skip navigational links United States Department of Labor
May 9, 2009        
DOL Home > OALJ Home > USDOL/OALJ Reporter
DOL Home USDOL/OALJ Reporter

BALL, BALL AND BROSAMER, INC., WAB No. 90-18 (WAB Nov. 29, 1990)


CCASE: BALL, BALL AND BROSAMER, INC. DDATE: 19901129 TTEXT: ~1 [1] WAGE APPEALS BOARD UNITED STATES DEPARTMENT OF LABOR WASHINGTON, D.C. In the Matter of Ball, Ball and Brosamer, Inc., WAB Case No. 90-18 Prime Contractor Red Rock Products, Inc., Subcontractor BEFORE: Jackson M. Andrews, Chairman Ruth E. Peters, Member Stuart Rothman, Member, Concurring Separately DATED: November 29, 1990 DECISION OF THE WAGE APPEALS BOARD This case is before the Wage Appeals Board on the petition of Ball, Ball and Brosamer, Inc. ("Ball" or "Petitioner"), seeking review of a decision of the Acting Administrator of the Wage and Hour Division dated February 6, 1990. The Acting Administrator, upon an investigation by the Wage and Hour Division, determined that Red Rock Products, Inc. ("Red Rock") was a subcontractor on a federal construction project, and that Red Rock had failed to pay its employees pursuant to the prevailing wage requirements of the Davis-Bacon Act (40 U.S.C. [sec] 276a et seq.) and the overtime pay requirements of the Contract Work Hours Safety Standards Act ("CWHSSA") (40 U.S.C. [sec] 327 et seq.). The Wage and Hour Division determined that Red Rock owed $60,976.71 in back wages. [1] ~2 [2] Petitioner, the prime contractor, alleges that the Davis- Bacon Act is inapplicable here because Red Rock did not perform on the site of work and was a materialman. For the reasons stated below, the Board denies the petition for review. I. BACKGROUND Petitioner is a general construction contractor, specializing in earthwork, road work, dam construction and canal construction. Petitioner, a California corporation, has its principal place of business in California (Tab B, p. 3; Tab E [par] 2). On March 29, 1985 the Bureau of Reclamation of the U.S. Department of the Interior ("BOR") awarded a $43.5 million contract (Contract No. 5-CC-30-02830) to Petitioner to perform construction work at Tucson Aqueduct Reach 1B and Reach 2, Tucson Division, Central Arizona Project ("CAP") (Tab B, p.3). On September 20, 1985, BOR awarded Petitioner a contract valued at $14,557,920.90 (Contact No. 5-CC-30-03560) to perform earthwork and to construct 13 miles of concrete lined canal, earth dikes and other structures at Tucson Aqueduct Reach 3 of the CAP project (Tab A, p. 3; Tab B, p. 3). The contracts were subject to the requirements of the Davis-Bacon Act and the CWHSSA, Department of Labor regulations, and the prevailing rate classifications and basic hourly rates specified in Wage Determination No. AZ 84-5005, dated March 8, 1984, as modified through Modification No. 5, dated November 9, 1984 (Tab A, pp. 13-19; Tab D, p. 1; Tab M, p. 1). Petitioner, according to Ball, issued a purchase order on December 14, 1985, for Red Rock to provide sand, gravel, concrete [2] ~3 [3] and other aggregates needed by Petitioner to complete its work on the Reach 3 project (Tab E, [par] 4). According to the record Red Rock, an Arizona-based company, performed the agreement between January and March 1986 (Tab I; Tab D, p. 2). In addition to its responsibilities regarding the Ball contracts, Red Rock also had obligations to fulfill with Bechtel Constructors Corporation, a prime contractor on another CAP construction contract (No. 5-CC- 30-02770, dated April 5, 1985) (Tab D, p. 1; Tab M, p.1). Red Rock established a sand and gravel pit which it had subleased from Western Rock Products, Inc., and set up a portable batch plant (Tab G; Tab D, p. 1; Tab M, p. 1). (FOOTNOTE 1) Red Rock commenced its operations about November 1985, and began removing material from the pit in January 1986 (Tab I; Tab D, p. 2; Tab M, p. 2). (FOOTNOTE 2) The record contains two descriptions of the distance of the pit and batch plant from the construction areas. The Wage and Hour investigation determined that the pit and batch plant were situated about 2 to 15 miles from the construction areas (Tab T, p. 2). Regarding Ball's Reach 3 project, Petitioner states that the plant "is approximately 5 miles away from the closest portion of the right of way for the Tucson Reach 3 project, and about 12 miles from the middle of Reach 3," and about 19 miles from the farthest point of the work (Statement of Reasons for Appeal at pp. 3, 10; Tab E, [par] 4). [3] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ (FOOTNOTE 1) Western had leased the pit from the State of Arizona in about March 1985 (Tab G; Tab H; Pet. App. 17-25). (FOOTNOTE 2) According to the record, Red Rock went out of business during March 1986, and another firm began providing concrete to the prime contractors (Tab D, p. 2; Tab F). [3] ~4 [4] The BOR project officer for Arizona and the Wage and Hour Director of Enforcement in Arizona met on December 23, 1985 and agreed to determine whether Davis-Bacon Act requirements applied to Red Rock (Tab B, p. 3). Wage and Hour initiated an investigation of Red Rock in March 1986, and sought payroll records from Ball and Red Rock (Tab B, p. 3; Tab D, p.1; Tab M, p. 1). Ball's office manager said that the matter would be discussed with the Director of Industrial Relations at the firm's home office in Danville, California (Tab B, p. 3). Red Rock denied that it was subject to the Davis-Bacon Act and the CWHSSA, and failed to submit weekly certified payrolls, refused to make its payroll records available for inspection, and refused to permit interviews of employees (Tab D, pp. 1, 3; Tab M, p. 1). Red Rock claimed that the firm was established for commercial concrete sales in the area (Tab D, p. 1; Tab M, p. 1). At the March 10, 1986 opening conference, Charles E. Martin, secretary- treasurer of Red Rock, produced an undated "General Marketing Survey" (Tab J) which he claimed was a basis for establishing a commercial concrete plant in such a remote area (Tab D, p. 1; Tab M, p. 1; Tab J). When questioned, however, Martin said the survey was conducted in January 1986, which is the same month that Red Rock began removing materials from the pit, and a month or two after it commenced operations in about November 1985 (Tab D, p. 2; Tab M, p. 2). Following the March 1986 conference Wage and Hour, in an April 4, 1986 letter, noted that Red Rock had failed to comply with the request for records. Wage and Hour requested that BOR notify Red Rock in writing to produce the records (Tab K). [4] ~5 [5] Red Rock went out of business in March 1986, apparently because of financial difficulties (Tab L; Tab D, p. 2, Tab M, p. 2). The defunct firm made its records available on July 13, 1988, after a phone call to Martin (Tab D, p. 1; Tab M, p. 1). Red Rock claimed that the firm was neither a contractor or subcontractor to the prime contractors, and was a material supply vendor (Tab D, p.1; Tab M, p. 1). As a result of its investigation, Wage and Hour concluded that both the operation of the pit and the batch plant were covered by the Davis-Bacon Act. Wage and Hour further concluded that Red Rock had paid its employees less than the required rates (Tab D). Wage and Hour determined that Red Rock paid its employees time and a half their regular hourly rates of pay for all hours worked in excess of 40 per week. However, Wage and Hour concluded that violations of the overtime pay requirements of the CWHSSA had occurred because Red Rock had paid less than the required prevailing basic hourly rates (Tab M). Wage and Hour allocated the amount of back wages owed on the government contracts based on the amount of concrete Ball and Bechtel purchased from Red Rock. Based on information provided by Ball and Bechtel, Wage and Hour concluded that Ball had purchased 4,115 cubic yards (or 70.16% of Red Rock's production) for its two contracts, Bechtel had purchased 1,500 cubic yards (or 25.58% of Red Rock's production), and that the firm produced 250 cubic yards (or 4.26%) for non-Government accounts (Tab D, p. 2; Tab M, p. 3). Regarding the amount of unpaid wages owed, Wage and Hour concluded that for the Ball work, Red Rock owed $57,782.44 to 23 employees [5] ~6 [6] for Davis-Bacon violations (Tab D, p. 3) and $3,194.27 to 17 employees for overtime pay violations (Tab M, p. 3), for a total of $60,976.71. Wage and Hour, by letter dated July 28, 1988, advised the BOR contracting officer that the investigation had disclosed violations, and requested that BOR withhold $30,000 on the Ball contract payment pending final resolution (Tab N). BOR, by letter dated August 8, 1998, informed Ball that it was retaining $30,000 from future progress payments, and would not release the funds until authorized to do so by the Department of Labor at the conclusion of the Department's investigation (Pet. App. 37a). Wage and Hour amended the withholding request to $60,976.71 by letter dated November 22, 1988 (Tab O). BOR, by letter to Ball dated March 12, 1990, stated that the amount had been withheld (Tab P). By letter dated August 19, 1988, Wage and Hour transmitted to Ball copies of the Wage Transcription and Computation Sheet, Form WH-55, which listed the amounts due employees (Tab Q). Wage and Hour informed Ball that the back wages due could be paid by check either to the employees or to Wage and Hour (Tab Q). Ball responded to Wage and Hour by letter dated September 16, 1988, in which Ball denied that it was liable for the back wages owed to the former Red Rock employees. (Pet. App. 42-43). Ball requested review of the matter pursuant to 29 C.F.R. 5.11 (Pet. App. 42). In addition, by letter dated September 8, 1988, Ball filed a claim for $60,976.71 with BOR. By letter dated November 1, 1988, BOR provided Ball with an "executed copy of Modification No. 026," the final decision of the contracting officer regarding the Red [6] ~7 [7] Rock matter (Tab B). The decision noted the contractor's claim in the amount of $60,976.71, and Ball's statement that they were not affiliated with Red Rock and that "[t]he purchase of materials from this off-site vendor constitutes the only relation between us and this entity" (Tab B, p. 2). The decision added that Ball's claim involved an investigation by the Department of Labor, a matter not within the jurisdiction of BOR (Tab B, p. 4). Accordingly, the decision denied Ball's claim (Tab B, p. 4). Ball filed a complaint under the Contract Disputes Act in the United States Claims Court on October 18, 1989 (Tab E). The request for relief included, among other things, judgment in the amount of $60,976.71, release of the amount being withheld for payment of back wages and interest on the amount being withheld (Tab E, p. 5). The Department of Justice ("DOJ") moved to suspend the proceedings pending a final decision by the Department of Labor (Tab R), and Ball opposed the motion (Tab S). Before the court ruled on the motion the Acting Administrator, by letter to Red Rock dated February 6, 1990, affirmed the findings of the compliance officer (Tab T, p. 3). The Acting Administrator noted that Red Rock operated both a pit and a batch plant, and that the record indicates that materials produced at the pit were used exclusively by the batch plant (Tab T, p. 2). Furthermore, the Acting Administrator stated, "approximately 96 percent (96%) of the materials produced at the batch plant was used as construction materials on the [Ball and Bechtel] contracts, which were segments of the Central Arizona Project. Moreover, the record indicates that the above-mentioned facilities were located at distances [7] ~8 [8] ranging approximately from two to 15 miles from areas where construction work was being performed on the above contracts" (Tab T, p. 2). The Acting Administrator further stated that covered contractors must pay Davis-Bacon prevailing wages to all the laborers and mechanics employed on the site of work (Tab T, p. 2). The Acting Administrator explained that under 29 C.F.R. 5.2(1)(2), "the 'site of work' generally includes pits and batch plants which are opened for the purpose of fulfilling contract requirements; are located close enough to the actual construction site that it would be reasonable to include them; and are dedicated exclusively, or nearly so, to the performance of a covered project" (Tab T, p. 2). The Acting Administrator concluded that Red Rock employees "who performed work at the pit and batch plant are subject to the applicable prevailing wage rates and overtime requirements" (Tab T, p. 2). The Acting Administrator stated that since there did not appear to be a dispute over relevant facts, her letter constituted a final ruling under 29 C.F.R. 5.11(c)(1) (Tab T, p. 3). If Red Rock or the prime contractors believed relevant facts were in dispute, the Acting Administrator stated, they should inform her within 30 days, for purposes of referring the matter to the Chief Administrative Law Judge for a hearing (Tab T, p. 3). If the facts are not contested, the Acting Administrator added, Red Rock and the prime contractors could file a petition for review with the Wage Appeals Board (Tab T, p. 3). [8] ~9 [9] The Acting Administrator also sent the February 6, 1990 decision letter to Ball (Pet. App. 48-49). Ball filed a petition for review with the Board by letter dated March 8, 1990, and requested that its statement in support of the petition be postponed until the Claims Court ruled on DOJ's motion to suspend the court proceedings (Tab W). The court granted DOJ's motion by order filed April 11, 1990 (Pet. App. 51). II. THE PARTIES' CONTENTIONS Petitioner claims that the Red Rock plant was not "directly upon the site of the work" within the meaning of the Davis-Bacon Act, and thus was not covered by the Act (Statement of Reasons for Appeal at p. 14). The Department of Labor's regulations, Ball alleges, "essentially ignore[] the portion of the statutory phrase 'directly upon' in defining the site of work" (Statement, at p. 10). Ball also claims that under the terms of the Act, Red Rock is a materialman and not a subcontractor (Id. at p. 15). In addition, Petitioner claims that the Department of Labor's administrative decision is barred by the two-year statute of limitations under the Portal-to-Portal Act. Finally, Ball "maintains its position that the Department of Labor is not authorized to adjudicate and decide disputes such as the one here in issue" (Id. at p. 5), and that the "sole authority of the Board . . . is to advise the contracting officer" (Id. at p. 8). The Solicitor, on behalf of the Administrator, states that under Reorganization Plan No. 14 of 1950, the Department of Labor is the appropriate administrative agency to issue an authoritative [9] ~10 [10] ruling on whether Red Rock was covered by the Davis-Bacon Act (Response at p. 12). Under the Department of Labor's regulations and prior decisions of the Board, the Solicitor states, Red Rock meets the requirements for coverage both by the proximity of the pit and the batch plant to the site of construction (Id. at p. 18), and by virtue of the fact that the pit and batch plant "were established and dedicated almost exclusively to meet the contract requirements of Ball and the other Federal construction contractor on the CAP project" (Id. at p. 19). Petitioner, the Solicitor argues, makes no effort to demonstrate that the facts in this case are different from those in other cases where the Board has found that the work in question was performed at the "site of work," but instead Petitioner "merely asserts that those cases were wrongly decided" (Id. at p. 19). Furthermore, the Solicitor argues, under Department of Labor regulations and Board decisions Red Rock was not a materialman (Id. at pp. 20-21). Finally, the Solicitor argues that under the Board's consistent precedent, administrative proceedings under the Davis-Bacon Act are not barred by the Portal-to-Portal Act (Id. at pp. 22-23). III. DISCUSSION A. The requirement to pay the prevailing wage to laborers and mechanics "employed directly upon the site of the work" Our analysis of whether the work at Red Rock's pit and batch plant was subject to Davis-Bacon prevailing wage requirements begins with an examination of the relevant statutory and regulatory provisions. The Davis-Bacon Act provides, at 40 U.S.C. [sec] 276a, [10] ~11 [11] that "the contractor or his subcontractor shall pay all laborers and mechanics employed directly upon the site of the work. . . ." The Act further provides, at 40 U.S.C. [sec] 276a-1, for sanctions if laborers or mechanics employed "directly upon the site of the work covered by the contract" are not paid according to the prevailing wage rates determined by the Secretary of Labor. The regulations of the Secretary of Labor implementing the Davis-Bacon Act also address the meaning of the term "site of the work" as that term is used in the Act. These regulations (29 C.F.R. 5.2(1)) provide, in pertinent part: (1) The "site of the work" is limited to the physical place or places where the construction called for in the contract will remain when work on it has been completed and, as discussed in paragraph (1)(2) of this section, other adjacent or nearby property used by the contractor or subcontractor in such construction which can reasonably be said to be included in the "site." (2) Except as provided in paragraph (1)(3) of this section, fabrication plants, mobile factories, batch plants, borrow pits, job headquarters, tool yards, etc., are part of the "site of the work" provided they are dedicated exclusively, or nearly so, to performance of the contract or project, and are so located in proximity to the actual construction location that it would be reasonable to include them. (3) Not included in the "site of the work" are permanent home offices, branch plant establishments, fabrication plants, and tool yards of a contractor or subcontractor whose locations and continuance in operation are determined wholly without regard to a particular Federal or federally assisted contract or project. In addition, fabrication plants, batch plants, borrow pits, job headquarters, tool yards, etc., of a commercial supplier or materialman which are established by a supplier of materials for the project before opening of bids, and not on the project site, are not included in the "site of the work". Such permanent, previously established facilities are not a part of the "site of the work", even where the operations for a period of time may be dedicated exclusively, or nearly so, to the performance of a contract. [11] ~12 [12] The Acting Administrator concluded that Red Rock employees who performed work at the Red Rock pit and batch plant were subject to the prevailing wage requirements of the Davis-Bacon Act and the overtime requirements of the CWHSSA. Our review of the record in this case leads the Board to conclude that the decision of the Acting Administrator in this case is a straightforward application of the pertinent statutory and regulatory provisions, is consistent with Board precedent, and should be affirmed. Under the Secretary's regulations (29 C.F.R. 5.2(1)) pits, batch plants and other facilities are included within "the site of the work" providing that the facilities in question meet two requirements: (1) the facilities "are dedicated exclusively or nearly so to performance of the contract or project"; and (2) the facilities "are so located in proximity to the actual construction location that it would be reasonable to include them." Likewise, the Board has explained that its case precedent has utilized "an exclusive or nearly exclusive use or dedication test, and a geographical test for covering fabrication plants, batch plants, and borrow or gravel pits located on adjacent or nearby property to a covered construction site." ATCO Construction, Inc., WAB Case No. 86-1 (Aug. 22, 1986), at pp. 3, 5, and cases cited therein. The record in this case shows that the Red Rock pit and batch plant meet both the functional and geographical tests for coverage. First, the operations at the pit and batch plant meet the functional requirement set forth in the regulations and Board cases. As noted at p. 3, supra, Red Rock began removing materials from the pit in January 1986, months after award of the prime [12] ~13 [13] contracts to Ball and Bechtel. No material was being excavated from the pit prior to January 1986. Furthermore, Red Rock set up a portable concrete batch plant, and all the materials from the pit were used at the batch plant. Information provided by Ball and Bechtel indicated that about 96% of Red Rock's concrete production was provided to Ball and Bechtel for use on their CAP contracts -- 4,115 cubic yards for Ball and 1,500 cubic yards for Bechtel, compared with only 250 yards for non-Government accounts. Given these factual circumstances, the Board is satisfied that Red Rock's pit and batch plant were established and dedicated nearly exclusively to meet the contract requirements of the two prime contractors. The Red Rock pit and batch plant also meet the geographical test, in that they were "so located in proximity to the actual construction location that it would be reasonable to include them [in the site of the work]." 29 C.F.R. 5.2(1)(2). As the Acting Administrator noted (Tab T, p. 2), the record indicates that the facilities were located about 2-15 miles from the construction areas. Given the nature of the construction work on the CAP project (for example, the Reach 3 contract awarded to Ball was for performing earthwork and constructing 13 miles of concrete lined canal, earth dikes and other structures) and the proximity of the facilities to the construction areas, it is entirely reasonable to include them within the "site of the work." See, e.g., United Construction Company, Inc., WAB Case No. 82-10 (Jan. 14, 1983), at p. 7 (given the physical layout of the project, "the Board does not have difficulty finding that the various distances (ranging from [13] ~14 [14] 1.8 miles to 55 miles) between the batch plant and the locations of the individual construction sites" are within the site of work). (FOOTNOTE 3) Apparently conceding that the Acting Administrator's decision is within the contours of the Secretary's regulation and Board case precedent, Petitioner argues (Statement, pp. 11, 13) that the line of Board cases applying the functional and geographical tests were wrongly decided, and that the Secretary's regulation setting forth these same tests "is so disparate in relationship to the clear and conclusive phrasing of the statute that the regulation must be declared to be ultra vires." In this regard, Petitioner notes (Statement, p. 14) the D.C. Circuit's remand to the district court in Building & Construction Trades Dep't, AFL-CIO v. U.S. Dep't of Labor Wage Appeals Board, 829 F.2d 1188 (D.C. Cir. 1987) for resolution of the issue whether this regulation is consistent with the statutory term, "directly upon the site of the work." Petitioner can take no comfort from the district court's decision on remand, however, for the U.S. District Court for the District of Columbia upheld the Secretary's site of work regulation as "entirely consistent with the statutory objective of the Davis- [14] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ (FOOTNOTE 3) As the Solicitor notes (Response, at p. 18 n.6), Petitioner did not dispute the facts as set forth in the Acting Administrator's decision, although Petitioner was advised of its right to do so (see p. 8, supra), but now states that regarding the Reach 3 project the facilities were about 5 miles from the closest point of the right of way for the project and about 19 miles from the farthest point of the work (see p. 3, supra). We note that the Board is, under its governing regulations, "an essentially appellate agency." 29 C.F.R. 7.1(e). However, these very minor differences raised by Ball, even if accepted into the record at this late date, would not affect the Board's determination that the Red Rock pit and batch plant meet the geographical test for inclusion within the site of work. [14] ~15 [15] Bacon and related Acts." Building & Construction Trades Dep't, AFL-CIO v. McLaughlin, C.A. No. 84-0705 (WBB) (Aug. 17, 1990), slip op. at p. 8. Petitioner also relies upon a 1963 Comptroller General decision (43 Comp. Gen. 84) as support for Petitioner's argument that the Department of Labor's site of work interpretation is "ultra vires." However, we direct Petitioner's attention to the Board's decision in Mayfair Construction Company, WAB Case No. 81- 16 (April 16, 1983), wherein the Board noted (at p. 4) that the Comptroller has subsequently agreed that coverage of the Act " 'could extend to offsite construction activities which are dedicated to the performance of the contract and are located in close proximity to the actual construction site.' " In sum, the Board finds no basis in Petitioner's argument for abandoning the long-standing use of the functional and geographical tests for assessing whether facilities are within the "site of the work." Petitioner additionally argues (Statement, at pp. 14-15) that Red Rock was a materialman, and not a subcontractor. However, the Board has explained that under its precedent, when a facility "is located at or near the site of a federally financed construction site for the exclusive or nearly exclusive purpose of fulfilling the contract's material requirements, the operator of such a facility has in effect undertaken the performance of a part of the contract and as a result is a subcontractor working on the site for the purpose of the prevailing wage requirements." Ontario Pipeline, Inc., and Farmington Concrete Products, Inc., WAB Case [15] ~ [16] Nos. 81-12 & 81-13 (Jan. 23, 1985) at pp. 4-5, 6 and cases cited therein at pp. 4-5. (FOOTNOTE 4) As discussed at pp. 12-14, supra, the record here indicates that Red Rock's pit and batch plant were situated proximately to the CAP construction areas and were dedicated nearly exclusively to the Ball and Bechtel CAP contracts "to the general exclusion of other contracts in the area." Ontario Pipeline, supra, at p. 6. Indeed, only about 4% of the Red Rock batch plant production went to non-Government accounts. The record indicates that Red Rock claimed during the investigation that the firm was set up for commercial concrete sales. Red Rock's secretary-treasurer produced a "General Marketing Survey" and claimed that this undated survey was a basis for establishing a commercial concrete batch plant in that remote area. However, the Red Rock official also stated that the survey was conducted in January 1986 -- the same month that Red Rock began removing materials from the pit and a month or two after Red Rock commenced operations in November 1985. Given these circumstances, the Board finds no infirmity in the Wage and Hour investigation's determination (Tab D, p. 2; Tab M, p. 2) that the survey was apparently conducted to assess whether commercial concrete sales could sustain the business in the event that Red Rock lost Ball and Bechtel's CAP project business. Furthermore, Red Rock did go out of business in March 1986, [16] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ (FOOTNOTE 4) The Board notes that the Davis-Bacon regulation defining the term "construction" explicitly includes the "furnishing of materials . . . on the site of the building or work . . . by persons employed by the contractor or subcontractor." 29 C.F.R. 5.2(j). [16] ~17 [17] apparently because the two prime contractors discontinued using Red Rock's production (Tab D, p. 2; Tab M, p. 2). Based on the circumstances present in this case, and consistent with Board precedent, the Board concludes that Red Rock's status was that of subcontractor. (FOOTNOTE 5) See, e.g., United Construction, supra, at p. 8 (the Board has considered and rejected the notion that a company's operations are not covered by the Davis-Bacon Act simply because of the company's hopes for future sales). B. The Department of Labor's administrative action is not barred by the Portal-to-Portal Act Petitioner additionally argues that the Department of Labor's administrative action regarding the liability of the prime and subcontractor for back wages is barred by the 2-year statute of limitations of the Portal-to-Portal Act (29 U.S.C. [sec] 255). Resolution of this contention is squarely controlled by Board precedent, since the Board has consistently held that the Portal- to-Portal Act does not apply to administrative proceedings under the Davis-Bacon Act. See, e.g., Martell Construction Co., Inc., WAB Case No. 86-26 (July 10, 1987), at pp. 2-3 and cases cited therein. In so holding, the Board explained in Martell, the Board has followed the Supreme Court's ruling in Unexcelled Chemical Corp. v. United States, 345 U.S. 59 (1953), that an admin- istrative [17] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ (FOOTNOTE 5) The responsibility of Ball, as prime contractor, for the unpaid wages due to the employees of subcontractor Red Rock is clear under Board precedent. As the Board has explained, "the Davis-Bacon Act itself creates a contractual obligation on the part of the prime contractor to pay the sums which its subcontractor owes to the subcontractor's employees." Northern Colorado Constructors, Ltd., WAB Case No. 86-31 (Dec. 14, 1987).[17] ~18 [18] proceeding is not an "action" within the meaning of the statute of limitations under the Portal-to-Portal Act. See also Glenn Electric Co. v. Donovan, 755 F.2d 1028, 1033 n.7 (3d Cir. 1985). Based on this precedent, the Board rejects Ball's contention that the Portal-to-Portal Act's statute of limitations applies in this case. C. The Department of Labor's authority to resolve the issue whether Red Rock's operations were covered by the Davis-Bacon Act Finally, the Board rejects Ball's contention (Statement, at pp. 5-8) that the Department of Labor lacks authority to rule dispositively on the Davis-Bacon Act coverage issues involved in this matter. We agree with the Solicitor that Petitioner's attempt to cast this matter as a "jurisdictional" dispute is unavailing. The contracting agency (BOR) agreed to the withholding requested by the Department of Labor, and stated that the issue of the Ball/Red Rock relationship was a matter to be addressed by the Department of Labor (Tab B, p. 4). The Department of Labor's authority to resolve coverage issues under the Davis-Bacon Act and the Related Acts is provided by Reorganization Plan No. 14 of 1950 (5 U.S.C. App.). With the aim of assuring uniformity in enforcement of these labor standards provisions, the Reorganization Plan explicitly vests the Secretary with the authority to "prescribe appropriate standards, regulations, and procedures" to be observed by federal agencies, and to "cause to be made by the Department of Labor, such investigations, with respect to compliance and enforcement of such labor standards, as he deems desirable." Under this grant of authority of 40 years' standing the Department of Labor has issued [18] ~19 [19] regulations addressing coverage and other matters. In addition, the Board has often ruled on coverage issues such as those presented in this case, and has affirmed the Department of Labor's authority under the Reorganization Plan to rule dispositively on Davis-Bacon matters. See generally United Construction, supra, at p. 6; Arbor Hill Rehabilitation Project, WAB Case No. 87-4 (Nov. 3, 1987), at pp. 20-22 (Bramow, concurring) (regarding final authority of the Department of Labor under the Reorganization Plan to interpret the labor standards provisions of the Related Acts). To accept Ball's contention here that the Secretary of Labor does not have authority to rule dispositively on questions of coverage under the Davis-Bacon Act "would defeat the primary objective of the Reorganization Plan, i.e., the protection of the workers which varied from agency to agency [before the Reorganization Plan]." Arbor Hill, supra, at p. 21. Accordingly, the Board rejects Ball's contention that the Department of Labor is without authority to decide the coverage issues presented in this case. The decision of the Acting Administrator in her letter of February 6, 1990 is affirmed. The petition for review is denied. MEMBER ROTHMAN, CONCURRING I find myself in agreement with the reasoning of the majority decision. I write separately because in my view it is necessary to reaffirm a Board rule which has been in effect since 1969 with respect to newly opened gravel pits, other kinds of borrow pits, and batch plants. This rule establishes a prima facie case when [19] ~20 [20 the Administrator demonstrates that such facilities have been newly opened on a temporary basis with temporary equipment in proximity to highway, river improvements, lock construction, dam construction, canal irrigation and similar projects. The burden then shifts to the employing contractor to show by relevant and persuasive evidence that the work performed is not construction site work within the requirements of the Davis-Bacon and Davis- Bacon Related Acts. By defining when the Administrator makes a "prima facie" case of Davis-Bacon coverage, the gravel pit and batching plant segments of the construction industry are put on notice that should an operator contend that it has engaged in nothing more than the normal commercial materialman's operations the burden will be upon such claimant to prove it. In Ross Brothers Construction, Inc., WAB Case No. 87-36 (Nov. 21, 1988) Ross Brothers, the prime contractor, was awarded a highway grading and paving contract in Oregon. Aggregate was supplied by a Roseburg, Oregon company, Umpqua, from a sand and gravel bar in the Umpqua River, about 24 miles from the highway project. Umpqua obtained a temporary permit from the Oregon State Lands Division to mine, crush and remove aggregate from the bar. The aggregate was trucked from a portable crushing plant to a storage yard about a half mile from the highway project. In Ross Brothers, the Board cited with continuing approval Big Six, Inc., WAB Case No. 75-3 (July 21, 1975) with regard to a batch plant operation: . . . [T]he Board believes [] that in the case of an established commercial batching plant, it is not expected when work is awarded that the prime contractor will do [20] ~21 [21] the work to provide the material that normally comes from such sources. It is for this reason, too, the established commercial quarry or batching plat is said to be a "materialman". In such cases the established commercial operator continues to do its own thing in its own same way at the same place. But where the prime contractor must do the work with his own forces because no commercial operator is established and ready to perform, another contractor who takes on a part of the contractor's obligation to do this becomes subject to the Davis-Bacon Act in the same way. Big Six, Inc., supra, at p. 11. Further, in Ross Brothers, supra, at p. 4, the Board referred with approval to its decision in T. L. James, WAB Case No. 69-2 (Aug. 13, 1969): In T. L. James [citation omitted] one of the earlier decisions of the Wage Appeals Board, the Board stated at pp. 5 & 6, in a case that also dealt with a borrow pit for a highway contractor: . . . based upon experience in the construction industry where but for the contemplated construction of a highway project in the locality, borrow pits or waste areas would not be opened, the opening of such pits or areas primarily in and substantially devoted to the prosecution of the highway work will establish a "prima facie" case that the work performed in connection with the borrow pits or waste areas is a part of the construction activity of the project, and the employees who do the work are entitled to the same protection accorded the construction workers elsewhere on the project. . . . In another Board decision, Sweet Home Stone Company, WAB Case No. 75-01 and -02 (Aug. 14, 1975), the prime contractor for a river and dam improvement project on the Arkansas River in Oklahoma contracted with Sweet Home, an established Oklahoma commercial quarry operator to supply stone. Sweet Home opened three new or defunct quarries in proximity to the project. It made no sales in the public market, closing the quarries upon completion of its [21] ~22 [22] contract. The Board held that when a quarry is opened and becomes devoted exclusively to fulfilling the material requirements of a Davis-Bacon project the supplying contractor is considered to have undertaken a part of the construction work of the prime contract itself and is a subcontractor for purposes of Davis-Bacon Act coverage. The Board's three lead cases in gravel pit, borrow pit, or batch plant cases have been T. L. James, Big Six, and Sweet Home. Together with the more recent decisions cited in the Board's decision, I would reaffirm the "but for" rule announced in T. L. James which establishes a "prima facie" case for Davis-Bacon Act coverage in the case of newly opened temporary facilities of this kind in the proximate vicinity of the construction project to be served. An operator that opens such a facility should have every opportunity and is not precluded from showing that under the circumstances of its operations the performance of its contract to supply the project with materials is that of and should be deemed to be the performance of a materialman, but it should be aware from the beginning of the undertaking that the burden will be upon it to do so and it can and should determine the nature of its operation accordingly. For the factual considerations set forth in the Board's opinion, Ball, Ball & Brosamer and Red Rock Construction Co. have not met the burden of relevant and persuasive evidence to show that [22] ~23 [23] Red Rock was a materialman and not a subcontractor. For these reasons I concur in the Board Order. BY ORDER OF THE BOARD: Gerald F. Krizan, Esq. Executive Secretary [23]



Phone Numbers