skip navigational links United States Department of Labor
May 9, 2009        
DOL Home > OALJ Home > USDOL/OALJ Reporter
DOL Home USDOL/OALJ Reporter

MARTA CONTRACTS, WAB No. 83-09 (WAB May 14, 1984)


CCASE: MARTA CONTRACTS DDATE: 19840514 TTEXT: ~1 [1] WAGE APPEALS BOARD UNITED STATES DEPARTMENT OF LABOR WASHINGTON, D. C. In the Matter of MARTA CONTRACTS CN-710 & WAB Case No. 83-09 CN-730 and Options thereto No. Georgia Bldg. Trades Dated: May 14, 1984 Council APPEARANCES: Frank B. Shuster, Esquire, for North Georgia Building Trades Council Bruce Bromberg, Esquire, for Metropolitan Atlanta Rapid Transit Authority Terry R. Yellig, Esquire, for the Building and Construction Trades Department, AFL-CIO Douglas J. Davidson, Esquire, for the Wage and Hour Division, U.S. Department of Labor BEFORE: Alvin Bramow, Chairman, Stuart Rothman, Member Thomas X. Dunn, Member, Dissenting DECISION OF THE WAGE APPEALS BOARD This case is before the Wage Appeals Board on the petition of the North Georgia Building Trades Council (hereinafter BTC) seeking review of the decision of the Administrator, Wage and Hour Division, dated August 19, 1982. The Administrator ruled, in response to an earlier request from a representative of Local Union 613 of the International Brotherhood of Electrical [1] ~2 [2] Workers, that the Davis-Bacon labor standards provisions of the Urban Mass Transportation Act of 1964 (49 USC 1609) were not applicable to the Metropolitan-Atlanta Rapid Transit Authority (hereinafter MARTA) Contract CN-710. Subsequently, MARTA awarded CN-710 and construction began on December 30, 1982. A second contract, CN-730, for construction of a station was advertised and awarded while a request for reconsideration of the Administrator's decision was pending. That contract was awarded and construction began on CN-730 on March 1, 1983. Following denial of the petitioner's request for reconsideration, petitioner notified the Wage Appeals Board on May 27, 1983 of its intention to file a petition for review by the Board. The rapid rail system being constructed by MARTA in Atlanta is divided into three phases, A,B & C. Phases A and B have been partially financed by grants or commitments from the U.S. Department of Transportation's Urban Mass Transit Administration (hereinafter UMTA), and as a result all construction contracts in Phases A and B contained the Davis-Bacon prevailing wage provisions as required by the Urban Mass Transportation Act. The two MARTA contracts in issue are in Phase C and thus far no federal grants have been obtained and neither contract contains Davis-Bacon labor standards provisions. However, extensions of two contracts being performed in Phase B for tracks, traction power, train control and the communication [2] ~3 [3] system have been undertaken and will extend for 2000 feet into Phase C on top of the track preparation encompassed in CN-710. It is because of this that petitioner argues that federal funds will, in fact, intrude into Contract CN-710 and, as a result, the BTC argues that the project should be considered as a whole and that Davis-Bacon labor standards provisions should apply to Contract CN-710 also. It is MARTA's position that it has, by beginning the contracts without Davis-Bacon labor standards provisions, precluded itself from any opportunity of receiving or using federal funds on CN-710 or CN-730, that it has no intention of applying for federal grants for the contracts, and finally, MARTA indicates that it intends to use solely local (non-federal) funds to finance the contracts in question. MARTA argues that the exercise of the aforementioned options from Phase B and the continuation of construction paying the Davis-Bacon wage rates is merely a carryover from the contract begun in Phase B and should not affect the financial arrangements for Contract CN-710 since only local, non-federal funds will be used on those portions of the options lying in the same area as CN-710. The Administrator in his decision indicated that he considered the options to be a significant part of the rail construction. Therefore he concluded that if MARTA subsequently obtained federal funds for the options to be built over CN-710 the Davis-Bacon labor standards provisions would be applicable [3] ~4 [4] to all construction work on that segment of track including CN-710. However, the Administrator's decision was that under the facts that existed at the time he made his decision, it was not improper for UMTA to advertise and build the projects without Davis-Bacon wage rates and the applicable labor standards provisions. The Wage Appeals Board considered this appeal on the basis of the BTC's Petition for Review and a Supplemental Brief with exhibits, a Response and a second Response to Petitioner's Supplemental Brief filed by MARTA, a Statement for the Administrator and a record of the case before the Wage and Hour Division filed by the Solicitor of Labor, and a hearing conducted April 3, 1984, at which all interested parties were present and participated. * * * This case is before the Board on the petition of the North Georgia Building Trades Council because the Council believes that at the time the Wage and Hour Administrator made his basic decision that the disputed work in question need not be covered by Davis-Bacon Act requirements, MARTA had not disclosed to the Administrator that there were segments of contractually committed work awarded subject to the Davis-Bacon Act which under the [4] ~5 [5] terms of the prior contracts overlapped with and continued on into the area here in dispute (identified as the Phase C area). This work would be performed under Davis-Bacon Act requirements. This "overlap" work includes the laying of track, installation of signals, signs, switches and other electrical equipment. At the hearing BTC contended that despite MARTA's continued denials that any federal funds would be used in any of this disputed work, including that segment of the previously awarded track work and the electrical, signal and switching equipment, MARTA's own budgeted figures for such work, awarded subject to the Davis-Bacon Act, projected the inclusion of federal funds into the disputed area. It was said at the hearing that the total value of the disputed work was around $40,000,000. The "overlap" work was valued at around $1,000,000. MARTA's spokesman at the hearing strongly represented that whatever the budgeted figures purport to show, these figures are only prospective budgeted amounts. In the actual completion of the work, MARTA would see to it that there would be no federal funds whatsoever in any of the disputed work, including the work referred to herein or the "overlap" from Phase B to Phase C. MARTA pointed out that in the administration of the track laying and other overlap contracts, actual budgeting and the making of payments thereunder to contractors is and will be on a segment- by-segment basis. MARTA claimed that a segment identified as [5] ~6 [6] CN-490 in the Phase B area ran only to the perimeter of the Phase C area and that a local funding arrangement would be provided for all work in the Phase C area, including the overlap. There were a number of matters raised at the hearing which the Board does not reach for the reason that the outcome of this case does not turn upon their resolution. These other matters include, for example, the question whether BTC, having once secured an injunction against MARTA going ahead with all or part of the disputed work, nonetheless entered into some kind of understanding with MARTA that the work in question could proceed on MARTA's terms -- that is, without the inclusion of the Davis-Bacon provisions. There would be a subsidiary question whether BTC or anyone else could waive the application of the Davis-Bacon Act in any case required by law. There is another question concerning work sequences subject to the contracts in dispute and the work subject to the overlap contracts and the interrelation of all the contracts considered together. We do not reach these questions for the reason that BTC took the position at the hearing that if, in truth, there is and will be no federal monies, grants, aids or otherwise, in any of the disputed work in the Phase C area -- the construction of the road bed, the laying of the railroad tracks, the electrical equipment including signals and switches, or any other [6] ~7 [7] work -- then BTC would not contend that the Davis-Bacon Act requirements must be applied. The BTC did not contend that because the Davis-Bacon Act was applied in the Phase A and B areas, it must necessarily be applied in the Phase C area if in fact there were no federal funds involved in the work there. We hold that in a subway rail project of this type, segments can be built without the use of federal funds and in such a case the Davis-Bacon Act does not have to be included. The Administrator concluded that MARTA has not gerrymandered the project to avoid Davis-Bacon on the disputed contracts. We have no reason to question the factual accuracy of the Administrator's decision. As already noted, MARTA made strong representations at the hearing that there would be no federal funds whatsoever used with respect to any of the disputed work in Phase C. We have no reason to question either the integrity of MARTA in making such representations or the administrative processes by which the Wage and Hour Administrator came to the conclusion that MARTA was not withholding any information to do otherwise. The Wage and Hour Administrator had the facilities and opportunities to examine more fully into the representations made by MARTA, and we see no reason to set aside the Administrator's conclusions. However, at the hearing it was not made as clear as it might have been by either party, precisely what the budgeted [7] ~8 [8] figures for the railroad track stand for with respect to the areas in which the track is to be constructed. Additionally, it may not have been made as clear as it might have been precisely how MARTA would assure itself as well as the Wage and Hour Administrator and the Department of Transportation that no federal funds will be used for work already awarded subject to the Davis-Bacon Act which may extend into Phase C. MARTA has, of course, noted that in cases in which such contractual arrangement presently exists, the wage standards already provided in those contracts would not be changed even though there may not be a statutory requirement that the Davis-Bacon Act provisions be included in such work. In view of the foregoing, the Board agrees with the conclusions reached by the Wage and Hour Administrator and would affirm the determination that he has reached in this matter subject to the following single condition. The case is remanded to the Administrator with instructions to secure from the appropriate officer or officers of MARTA, by letter or other writing, a clear and unmistakable commitment that with respect to any and all of the disputed work in question, including the overlap work described above, no federal funds in any way, shape or manner which would require the inclusion of the Davis-Bacon Act in contract awards, will be used [8] ~9 [9] in the area. Under the circumstances of this case, the Board believes that this is a very simple and direct way within the contentions of all the parties to dispose of this long lasting dispute. * * * Member Dunn, dissenting: MARTA has elected to proceed with Contract CN-710 relying solely on local funding. By so doing, MARTA will be precluded from receiving any reimbursement from UMTA for the work performed under Contract CN-710. /FN1/ The Administrator found in his August 19, 1982 decision that Contract CN-710 is not covered by the Davis-Bacon provisions in the Urban Mass Transportation Act because UMTA has not approved a grant or issued a letter of no prejudice against subsequent funding for any of Phase C of MARTA's system. [9] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN1/ As stated by UMTA: UMTA will not reimburse MARTA, for construction work performed by MARTA, its contractors or subcontractors, where such work is performed without prior documented approval by UMTA as the Federal grantor agency. Without prior approval, the cost of such work is not an allowable cost under the provisions of Office of Management and Budget (OMB) Circular A-87, Janu[]ary 28, 1981, 46 C.F.R. 553 and UMTA Order 1000.2, External Operating Manual, Change 4, May 23, 1974, Paragraph 5, IIID-31. [9] ~10 [10] The Building Trades Council argues, however, that the consolidated letter of no prejudice issued to MARTA on February 9, 1981 and the subsequent announcement by Secretary of Transportation Dole that MARTA would receive a $45.1 million grant for the completion of its North-South line, which includes Contract CN-710, indicates that Phase C is, in fact, partially funded with federal money. In addition, the Building Trades Council alleges that under the Administrator's ruling and UMTA's letter of no prejudice, MARTA could receive federal assistance for segments of Phase C other than Contract CN-710. Thus, by using federal funds for Phase C work before and after Contract CN-710, petitioner contends that MARTA has more local funds available for Contract CN-710. Specifically, petitioner argues that, contrary to MARTA's representations and the Administrator's finding, federal funds are already being used to help pay for "system-wide" contracts to lay the rail, cable, wayside signs, and train control system which begin in Phase B, but continue into Phase C and certain options to complete that phase. Petitioner contends that this is analogous to paying for the foundation of a house with local money and, thereafter, building the structure with federal funds. MARTA strenuously argues that UMTA has neither provided money for any Phase C work nor issued letters of no prejudice or [10] ~11 [11] grants of federal funds for any of the option work in Phase C and that federal funds made available for the initial part of these system wide contracts have been carefully segregated to insure that they are used only to help pay for construction work in Phase B2. This, MARTA contends, has been done pursuant to UMTA's directions. A hearing before this Board is appellate, not an evidentiary, hearing. None of the parties have a right to cross-examine or confront witnesses at a Wage Appeals Board hearing. Hearings before this Board are limited to arguments on the facts as developed in the record and the law as applied to the facts of the case. Framlau Corp. v. Dembling, 360 F. Supp. 806 (E.D. PA 1973). Accordingly, we cannot resolve these factual disputes. /FN2/ Instead, I would remand this case to the Administrator pursuant to the Board's Rules of Procedure /FN3/ with instructions to [11] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN2/ The Board's Rules of Procedure provide: The Board is essentially an appellate agency. It will not hear matters de novo except upon a showing of extraordinary circumstances. It may remand under appropriate instructions any case for the taking of additional evidence and the making of new or modified findings by reason of the additional evidence. 29 C.F.R. [sec] 7.1(e). /FN3/ It is ironic that the majority has chosen to credit the unsupported arguments presented by MARTA that no federal money has been used to fund any portion of Phase C inasmuch as the Board has, in the past, found that MARTA "*** manipulate(d) wage rates to its own satisfaction in bid documents". In Re Prevailing Wage Rates [11] [FN3 CONTINUED PAGE 12] [12] (Continued) Applicable to Metropolitan Atlanta Rapid Transit Authority (Brown's Mill Road Bus Facilities) WAB Case No. 75-11 (Apr. 19, 1976) 22 Wage & Hour Cases 971, 982, (Barker concurring), (Rothman, concurring in part, dissenting in part). In that case, MARTA disregarded a determination by the Wage and Hour Division that the schedule of prevailing wages for building construction in the area should be included in 2 contract for site work on a garage facility for MARTA buses. Instead, MARTA awarded the contract with lower prevailing wage rates for highway construction included while the matter was pending before the Board. In view of MARTA's flagrant action, the Board fashioned a rather extraordinary remedy. See id. at 980-981. [END FN3] [12] ~12 [12] investigate this matter and issue a new decision on the basis of the results of such investigation. Even if such investigation failed to support the Building Trades' position, I am impressed by the petitioner's contention that the work performed under Contract Cn-710 is so intermingled with the other contacts in Phase C, in particular, and the entire MARTA system, in general, that it cannot be treated differently for Davis-Bacon purposes from the other contracts which have been or may be federally financed. The Administrator concluded in his August 19, 1982 decision that the Davis-Bacon provisions of the Urban Mass Transportation Act would apply to Contract CN-710 even if that contract received no federal funds provided that other work pertaining to and integral to that same segment of track did receive federal assistance. However, the Administrator narrowed his original [12] ~13 [13] ruling in his May 4, 1983 response to petitioner's request for reconsideration. Petitioner presented evidence, which is not disputed, that UMTA has issued a letter of no prejudice for construction of the Airport Station at the southern end of Phase C. The Administrator advised petitioner in his May 4, 1983 letter that even if federal funding is later approved for this contract, this alone is not a sufficient basis to require application of the Davis-Bacon provisions to be applied to all other Phase C construction including that for which no federal funds are used. It is this portion of the Administrator's ruling with which I disagree. In North Georgia Building & Construction Trades Council v. Goldschmidt, 621 F.2d 697 (5th Cir. 1980), the court of appeals considered a case where the City of Atlanta had solicited bids to perform three airport contracts. Federal funding was anticipated, although it had not been applied for or received. Prior to bid opening, the North Georgia Building Trades Council sought different, higher prevailing wage determinations than those the City had selected from the Federal Register published by the Department of Labor. The Department notified the Federal Aviation Administration (FAA) by telephone within 10 days from the date of bid opening that different and higher wage determinations should apply to all three airport contracts. A telegram advising FAA and the City of the changes was sent the next day. [13] ~14 [14] Concluding that there was not "reasonable time" in which to notify bidders, the FAA directed that bid opening proceed on schedule without changes in wage rate specifications. The Building Trades Council filed an appeal to this Board as well as an action in federal district court seeking to enjoin the City from receiving bids or awarding contracts based on the challenged wage determinations. In its decision, the Board concluded that, since the City had neither applied for nor received any financial assistance from the FAA at the time it received bids on the disputed contracts, the Davis-Bacon provisions in the Airport and Airway Development Act, 49 USC [sec] 1722(b), and applicable regulations were inapplicable to the controversy. The Prevailing Wage Rates Applicable to the Construction of the Hartsfield International Airport, WAB Case No. 77-04 (February 25, 1977). The court of appeals overruled the Board's decision holding instead that the Davis-Bacon provisions of the Airport Act applied to the project even though federal funds had not yet been formally applied for or authorized at the time of bid opening where the City anticipated applying for and receiving federal assistance for its airport project. Here, unlike the City of Atlanta in North Georgia Building and Construction Trades Council v. Goldschmidt, MARTA is unwilling to comply with federal prevailing wage standards until, and unless, UMTA commits federal money to a specific contract. I am unaware [14] ~15 [15] of any case, before the Board or the courts, which has considered this question. Nevertheless, the courts have frequently been concerned about the possibility of local agencies avoiding federal requirements. In Named Individual Members of San Antonio Conservation Society v. Texas Highway Department, 446 F.2d 1013 (5th Cir. 1971), the State of Texas, unable to comply with requirements of the National Environmental Policy Act (NEPA), 42 USC [secs] 4321-4361, through[]out the length of a highway in San Antonio, Texas, proposed to construct end segments of the road with state and federal funds and the middle segment with state funds only. The State argued that because the middle segment would proceed with 100 percent state money, the NEPA requirements were inapplicable. The Fifth Circuit rejected the State[']s argument holding: We are not impressed with this argument. If we were to accept it, we would be giving approval to the circumvention of an Act of Congress. The North Expressway is now a federal project, and it has been a federal project since the Secretary of Transportation authorized federal participation on August 13, 1970. As such the North Expressway is subject to the laws of Congress, and the State as a partner in the construction of the project is bound by those laws. The supremacy of federal law has been recognized as a fundamental principle of our Government . . . . The State may not subvert that principle by a mere change in bookkeeping or by shifting funds from one project to another. 446 F.2d at 1027. [15] ~16 [16] While the statutory requirement at issue in San Antonio was not a Davis-Bacon provision, the principles expressed furnish sound precedent for my decision. Here, too, an Act of Congress will be subverted if MARTA builds part of Phase C with federal assistance but fails to comply with the prevailing wage provisions in the Urban Mass Transit Act for the entire project. MARTA represented to this Board in 1975 in The Prevailing Wage Rates Applicable to Three Construction Projects of the Metropolitan Atlanta Rapid Transit Authority, Wage Decisions Nos. 75-GA-159, 75-GA-159, 75-GA-160 and 75-GA-161, WAB Case No. 75-05; that: When completed the (MARTA rapid rail transit) system will consist of 60.9 miles of rapid rail and busway lines in Fulton and DeKalb Counties. It will utilize 39 rapid rail stations and two rapid busway stations. Parking will be provided for over 30,000 vehicles. The projected cost of the system is $2.1 billion. The Urban Mass Transportation Administration (UMTA), a department of the United States Department of Transportation, will provide 80 percent of the capital construction and equipment expenditures. The remaining 20 percent will be provided by the local governments through a one percent sales and use tax. MARTA's Brief, at p.3, in WAB Case No. 75-05. Thus, MARTA's rapid rail transit system, like the expressway in San Antonio Conservation Society and the airport in North Georgia BTC v. Goldschmidt, is a federal project, and has been a federal project since UMTA originally authorized federal participation in the project. As such, the MARTA rapid rail [16] ~17 [17] transit system is subject to the laws of the United States, including the Davis-Bacon provision in the Urban Mass Transportation Act, 49 U.S.C. [sec] 1609(a). MARTA cannot avoid the requirements of [sec] 1609(a) simply because federal funds are limited to certain contracts or portions of contracts. This labor standards provision was designed to assure to the fullest extent possible that the expenditure of federal funds will not depress locally prevailing wages. A local public agency's avoidance of this requirement on part of the project while receiving federal funds for other portions of the project frustrates Congressional intent to maintain locally prevailing wage standards. At this time MARTA claims no federal funds have been allocated for any of the construction work in Phase C. Nonetheless, MARTA has included Davis-Bacon requirements in contracts for work which it still hopes will be federally funded. It is my position that UMTA may not make any federal funds available to MARTA for any construction work theretofore performed in Phase C, including the Airport Station, unless it first determines that Davis-Bacon wage rates have been applied to [*] every [*] contract and subcontract performed in Phase C, including Contracts CN-710 and CN-730. This does not mean that MARTA must amend Contracts CN-710 or CN-730 or include Davis-Bacon requirements in any future contract in Phase C which is locally funded. However, failure to do so will preclude receipt of federal funds for any other contracts in Phase C. [17] ~18 [18] Accordingly, I would remand this case to the Administrator for further action consistent with my dissenting opinion. BY ORDER OF THE BOARD Craig Bulger, Executive Secretary Wage Appeals Board [18]



Phone Numbers