skip navigational links United States Department of Labor
May 9, 2009        
DOL Home > OALJ Home > USDOL/OALJ Reporter
DOL Home USDOL/OALJ Reporter

SWANSON'S GLASS, WAB No. 89-20 (WAB Apr. 29, 1991)


CCASE: SWANSON'S GLASS DDATE: 19910429 TTEXT: ~1 [1] WAGE APPEALS BOARD UNITED STATES DEPARTMENT OF LABOR WASHINGTON, D. C. In the Matter of: SWANSON'S GLASS Des Moines, Iowa WAB Case No. 89-20 Wage Decision 86-IA-1095 BEFORE: Charles E. Shearer, Jr., Chairman Ruth E. Peters, Member Patrick J. O'Brien, Member DATED: April 29, 1991 DECISION OF THE WAGE APPEALS BOARD This case is before the Wage Appeals Board on the petition of Swanson's Glass ("Petitioner"), for review of a June 13, 1989 final ruling by the Administrator of the Wage and Hour Division denying Petitioner's request for addition of a "glazier" classification to a wage determination. For the reasons stated below, the Board denies the petition for review. I. BACKGROUND Swanson's Glass entered into a subcontract on November 17, 1986 with M.A. Mortenson Company, prime contractor on a contract with the Environmental Protection Agency for construction of a waste water treatment plant in Des Moines, Iowa. The subcontract between Petitioner and the prime contractor was for installation of doors, windows and glass. Both the prime contract and the subcontract were subject to the Davis-Bacon Act (40 U.S.C. [sec] 276a et seq.), and the Contract Work Hours and Safety Standards Act ("CWHSSA") (40 U.S.C. [sec] 327 et seq.), as well as Wage Decision No. 86-IA-0195. That wage determination did not contain a wage rate for glaziers. In October 1987, Petitioner submitted to the Iowa Department of Natural Resources ("DNR") a Request for Authorization of Additional Classifications and [1] ~2 [2] Rates. Petitioner requested the addition of a glazier classification to the wage determination at a wage rate of $9 per hour plus 6.62% in fringe benefits. On October 15, 1987, DNR notified the City of Des Moines that the requested rate was to be used on the project, subject to the approval of the Wage and Hour Division of the U.S. Department of Labor. DNR also submitted the request to the Wage and Hour Division on October 15. The Wage and Hour Division had no record of receiving the request, and the State of Iowa renewed the request in July 1988. The Wage and Hour Division denied the request for the additional classification on November 16, 1988, on the basis that the proposed rate did not bear a reasonable relationship to the wage determination as required by 29 C.F.R. 5.5(a)(1)(ii)(A)(3), and that the request did not reflect the concurrence of the employees, as required by 29 C.F.R. 5.5.(a)(1)(ii)(B). The State of Iowa requested reconsideration of the Wage and Hour ruling on January 19, 1989. The request included five "Wage Acknowledgement Forms" which had been signed by employees on the project and that stated that the employees agreed to be paid at $9 per hour plus 6.6% in fringe benefits for their work as glaziers. On June 13, 1989, the Administrator issued a final decision affirming the previous denial of the request for the additional glazier classification. The Administrator stated that the "Wage Acknowledgment Forms" were a sufficient demonstration of the employees' concurrence with the additional classification. However, the Administrator stated, "no information has been submitted regarding the conformability of the proposed wage rate." II. DISCUSSION On review of the record in this case, the Board concludes that the Administrator's denial of the request for the additional glazier classification should be affirmed. The regulations governing conformance procedures provide, at 29 C.F.R. 5.5(a)(1)(ii)(A) that "[t]he contracting officer shall require that any class of laborers or mechanics which is not listed in the wage determination and which is to be employed under the contract shall be classified in conformance with the wage determination." Section 5.5(a)(1)(ii)(A) also specifies that an additional classification and wage rate is to be approved only when three criteria have been met: (1) The work to be performed by the classification requested is not performed by a classification in the wage determination; and (2) The classification is utilized in the area by the construction industry; and [2] ~3 [3] (3) [*] The proposed wage rate, including any bona fide fringe benefits, bears a reasonable relationship to the wage rates contained in the wage determination. [*] [*] (Emphasis supplied.) [*] In this matter, the Wage and Hour Division initially disapproved the request for addition of a glazier classification at $9 per hour and 6.62% in fringe benefits because the request did not reflect the concurrence of employees, and required by 29 C.F.R. 5.5(a)(1)(ii)(B), and because the requested wage rate did not bear a reasonable relationship to the wage determination. With respect to the relationship of the requested wage rate to the wage determination, the Wage and Hour Division's November 16, 1988 letter specifically called attention to the rate listed in the wage determination for roofers, the lowest paid skilled classification on the wage determination. When the State of Iowa requested reconsideration, the Administrator ruled that the submission of "Wage Acknowledgement Forms" signed by employees was sufficient to demonstrate the employees' concurrence in the request, but denied reconsideration on the basis that no information was submitted with regard to the conformability of the proposed wage rate to the wage determination. The record indicates that the Administrator properly ruled that Petitioner failed to show a reasonable relationship between the proposed wage rate and the wage rates contained in the wage determination, since the wage rate requested for glaziers ($9, plus 6.62% in fringe benefits) is substantially lower than the wage rate for roofers ($12.65, plus $1.45 in fringe benefits) -- the lowest paid skilled classification on the applicable wage determination. Furthermore, the wage rate proposed for glaziers is substantially lower than the hourly rate in the wage determination for laborers ($12.95, plus $1.45 in fringe benefits). See Rite Landscape Construction Co., Inc., WAB Case No. 83-03 (Oct. 18, 1983) (the $4.50 rate proposed for lawn sprinkler installer was not reasonably related to a wage determination in which the rate specified for laborers was $8.29 plus fringe benefits). As noted by the Solicitor (Statement for the Administrator, at pp. 6-7), the wage determination put Petitioner on notice at the time of bidding on the subcontract of the wage rates the lowest paid skilled classification and the laborer classification; Petitioner could not reasonably assume that an additional skilled classification could be paid at a substantially lower rate unless the wage determination itself was amended. Indeed, Petitioner essentially challenges the applicable wage determination by arguing before the Board that the proposed glazier wage rate "is in reasonable conformity with the prevailing wage rate for glaziers for this locality" (Petition, at p. 3), and that the applicable wage determination is "artificially inflated and the wage rates are not comparable to the prevailing rates paid in the industry in Central Iowa" (Affidavit of Tim Woolworth, at [par] 7). However, the Board has consistently ruled that in order for a challenge to a wage determination to be [3] ~4 [4] timely, the challenge must be made prior to contract award (or the start of construction if there is no contract award). Harper County, Kansas, WAB Case No. 90-30 (Oct. 23, 1990), at p. 6, citing Dairy Development, Ltd., WAB Case No. 88-35 (Aug. 24, 1990); (FOOTNOTE 1) Rite Landscape Construction Co., supra. See 29 C.F.R. 1.6(c)(3). Once the contract is awarded, the only method -- absent certain limited exceptions not applicable here (FOOTNOTE 2) -- for establishing an additional classification and wage rate is through the conformance procedure. As discussed above, that procedure requires the demonstration of a reasonable relationship between the proposed wage rate for the additional classification and the wage rates in the applicable wage determination, and the Administrator properly determined that no such showing was made in this case. Petitioner additionally contends that it began work on the project only after receiving approval from the Iowa DNR as contracting officer (Woolworth Affidavit, at [par] 9), that the DNR had the right to approve the rate, and that the contracting officer's approval of the rate should be affirmed (Petition, at pp. 2-3). However, the record shows that the DNR specifically informed the City of Des Moines that use of the requested rate was subject to the approval of the Wage and Hour Division of the Department of Labor (see p. 2, supra). Furthermore, the Department's conformance regulations do not give the contracting officer final authority to approve requested classifications and wage rates, but instead provide, at 29 C.F.R. 5.5(a)(1)(ii)(B), for approval by the Administrator of the Wage and Hour Division. Finally, even if the Iowa DNR had described its actions as the authoritative approval of the glazier classification and wage rate, Board precedent establishes that erroneous contracting agency advice does not bar the Department of Labor from requiring payment of the appropriate wage rate. Metropolitan Rehabilitation Corp., WAB Case No. 78-25 (Aug. 2, 1975); Tollefson Plumbing and Heating, WAB Case No. 78-17 (Sept. 24, 1979). [4] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ (FOOTNOTE 1) "Manifest injustice to bidders would result," the Board has noted, "if the successful bidder on a project could challenge his contract's wage determination rates after all other competitors were excluded from participation." Dairy Development, Ltd., at p. 19. (FOOTNOTE 2) 29 C.F.R. 1.6(f) provides: The Administrator may issue a wage determination after contract award or after the beginning of construction if the agency has failed to incorporate a wage determination in a contract required to contain prevailing wage rates determined in accordance with the Davis-Bacon Act, or has used a wage determination which by its terms or the provisions of this part clearly does not apply to the contract. Further, the Administrator may issue a wage determination which shall be applicable to a contract after contract award or after the beginning of construction when it is found that the wrong wage determination has been incorporated in the contract because of an inaccurate description of the project or its location in the agency's request for the wage determination. . . . [4] ~5 [5] Petitioner also argues that the Administrator did not act on the requested glazier wage rate in a timely manner, and that the Administrator should be estopped from denying the request (Petition, at p. 3). Petitioner's timeliness argument is based on 29 C.F.R. 5.5(a)(1)(ii)(B), which provides that where the contractor, the employees or their representative, and the contracting officer agree on the proposed additional classification and wage rate, a report of the contracting officer's action is to be sent to the Wage and Hour Division. Section 5.5.(a)(1) (ii)(B) further provides that the Administrator "will approve, modify, or disapprove every additional classification action within 30 days of receipt and so advise the contracting officer or will notify the contracting officer within the 30-day time period that additional time is necessary." In this case, the Wage and Hour Division's November 16, 1988 decision denying the requested glazier classification and wage rate was not issued within the 30-day timeframe contemplated in Section 5.5(a)(1)(ii)(B). However, as stated by the Deputy Secretary in a decision regarding an essentially identical provision (29 C.F.R. 4.6(b)(2)(ii) of the regulations governing conformance procedures under the Service Contract Act, that provision is not jurisdictional, and does not preclude the Wage and Hour Division from taking action outside the 30-day period. CACI, Inc. - Federal, Case No. 86-SCA-OM-5 (Mar. 27, 1990), at p. 29. Indeed, the Board observes that the 29 C.F.R. 5.5(a)(1)(ii)(B) expressly references the possibility that additional time may be needed to complete action on the requested classification and wage rate. The Board also notes, as did the Deputy Secretary in CACI, that the conformance regulations do not specify that the failure of the Administrator to act within 30 days is effectively the Administrator's approval or acquiescence in the proposed classification or wage rate. In sum, the 30-day time period referenced in Section 5.5(a)(1)(ii)(B) does not provide a basis for Petitioner to presume that in the absence of a response from the Administrator, the glazier classification and wage rate had been approved. For all the foregoing reasons, the petition for review is denied and the final ruling of the Administrator is affirmed. BY ORDER OF THE BOARD: Charles E. Shearer, Jr., Chairman Ruth E. Peters, Member Patrick J. O'Brien, Member _____________________________ Gerald F. Krizan, Esq. Executive Secretary [5]



Phone Numbers