Sec. 107.309  Crane plans and information.

    (a) Three copies of each of the following must be submitted:
    (1) Stress and arrangement diagrams, bill of materials, and 
supporting calculations for all structural components listed in API 
Spec. 2C, Second Edition, February 1972 (with supplement 2).
    (2) Drawings of foundations and substructures with supporting 
calculations for support and stability of each crane under its rated 
load.
    (3) Plans showing the installation of the safety features required 
in Sec. 108.601.
    (4) Drawings of the means provided to stop motion and set brakes 
during a power failure.
    Note: These plans must be submitted to the Coast Guard, if the crane 
is not certified. If the crane is to be certified, four copies must be 
sent to the American Bureau of Shipping or the International Cargo Gear 
Bureau.
    (b) In addition to the plans and information required in paragraph 
(a), the following plans and information must be submitted to the Coast 
Guard only:
    (1) One line diagrams of the electrical power circuits of the 
electric power crane overload protection required in Subpart 111.50 of 
this chapter.
    (2) Diagrams of the hydraulic or pneumatic power and control 
systems, as required by Subpart 58.30-40 or 58.30-50 of this chapter, as 
applicable.