Project Stamp |
Project name: |
SAP 1.2 CCSP Timeline |
Planned: Start-End: |
Sep 1, 2007 - Jun 30, 2008 (403 days ? Work) |
Expected: Start-End: |
Sep 1, 2007 - Jun 30, 2008 (403 days ? done) |
Milestones
The following project milestones have been defined:
Milestone
|
Group
|
Responsible
|
Priority
|
Deadline
|
Complete
|
Submit Peer Review Plan for Approval |
FSP Timeline |
|
Normal |
Sep 10, 2007 |
100% |
Zero Draft Complete |
SAP 1.2 CCSP Timeline |
|
Normal |
Oct 31, 2007 |
0 |
Peer review panel finalized |
FSP Timeline |
|
Normal |
Nov 26, 2007 |
0 |
1st Draft Complete |
SAP 1.2 CCSP Timeline |
|
Normal |
Dec 1, 2007 |
0 |
Peer Review Complete |
SAP 1.2 CCSP Timeline |
|
Normal |
Jan 1, 2008 |
0 |
2nd Draft Complete |
SAP 1.2 CCSP Timeline |
|
Normal |
Apr 1, 2008 |
0 |
End Public Comment Period |
SAP 1.2 CCSP Timeline |
|
Normal |
May 16, 2008 |
0 |
Final Draft Complete |
SAP 1.2 CCSP Timeline |
|
Normal |
Jun 15, 2008 |
0 |
Submit to CCSP / CENR for Clearance |
SAP 1.2 CCSP Timeline |
|
Normal |
Jun 15, 2008 |
0 |
Submit 3rd Draft for USGS and DOI approval |
FSP Timeline |
|
Normal |
Jun 15, 2008 |
0 |
Web publish final report, submit printing order |
SAP 1.2 CCSP Timeline |
|
Normal |
Jun 30, 2008 |
0 |
Signature page complete |
FSP Timeline |
|
Normal |
Jun 30, 2008 |
0 |
Upcoming
The following activities have to be started the next days:
Activities |
Group |
Responsible |
Prio |
Start |
Deadline |
Work |
Duration |
Complete |
Prepare 1st Draft / (EPN copy edit here) |
SAP 1.2 CCSP Timeline |
|
Normal |
Oct 31, 2007 |
Dec 1, 2007 |
29.5 days ? |
29.5 days ? |
0 |
Overdues
The following activities are overdue:
Activities |
Group |
Responsible |
Prio |
Start |
Deadline |
Work |
Duration |
Complete |
Compose Zero Draft |
SAP 1.2 CCSP Timeline |
|
Normal |
Sep 1, 2007 |
Oct 31, 2007 |
59 days ? |
59 days ? |
0 |
Solicit names for Peer Reviewers |
FSP Timeline |
|
Normal |
Sep 10, 2007 |
Nov 11, 2007 |
60 days ? |
60 days ? |
0 |
Deadlines
The following activities have to be completed within the next days:
Activities |
Group |
Responsible |
Prio |
Start |
Deadline |
Work |
Duration |
Complete |
Compose Zero Draft |
SAP 1.2 CCSP Timeline |
|
Normal |
Sep 1, 2007 |
Oct 31, 2007 |
59 days ? |
59 days ? |
0 |
Zero Draft Complete |
SAP 1.2 CCSP Timeline |
|
Normal |
Oct 31, 2007 |
Oct 31, 2007 |
|
0 hours |
0 |
|