skip navigational links United States Department of Labor
May 9, 2009        
DOL Home > OALJ Home > USDOL/OALJ Reporter
DOL Home USDOL/OALJ Reporter

A.S. McGAUGHAN CO., INC., WAB No. 92-17(WAB May 26, 1993)


CCASE: A.S. McGAUGHAN CO., INC. DDATE: 19930526 TTEXT: ~1 [1] WAGE APPEALS BOARD UNITED STATES DEPARTMENT OF LABOR WASHINGTON, D. C. In the Matter of: A.S. McGAUGHAN CO., INC. WAB Case No. 92-17 Prime Contractor With respect to subcontractor Gebhardt, Inc., and application of Davis-Bacon labor standards to General Wage Decision No. DC 88-1 to construction of dual purpose sedimentation basins at Blue Plains Wastewater Treatment Plant BEFORE: Charles E. Shearer, Jr., Chairman Ruth E. Peters, Member Anna Maria Farias, Member DATED: May 26, 1993 DECISION OF THE WAGE APPEALS BOARD This matter is before the Wage Appeals Board on the petition of prime contractor A.S. McGaughan Co., Inc. ("McGaughan"), "for the use and benefit" of second tier subcontractor Gebhardt, Inc. ("Gebhardt"), and Gebhardt, for review of a September 29, 1992 decision of the Acting Administrator of the Wage and Hour Division. The Board heard oral argument in this matter on May 4, 1991. Petitioners challenge the Acting Administrator determination that heavy construction wage rates, and not sewer and water wage rates, apply to work performed by Gebhardt. For the reasons stated below, the petition for review is denied. [1] ~2 [2] I. BACKGROUND Pursuant to a bid solicitation advertised on August 8, 1988, McGaughan was awarded a contract on November 16, 1988 with the Government of the District of Columbia, Department of Public Works ("DPW") to construct dual purpose sedimentation basins at the Blue Plains Wastewater Treatment Plant. The contract was subject to the requirements of the Davis-Bacon Act, as amended, 40 U.S.C.  276a et seq. McGaughan subcontracted with Parker-Kirlin Joint Venture, which subcontracted with Gebhardt for the furnishing and installation of a storm sewer, and related excavation and backfilling. The contract specifications contained the applicable wage determination, General Wage Decision DC 88-1 (Modification Nos. 1-12), which was incorporated as an addendum to the specifications. Wage Decision DC 88-1 provides building, heavy, highway, sewer and water wage rates for the Washington Metropolitan Area. The wage decision describes the four categories of construction as follows: BUILDING CONSTRUCTION PROJECTS (does not include single family homes and apartments up to and including four (4) stories), EXCLUDING INDEPENDENT CITY OF ALEXANDRIA; HEAVY CONSTRUCTION PROJECTS (does not include Sewer and Water Lines Construction Projects); HIGHWAY CONSTRUCTION PROJECTS in DISTRICT OF COLUMBIA ONLY; SEWER AND WATER LINES CONSTRUCTION PROJECTS IN DISTRICT OF COLUMBIA AND MONTGOMERY COUNTY, MARYLAND ONLY. Prior to award of the contract, the DPW determined that heavy construction rates should apply to all work under the contract. Special Provision No. 27 of the contract provides that "General Wage Decision No. 88-1 and Modifications 1-9 are bound herein and contain the specific applicable wage rates, which are Heavy Construction Rates." The record indicates that McGaughan was also advised of the applicability of heavy construction wage rates at the preconstruction conference. In September 1991, after an investigation of Gebhardt's performance on the contract, DPW found that $25,067.63 in back wages were owed because of Gebhardt's underpayment of the prevailing wage rates. Gebhardt had paid its employees the rates listed in General Wage Decision DC 88-1 for "Sewer and Water Lines Construction," rather than the rates listed for "Heavy Construction." Gebhardt then objected to application of heavy construction rates to its work under the contract, arguing that application of sewer and water wage [2] ~3 [3] rates was appropriate because the work involved small equipment and excavation to relatively shallow depths. In a final decision issued on September 29, 1992, the Acting Administrator agreed with DPW's determination that heavy construction wage rates were applicable to the entire contract, including the work done by Gebhardt. The Acting Administrator noted that contractors had been advised of DPW's determination regarding application of the heavy construction wage rates in the contract documents and at the preconstruction conference. She stated that DPW's determination was in accordance with All Agency Memoranda ("AAM") Nos. 130 and 131, regarding determination of "projects of a character similar" for wage determination purposes. The Acting Administrator further stated that even if the work done by Gebhardt could be considered to be water and sewer line construction, that work ($886,000) represented only 1.3% of the overall cost of the project ($66,423,000). AAM 130 and 131 explain, she stated, that "`multiple schedules are issued if the construction items are substantial in relation to project cost -- more than approximately 20%."' II. DISCUSSION In her September 29, 1992 decision, the Acting Administrator resolved the merits of this case and did not address whether Gebhardt had timely raised its contention that the water and sewer line rates were the appropriate rates for the work performed by Gebhardt's employees. Before this Board, however, counsel for the Acting Administrator leads off the argument that the Acting Administrator's decision should be affirmed with the contention that McGaughan has essentially made an untimely request for modification of wage rates in the applicable wage determination. Counsel notes that the solicitation contained the following provision: "General Wage Decision No. 88-1 and Modifications 1-9 are bound herein and contain the specific applicable wage rates, which are Heavy Construction Rates." With this unambiguous statement, counsel argues, both McGaughan and other bidders were on notice that only the heavy construction wage rates in WD No. 88-1 applied to the work performed on the project. Any questions about the applicability of heavy construction rates, or sewer and water line rates, should have been resolved before contract award, counsel argues, but McGaughan did not challenge the application of heavy rates until long after award of the contract. "Since McGaughan's request to change or modify the wage rates contained in the applicable wage determination was not made prior to the award of the contract," counsel concludes, "its request was clearly untimely under both Wage Appeals Board case law and the Department's regulations." Counsel's argument is similar to the argument made by the Acting Administrator in Utility Services, Inc., WAB Case No. 90-16 (July 31, 1991). The petitioner in that case argued the water and sewer line rates in the applicable [3] ~4 [4] wage determination, rather than the building construction rates in the same wage determination, were the appropriate rates for the utility work performed by the petitioner. Counsel for the Acting Administrator invoked Board decisions (e.g., Granite Builders, Inc., WAB Case No. 85-22 (Jan. 27, 1986)) and Department regulations (29 C.F.R. 1.6(c)(3)) in support of the argument that the petitioner's request for sewer and water line rates should be rejected because the request was made well after award of the prime contract and the utility subcontract. Upon consideration of the Acting Administrator's argument in Utility Services, Inc., the Board observed that the case did not involve a challenge to the substantive correctness of the wage rates and classifications in the applicable wage determination, but instead involved the issue of which rates in that wage determination applied to the work done by the petitioner. The Board added: Regardless of whether the Board precedent and the regulations cited by counsel for the Acting Administrator strictly apply to such a question, we think that counsel properly emphasized the responsibility of contractors to resolve questions of applicable wage rates before contract award. The exercise of that responsibility, however, presupposes that contractors have adequate notice that a question requiring resolution does exist. As in Utility Services, Inc., the instant case does not present a challenge to the rates and classifications in the applicable wage determination, but rather involves a question of which of the rates in that wage determination -- the heavy rates or the water and sewer line rates -- are applicable to the work performed by Gebhardt's employees. Unlike Utility Services, Inc., however, it is patent in the instant case that the contractors had ample notice -- in the form of the above-cited provision in the solicitation and the contract -- that only heavy construction rates applied to the work performed on the project. Any question about the application of those rates should have been raised prior to award of the contract. Given the failure to raise any such issue until well after contract award, the Board concludes that the instant request for application of water and sewer line rates to the work performed by Gebhardt's employees must be regarded as untimely. To rule otherwise would be unfair to other bidders who also received clear notice that heavy construction rates were applicable to work performed on the project. Cf. Dairy Development, Ltd., WAB Case No. 88-35 (Aug. 24, 1990) (discussing the policy set forth in Board case law and Department regulations regarding the timeliness of substantive challenges to wage determinations, the Board explained that "[m]anifest injustice to bidders would result if the successful bidder on a project could challenge his contract's wage determination rates after all other competitors were excluded from participation." [4] ~5 [5] Accordingly, the petition for review is denied; the Acting Administrator's decision is affirmed. BY ORDER OF THE BOARD: Charles E. Shearer, Jr., Chairman Ruth E. Peters, Member Anna Maria Farias, Member Gerald F. Krizan, Esq. Executive Secretary [5]



Phone Numbers