USGS - science for a changing world

USGS Office of Global Change

Maps, Imagery, and Publications Hazards Newsroom Education Jobs Partnerships Library About USGS Podcasts/RSS

Project Site for SAP 1.2 CCSP Timeline

Project Stamp
Project name: SAP 1.2 CCSP Timeline
Planned: Start-End: Sep 1, 2007 - Jun 30, 2008  (403 days ? Work)
Expected: Start-End: Sep 1, 2007 - Jun 30, 2008  (403 days ? done)

Milestones

The following project milestones have been defined:

Milestone
Group
Responsible
Priority
Deadline
Complete
Submit Peer Review Plan for Approval FSP Timeline    Normal Sep 10, 2007 100%
Zero Draft Complete SAP 1.2 CCSP Timeline    Normal Oct 31, 2007 0
Peer review panel finalized FSP Timeline    Normal Nov 26, 2007 0
1st Draft Complete SAP 1.2 CCSP Timeline    Normal Dec 1, 2007 0
Peer Review Complete SAP 1.2 CCSP Timeline    Normal Jan 1, 2008 0
2nd Draft Complete SAP 1.2 CCSP Timeline    Normal Apr 1, 2008 0
End Public Comment Period SAP 1.2 CCSP Timeline    Normal May 16, 2008 0
Final Draft Complete SAP 1.2 CCSP Timeline    Normal Jun 15, 2008 0
Submit to CCSP / CENR for Clearance SAP 1.2 CCSP Timeline    Normal Jun 15, 2008 0
Submit 3rd Draft for USGS and DOI approval FSP Timeline    Normal Jun 15, 2008 0
Web publish final report, submit printing order SAP 1.2 CCSP Timeline    Normal Jun 30, 2008 0
Signature page complete FSP Timeline    Normal Jun 30, 2008 0

Upcoming

The following activities have to be started the next days:

Activities Group Responsible Prio Start Deadline Work Duration Complete
Prepare 1st Draft / (EPN copy edit here) SAP 1.2 CCSP Timeline    Normal Oct 31, 2007 Dec 1, 2007 29.5 days ? 29.5 days ? 0

Overdues

The following activities are overdue:

Activities Group Responsible Prio Start Deadline Work Duration Complete
Compose Zero Draft SAP 1.2 CCSP Timeline    Normal Sep 1, 2007 Oct 31, 2007 59 days ? 59 days ? 0
Solicit names for Peer Reviewers FSP Timeline    Normal Sep 10, 2007 Nov 11, 2007 60 days ? 60 days ? 0

Deadlines

The following activities have to be completed within the next days:

Activities Group Responsible Prio Start Deadline Work Duration Complete
Compose Zero Draft SAP 1.2 CCSP Timeline    Normal Sep 1, 2007 Oct 31, 2007 59 days ? 59 days ? 0
Zero Draft Complete SAP 1.2 CCSP Timeline    Normal Oct 31, 2007 Oct 31, 2007   0 hours 0

Accessibility FOIA Privacy Policies and Notices

Take Pride in America logo USA.gov logo U.S. Department of the Interior | U.S. Geological Survey
URL: http://www.usgs.gov/global_change/sap_1.2/timeline.asp
Page Contact Information: Ask USGS
Page Last Modified: Friday, October 19, 2007