route |
SRTT | Standard Reference Test Tire |
UDOT | Utah Department of Transportation |
VOC | Vehicle Operational Costs |