skip navigational links United States Department of Labor
May 9, 2009        
DOL Home > OALJ Home > USDOL/OALJ Reporter
DOL Home USDOL/OALJ Reporter

COLBY COOPERATIVE STARCH CO., WAB No. 84-21 (WAB June 3, 1985)


CCASE: COLBY COOPERATIVE STARCH COMPANY DDATE: 19850603 TTEXT: ~1 [1] WAGE APPEALS BOARD UNITED STATES DEPARTMENT OF LABOR WASHINGTON, D. C. In the Matter of COLBY COOPERATIVE STARCH COMPANY WAB Case No. 84-21 Caribou, Maine Dated: June 3, 1985 BEFORE: Alvin Bramow, Chairman, Thomas X. Dunn, Member, and Stuart Rothman, Member, Concurring DECISION OF THE WAGE APPEALS BOARD This case is before the Wage Appeals Board on the petition of Colby Cooperative Starch Company (hereinafter Colby) seeking reversal of the ruling of the Assistant Administrator, Wage and Hour Division, dated October 1, 1984. The ruling in question provides that the Economic Development Administration has the authority to withhold grant funds otherwise due Colby to satisfy Davis-Bacon and Contract Work Hours and Safety Standards Act wage violations and that these withheld funds may be transferred to the Department of Labor for disbursement directly to the employees. In February, 1980, Colby received a $1.5 million grant from the Economic Development Administration for the purpose of constructing a starch manufacturing facility in Aroostock, Maine. In July, 1980 Colby contracted with Barr & Murphy International Ltd. to be general contractor on the project. Construction began one year later. The general contract and all subcontracts contain [1] ~2 [2] the required prevailing wage and overtime pay provisions of the Public Works and Economic Development Act of 1965 and the Contract Work Hours and Safety Standards Act, respectively. An investigation of the project by the Department of Labor's Wage and Hour Division disclosed that six of the subcontractors to Barr & Murphy owed $167,883 for prevailing wage and overtime violations. Two of the subcontractors paid the back wages, leaving a balance of $151,186 remaining. In conferences between the parties in 1983 Barr & Murphy acknowledged the occurrence of the violations but indicated it could not pay the back wages until the grantee, Colby, paid Barr & Murphy the sums due it. Colby, on the other hand, claims that Barr & Murphy was responsible for a fire which occurred and seriously damaged the project. Colby claims Barr & Murphy owes Colby approximately $1,000,000. The parties have sued each other over these claims. The Wage and Hour Divis[i]on has requested that the Economic Development Administration pay $150,000 to it for disbursement to the employees and the prime contractor and subcontractors have agreed to this procedure. Colby, through its attorney, objected to the withholding and the proposed disbursement. Colby claims that the Economic Development Administration does not have the authority to pay over any of the grant to the Department of Labor, and that the Department did not have the authority to order EDA to turn over the grant money. [2] ~3 [3] Wage and Hour, through the Assistant Administrator, issued a ruling that it has the authority to request the withholding and EDA has the authority to withhold amounts from the grantee and transfer the funds to the Department for disbursement to employees. The Assistant Administrator concluded that since the grantee, Colby, had not contested the occurrence of the wage violations and since the contractors agree that at least $130,169.53 in back wages were due, the Department has the authority to request EDA to transfer the funds to it for disbursement to employees. It is from this ruling that Colby appealed to the Wage Appeals Board on November 27, 1984. The Board considered this appeal on the basis of the Petition for Review and the Reply Statement from the petitioner, Colby, and the record of the case before the Wage and Hour Division and the Statement for the Assistant Administrator, Wage and Hour Division, filed by the Solicitor of Labor. No request for an oral hearing was received by this Board. * * * The majority of the Board first must address the contention of the petitioner that the Economic Development Administration does not have authority to withhold grant funds from the grantee because of prevailing wage and overtime pay violations committed by contractors performing on the project. The labor standards provisions of the Public Works and Economic Development Act of 1965 and the Department of Labor Regulations [3] ~4 [4] pertaining to this matter provide as follows: All laborers and mechanics employed by contractors or subcontractors on projects assisted by the Secretary under this chapter shall be paid wages at rates not less than those prevailing on similar construction in the locality as determined by the Secretary of Labor in accordance with the Davis- Bacon Act, as amended. The Secretary shall not extend any financial assistance under section 3131, 3141, 3142, 3171, 3243, and 3246b of this title for such a project without first obtaining adequate assurance that these labor standards will be maintained upon the construction work. The Secretary of Labor shall have, with respect to the labor standards specified in this provision, the authority and functions set forth in Reorganization Plan Numbered 14 of 1950 and section 276c of Title 40. (42 U.S.C. 3222) Department of Labor Regulations: The (write in name of Federal Agency or the loan or grant recipient) shall upon its own action or upon written request of an authorized representative of the Department of Labor withhold or cause to be withheld from the contractor under this contract or any other Federal contract with the same prime contractor, or any other Federally-assisted contract subject to Davis-Bacon prevailing wage requirements, which is held by the same prime contractor, so much of the accrued payments or advances as may be considered necessary to pay laborers and mechanics, including apprentices, trainees, and helpers, employed by the contractor or any subcontractor the full amount of wages required by the contract. In the event of failure to pay any laborer or mechanic, including any apprentice, trainee, or helper, employed or working on the site of the work . . . all or part of the wages required by the contract, the (Agency) may, after written notice to the contractor, sponsor, applicant, or owner, take such action as may be necessary to cause the suspension of any further payment, advance, or guarantee of funds until such violations have ceased. (29 CFR 5.5(a)(2)) [*] With holding. [*] [4] ~5 [5] In the event of failure or refusal of the contractor or any subcontractor to comply with labor standards stipulations required by the regulations contained in this part and the applicable statutes listed in section 5.1, the Federal agency shall take such action as may be necessary to cause the suspension of the payment, advance or guarantee of funds until such time as the violations are discontinued or until sufficient funds are withheld to compensate employees for the wages to which they are entitled and to cover any liquidated damages which may be due. (29 CFR 5.9, Suspension of funds) The petitioner reads the labor standards provisions of the Public Works and Economic Development Act of 1965 and the Department of Labor's Regulations 29 CFR 5.5(a)(2) and 5.9, regarding withholding, to apply only to contractors performing on the project. The petitioner maintains that a grantee's only obligation is to insert in the construction contracts with its contractors all the terms imposed by the funding agency. After this is accomplished, it relinquishes all responsibility for all the labor standards provisions contained in the grant documents and applicable law. Notwithstanding the facts that petitioner maintains that the fire on the project was the responsibility of the prime contractor, that the prime contractor may owe petitioner approximately $1,000,000 as a result thereof, and that to turn over the money to the workers will in essence cause a further burden on petitioner, the majority of the Board cannot agree with petitioner's strained interpretation of the Davis-Bacon and related Acts and the regulations promulgated thereunder. There is no question that the Acts in question are remedial [5] ~6 [6] statutes for the benefit of laborers and mechanics. See U.S. v. Binghampton Construction Co., 347 U.S. 141 (1954). Therefore, the statute and all the regulations must be read together. Such a reading places a grantee in the same position as a prime contractor on a direct Federal project. To hold otherwise would render the labor standards provisions of the Public Works and Economic Development Act of 1965 and similar statutes meaningless. It is the grantee who entered into an agreement with a Federal agency for funds and as part of this agreement the grantee obligated itself to the Government to assure that the labor standards would be maintained upon the construction work. By a plain reading of the Act, Department of Labor regulations and the grant agreement there can be no question that a violation of the labor standards provision renders the grantee liable for such underpayments. The primary method provided by the Government to reimburse laborers and mechanics for underpayments is to withhold funds. In this case, the sanction of withholding can only be applied against the grantee and such action is proper under the Act and regulations promulgated by the Department of Labor as authorized by Reorganization Plan No. 14 of 1950 and section 276c of Title 40. Secondly, the petitioner contends that the Department of Labor has no authority to take possession of grant funds and to disburse the funds to employees. Again, the majority of the [6] ~7 [7] [Board] cannot agree with this position of the petitioner. It is perfectly clear that the above-cited Department of Labor Regulations and the Agency's Supplemental General Conditions at 5-15 (contained in the record) provide for the disbursement of withheld funds to satisfy the underpayment of wages. The above authorities are silent as to the manner this disbursement will be accomplished. It appears to the majority that this is a matter strictly between the Department of Labor and the Federal agencies involved and as long as the disbursement of the withheld funds is carried out in a proper manner there can be no basis in law to challenge such disbursement. In view of the foregoing, the decision of the Assistant Administrator is affirmed and the petition herein is dismissed. * * * Stuart Rothman, Member, Concurring I concur in the result reached in this case but write to explain my views. I am not in full accord with the expression of the majority's reasoning. As the majority opinion notes, "the prime contractor, Barr and Murphy acknowledge the occurrence of the violations but indicated it could not pay the back wages until the grantee, Colby, paid Barr and Murphy the sums due it." The Colby Cooperative [7] ~8 [8] Starch Company did not underpay the laborers and mechanics on this job. The contractors and subcontractors did. Two subcontractors paid the back wages. There is a standoff, according to the record, between Barr and Murphy on one side, and Colby on the other. Colby claims Barr and Murphy were responsible for a fire at the project and it owes Colby about one million dollars. The contractor claims that it cannot pay the back wages until it collects payments being withheld by Colby. We are told the parties have sued each other, but we are unaware of the status or outcome of this suit. My problem with this case on the basis of incomplete briefing is the following: I assume that the prime contractor worked under a lump sum construction contract. It owes the laborers and mechanics for underpaid wages due. Colby does not. The contractor either presently or in the long run is the one that should have to make up the payroll difference that should have been in the employee's checks. We do not know whether the contractor is saying it doesn't have the money to make the payment which it owes or it simply is not going to make the payment until it collects some partial or final payments from Colby. But it is the contractor who did not put the right amount of pay in the employee's checks. Into this intricate denouement the EDA and [8] ~9 [9] the Department of Labor are going to take $150,000 out of Colby's grant and pay the laborers and mechanics directly. This looks to me the same as giving the money to Barr and Murphy to make up the difference in underpayment that was Barr and Murphy's primary responsibility not to let happen. I concur in the result because of the specificness of the last sentence (29 CFR [sec] 5.9 Suspension of Funds) quoted in the majority opinion. This provision provides that in the event or refusal of the [*] contractor or any subcontractor [*] to comply with the labor standards stipulations, the Federal agency shall suspend "payment, [*] advance [*] or [*] guarantee [*] of funds until such time as . . . sufficient funds are withheld to compensate the employees for the wages to which they are entitled. . . ." [*] (Underlining supplied) [*] Under this provision I conclude that the authority to suspend [*] advances [*] or [*] guarantees [*] until sufficient funds are withheld to compensate employees for wages due encompasses the authority not only to withhold guaranteed funds to a sponsor but to pay them directly to the employees. [*][EMPHASIS IN ORIGINAL][*] The provision is quite specific. Whether the contractor and Colby have counterclaims against each other not related to whether Barr and Murphy has met its Davis-Bacon obligations is irrelevant to whether Barr and Murphy has a statutory and contractual obligation to the laborers and mechanics on the job. As third party beneficiaries, they should not be caught in any cross fire between Barr and Murphy, and Colby over a dispute irrelevant to whether they have been properly paid. [9] ~10 [10] I must assume for purposes of this concurring view, but in the absence of a better record and briefing, that the contractors on this job were required to post the necessary payment bonds or their equivalent. If not, this is a matter the grantee overlooked. While the laborers and mechanics who have been underpaid should receive their full wages with minimum delay, more should be done by EDA and the Department of Labor and by Colby to place the responsibility where it belongs, on the contractors and/or subcontractors and their sureties. The contractor's refusal to meet its contractual and statutory obligations can only result in the long run in that company making up the necessary underpayments and also exposing itself to additional statutory liabilities. BY ORDER OF THE BOARD Craig Bulger, Executive Secretary, Wage Appeals Board [10]



Phone Numbers