skip navigational links United States Department of Labor
May 9, 2009        
DOL Home > OALJ Home > USDOL/OALJ Reporter
DOL Home USDOL/OALJ Reporter

Metropolitan Atlanta Rapid Transit Authority, WAB No. 1975-05 (WAB Oct. 16, 1975)


CCASE: THREE CONST. V. ATLANTA TRANSIT AUTHORITY DDATE: 19751016 TTEXT: ~1 [1] UNITED STATES OF AMERICA DEPARTMENT OF LABOR DECISIONS AND ORDERS OF THE WAGE APPEALS BOARD IN THE MATTER OF The prevailing wage rates applicable to three construction WAGE APPEALS BOARD projects of the Metropolitan Rapid CASE NO. 75-05 Transit Authority, Wage Decisions SUPPLEMENTAL DECISION Nos. 75-GA-159, 75-GA-160, and Dated: October 16, 1975 75-GA-161 Metropolitan Atlanta Rapid Transit Authority Petitioner Georgia Highway Contractor's Association, Inc. Intervenor North Georgia Building and Construction Trades Council Intervenor at the Atlanta Hearing Upon Reconsideration BEFORE: Oscar S. Smith, Chairman, Wage Appeals Board and Stuart Rothman and Clarence D. Barker, Members [1] ~2 [2] The hearing on reconsideration was held in Atlanta, Georgia, on September 30, 1975, in Room 772, 1375 Peachtree Street, N.E. The North Georgia Building and Construction Trades Council was permitted to intervene at that time. Joseph Jacobs, Esq. appeared on behalf of the North Georgia Building and Construction Trades Council. SUPPLEMENTAL DECISION AND ORDER AFTER HEARING UPON MOTIONS FOR RECONSIDERATION BY THE U.S. DEPARTMENT OF LABOR AND THE BUILDING AND CONSTRUCTION TRADES DEPARTMENT, AFL-CIO Our first opinion in this case, issued August 25, 1975, directed the Employment Standards Administration (herein ESA) United States Department of Labor to consider three projects, CE 540, 173 and 330,1/ of the planned MARTA Subway and Rapid Rail Transit System (herein "planned MARTA system") on the basis of the individual characteristics of each project for comparison with other "projects of a character similar"to the contract work under the Davis-Bacon Act criteria. The Board also [2] ?????????????????? /FN1/ The bid documents with drawings and specifications had been prepared. Advertisement was said to be imminent. CE 173 has been consolidated with other segments. A new request for wage determination has been filed with ESA for the enlarged segment and this is not now before the Board. [2] ~3 [3] directed ESA to exclude wage rates paid on EPA financed water treatment and sewage disposal plants in identifying projects (such as building, heavy, highway or other categories) for the required similarity comparisons. There were a number of related directions to ESA dealing with other projects such as tracklaying and local water and sewer lines whose similarities to the contract work had been questioned. /FN2/ The challenge to the Board's two fundamental conclusions can be summed up as follows. BTD, relying greatly upon what Counsel for ESA had repeatedly stated at the original hearing, contended in its brief and orally upon reconsideration: The most important issue in this case is whether the "planned" MARTA railway system should be looked at in its entirety, or broken into segments, for the purpose of making wage determinations." * * * In the [3] ?????????????????? /FN2/ The Board in the original decision was not and is not now, oblivious to the fact that the three projects are planned as a part of MARTA's overall undertaking and are affected by the planning, financing, architectural engineering and developmental considerations of the entire system and that in time all segment projects will be tied together into one operative system, but this does not vary the conclusions reached. [3] ~4 [4] judgment of the ESA, the entire project for the purpose of wage determination was considered "an" appropriate method to satisfy the "objectives of the Act." * * * This reversal of the Board of a finding by the ESA that the entire project should be considered as a whole is totally opposed to the purposes of the Act. Both the Labor Department and BTD with equal intenseness contend that there are a number of water treatment and sewage disposal plants underway or completed since 1974 that partially but not wholly fall within the "heavy" category of work for wage predetermination purposes. It was apparently the ESA position that in some selective but undisclosed way, perhaps by a percentage of a project by volume of work or a percentage of the number of laborers and mechanics employed, portions of these water treatment and sewage disposal plants should be used as the primary base for wage predeterminations applicable to the entire MARTA system. MARTA, which is not a unitary project should be considered as an "entirety" while the water treatment and sewage disposal plants, which [4] ~5 [5] are unitary projects, should not be. For the reasons discussed later and in the August 25 decision the ESA's unique approach to the division of work on a single water treatment or sewage disposal plant is in error and to the knowledge of the Board without precedent. The challenge to the Board's decision from two responsible sources amid fervid claims that the Board has become hopelessly lost in a sea of misapplication of its own and Labor Department rulings led the Board to journey to Atlanta for a look-see of the factual situation and to reexamine its own opinion and the parties' positions on the local scene. The Board members visited the sites of the proposed work. They looked at at least two sewage disposal and water treatment plants, at a cut and cover flume project at the Atlanta Airport to divert the Flint River and at one bridge under construction on a federal aid highway program. The Board was accompanied by representatives of the Labor Department, MARTA, the Georgia Highway Contractors Association and the United Brotherhood of Carpenters and Joiners of America. All parties were invited to participate in the tour. Arrangements to accommodate them were made. [5] ~6 [6] After the tour there was a public hearing requested by the Labor Department and the BTD, which was held from approximately 2:00 p.m. to 7:45 p.m. Statements were made on behalf of ESA by Counsel for ESA and by an ESA official. Additional statements were made for the Building and Construction Trades Council (herein North Georgia BTC), for the International Brotherhood of Carpenters and Joiners of America, for the International Brotherhood of Electrical Workers, for the International Association of Bridge, Structural and Ornamental Iron Workers, for MARTA and for the Georgia Highway Contractors Association. Little factual data was submitted by any side which would enable the Board to take new or different bearings if it were wrong in the initial decision. /FN3/ [6] ?????????????????? /FN3/ The Ca[rp]enters representative presented additional factual data on the percentage breakdown of "building" construction at one of the sewage disposal plants. The split as reported by the project manager was 25% "building" and 75% so-called "heavy." [6] ~7 [7] BACKGROUND On November 1, 1974, ESA published in the Federal Register its decision AR-4051, a five county (Clayton, Cobb, Dekalb, Fulton and Gwinett) wage predetermination for "heavy construction". The basic hourly rates were as follows: Counties: Clayton, Cobb, Dekalb, Basic Hourly Fulton, & Gwinnett Rates Bricklayers 4.50 Carpenters 5.23 Cement masons 4.65 Electricians 9.55 * Ironworkers 6.40 Laborers: Unskilled 3.32 Pipelayers 4.06 Line Construction: Lineman 7.11 Groundman 3.84 Painters 5.00 Power Equipment Operators Asphalt Distributor Opr. 5.10 Backhoe 5.32 Bulldozer 4.48 Cranes, Derricks, Draglines 7.85 * Loader 4.15 Mechanics 5.00 Motor Graders, Motor Patrol 4.41 Oiler 5.58 * Scraper 4.00 Trenching Machines 5.69 Truck Drivers to 2.5 tons 3.56 Truck Drivers over 2.5 tons 3.75 [* Plus fringes.] [7] ~8 [8] This schedule would have been used for MARTA's three segments, CE 540, 173 and 330, had the North Georgia BTC not protested its application to MARTA work. It contended that there had been a fundamental change in the structure of the construction industry in the Atlanta area. "Heavy" work formerly performed at non-negotiated rates was now predominately performed under contracts applicable to building and commercial work at negotiated rates. In support of this position, it directed ESA's attention to a substantial number of water treatment and sewage disposal plants in Fulton and Dekalb. /FN4/ These projects in the past had been built at non-negotiated rates, but predominately if not exclusively, now were being performed under the negotiated building and commercial schedules. The North Georgia BTC contended that although these projects were now being built at negotiated building rates, nonetheless they were "heavy" construction projects. The MARTA subway and rapid rail transit system should similarly be characterized as "heavy" category work in all its parts (here the work on the three segments). These segments therefore should be built at the wage rates paid on the water treatment and sewage disposal plants or rates close to them. [8] ?????????????????? /FN4/ These projects are sometimes referred to herein as "the EPA projects." [8] ~9 [9] ESA accepted this new theory but applied it in an unusual way. It separated the work on these EPA projects into part "building" and part "heavy." In its survey it used some additional "heavy" projects. It recalled AR-4051, the area-wide determination. It issued three separate, but identical, project wage predeterminations for each of the three segments 75-GA-110, 109, and 98 on a two-county basis, as follows: HEAVY CONSTRUCTION 44-60-GA-2B Basic Hourly Rates Carpenters 7.95 * Cement Masons 6.10 Electricians 9.55 * Ironworkers: Structural 7.90 * Reinforcing 7.90 * Laborers: Unskilled 3.98 Air tool operator 5.52 * Piledrivermen 8.25 * Plumbers and Pipefitters 9.20 * Truck Drivers: up to and including 2.5 tons 3.56 over 2.5 tons 3.75 POWER EQUIPMENT OPERATORS: Backhoe 5.53 Bulldozer 7.65 * Crane 8.00 * Loader 4.24 Oiler 5.58 * Scraper 6.80 Mechanic 5.22 [9] ~10 [10] Apparently MARTA asked ESA to relate the survey back three additional months to October 1974. The result in ESA's final wage predetermination came even closer to the rates prevailing on building construction in the area. Three new and identical wage determinations, 75-GA-159, 160 and 161 which are the ones under attack in this proceeding were issued by ESA May 12, 1975 as follows: 44-60-GA-2C Basic Fringe Benefit Payments Hourly Rates H&W Pensions Vacation App.Ta Bricklayers 8.35 .35 .40 .05 Carpenters 7.95 .40 .45 .02 Cement Masons 7.25 .35 .55 Electricians 9.55 6% 7%+1% 1/2% Ironworkers: Structural 7.90 .40 .47 .07 Reinforcing 7.90 .40 .47 .07 Laborers: Unskilled 5.20 .20 .20 .05 Air tool operator 5.42 .20 .20 .05 Painters 7.70 .40 .40 .04 Piledrivermen 8.25 .40 .45 .02 Plumbers & Pipe- fitters 8.95 .35 .50 .09 Truck Drivers 3.50 POWER EQUIPMENT OPERATORS Backhoe 6.73 Bulldozers 7.65 .35 .20 .07 Crane 8.00 .35 .20 .07 Loader 7.65 .35 .20 .07 Mechanic 8.00 .35 .20 .07 Oiler 5.58 .35 .20 .07 Scraper 7.65 .35 .20 .07[10] ~11 [11] THE WATER TREATMENT AND SEWAGE DISPOSAL PLANTS ISSUE Because of current economic conditions major public works and private industrial construction found in an expanding economy have dried to a trickle in many areas. It is perhaps ironic that much major public works in the United States is held up by EPA controls while at the same time the limited number of projects that are going ahead in the Atlanta area are EPA financed water treatment and sewage disposal plants. There is also federal aid highway work which plays a part in the positions of the parties. But when the survey leading to the contested schedule was made the major construction projects outside of commercial buildings found in the Atlanta area appear to be the E[P]A projects, and some miscellaneous projects including railroad bridges and retaining walls. EPA receives or selects from the Federal Register two schedules, one for building construction and one for heavy construction. It uses both. So far as can be determined from statements in this case, EPA in the Atlanta area does not through prebidding conferences or otherwise tell bidders specifically which rates apply to certain parts of a project and which do not. Nor has EPA, we are told, policed [11] ~12 [12] appropriateness of wage rates paid so long as the minimums of either schedule were met. The Board in its Atlanta visit looked at the physical, architectural and engineering and industrial processes inherent in a typical sewage disposal plant. It adheres to its initial conclusion that these projects should be treated as "building" projects for wage predetermination purposes in this case. It is significant that as many times as the Board has asked ESA to tell it explicitly how and what it concluded were the wage rates paid for "building" and for "heavy" work by the numbers; that is, how many employees were engaged on the "heavy" side of the work and how many were engaged on the "building" side of these sewage treatment plants, just as many times ESA has been unable or unwilling to do so. Disputes over Davis-Bacon wage schedules between contracting agencies and various contractors' groups can involve fierce economic competition determinative of which groups of employees get jobs. In all cases, seeking [12] ~13 [13] fairness under Davis-Bacon principles tested by experience, the Board calls them as it sees them. In this case it has been necessary to go see what was being done because of erroneous reasons in support of both erroneous and correct positions. 1. ESA did not limit its survey to the EPA projects alone. It included undisputed and some ostensible "heavy" projects such as the cut and cover flume at the Atlanta Airport, railroad bridges, retaining walls and similar structures. The Board perceives that under the ESA contention that enough of the EPA projects should be considered heavy work to tilt the scales on the new heavy rate schedules, all heavy work in the Atlanta area henceforth will be done at building or near building rates. If hardly intended, it is a clear and unmistak[]able result of what ESA has done. It may come as a considerable surprise to FAA and the Atlanta Airport authority, to the State of Georgia and to others that because of the EPA projects all cut and cover flume work and other heavy work at the airport and all other heavy work elsewhere would now be done at building rates. [13] ~14 [14] 2. In its post hearing statement, the North Georgia BTC makes the point that there is only one recognized work classification for substantially all of the crafts in the negotiated sector of the industry and that is the building and commercial schedule. The Board is fortified by this in its conclusion that the water treatment and sewage disposal plants must stay in the building category as far as the wage determinations in this proceeding are concerned. There is no negotiated "heavy" schedule, nor can it be claimed that all heavy work in the Atlanta area or a predominate amount has been done at the building rates, except for the EPA projects. The Board does not perceive that because water treatment and sewage disposal plants are performed at the building and commercial wage rates, the construction industry in Atlanta has concluded there is no such classification as heavy work in the Atlanta area and that work of all kinds that is not highway work is performed at building and commercial wage rates. Rather the industry recognizes the "building" nature of a project such as a water treatment and sewage disposal plant. [14] ~15 [15] 3. It has been a strong contention of the BTD that since in its view, the distinction between building construction and heavy construction on water treatment and sewage disposal plants are divided by a fine thread, the Board in a review proce[e]ding should accord[] ESA the benefit of the doubt. The Board does not agree that the dividing line between building and heavy on such projects is a close question. There is no dividing line on these projects each of which must be awarded as a unitary project because of the inseparable nature of the work. Since the building work cannot be separated from the heavy work, such a distinction as far as this wage redetermination survey is concerned, cannot be made. The narrow question the Board has to decide is whether under the circumstances, water treatment and sewage disposal plants should be in or out of the ESA survey. The Board adheres to its initial conclusion that they should be excluded. [15] ~16 THE PLANNED MARTA SYSTEM AS A SINGLE ENTITY ISSUE The Labor Department's position at the initial hearing was structured to the extreme upon the foundation that ESA had considered each of the three segments to be as integrated parts of the whole planned Marta program which was to be considered an "entity" for all wage predetermination classification purposes, i.e., "one project - one entity - one 'heavy' wage schedule." The North Georgia BTC and the BTD to the same extreme persisted in this view at the September hearing in Atlanta. Counsel for ESA, perhaps being advised of our initial decision, but more likely by further consultations with ESA, apparently abandoned this position prior to the second hearing. Counsel for ESA stated in opening statement that in the future the ESA would be issuing building rate schedules, and heavy rate schedules, and even some highway rate schedules for Marta work. The significance of this was cleared up later by a representative of ESA who made a basic statement for ESA. In our August 25, 1975, decision we expressed concern at the Department's frightful gamble, for if it turned out that water treatment and sewage disposal plants in [16] ~17 [17] Atlanta were not pertinent for wage predetermination purposes to these segments of an electrified railroad then the Department was arguing for the application of the low rates of the open shop contractors to the Marta system and all its parts: to the stations, to all underground work in the downtown nucleus of the subway system, to all aerial work in built up areas, and to projects in many other places. This has been fully discussed in our initial decision. With the loss of the portion of the water treatment and sewage disposal plant wage rates relied on as the base upon which to launch the "one entity -- one heavy wage schedule," the North Georgia BTC should now be quite willing to abandon such claim. The North Georgia BTC and supporters have been almost totally occupied with this "one entity" concept and have quite belabored the Board for not agreeing that this is the way ESA as well as this Board had always done it. The Board was well aware, however, that this is not necessarily the way it has been done. We are reminded with respect to the heavy attack on the Board's August 25th decision, of the naval vessels that came out with all guns blazing and [17] ~18 [18] Withstood the storm when the seas were rough, Yet in a sunny hour fell off Like ships that have gone down at sea When heaven was all tranquility. /FN5/ For the ESA representative at the September 30 hearing, speaking for ESA and for himself, stated unmistakably, unequivocally, and with an authority based upon years of respect in Davis-Bacon work, that ESA did no such thing as had been claimed for it. It did not at all consider these three segments as parts of the planned Marta system as an "entity." Nor did it consider each of these segments as the same thing as the planned Marta system "considered as a whole." ESA considered each of these three segment projects as a "free-standing" project to be compared with other projects on the basis of their own individual project characteristics. In this the Board commendably agrees. And it is all for the good. It clears the atmosphere of a web of faulty inferences. It permits the Board to get on with some refinements in the application of the basic principles stated in the August 25, 1975 decision, and it permits the Board to consider each project before it separately and to dispose of each one separately. [18] ?????????????????? /FN5/ Author unknown to the Board. [18] ~19 [19] MARTA PROJECT CE 540 EARTHWORK AND STRUCTURES ANDERSON AVENUE TO FAIRFIELD PLACE This project is described in Marta's brief as the construction of a 4,000 foot of rapid transit-at-grade line section in Fulton County at a cost of between two and three million dollars. It includes site clearance, excavation and embankment, and fencing and seeding the site at completion of the project. The contractor does not include any track work. More specifically, the specifications include removing catch basins, pipe and fences, concreting an 18 inch culvert under Howard Street, relocating a highway sign on I-20 West; clearing, grubbing and disposing of vegetation, etc., within the indicated right of way, rough grading, excavating for concrete structures, trenching for drainage pipe, providing excavation support system, fill for embankments and slopes, and backfill for trenches and retaining walls, providing storm drains and subsurface drains, providing precast[] concrete manholes, cast in place concrete manholes, manhole foundations, dissipator and dumped rip rap, fencing, subballast, seeding and sodding, providing markers, modifying a sanitary [19] ~20 [20] sewer manhole at Howard Street, exposing supporting casing and backfilling a six-inch cast iron water main at Howard Street and other water mains similarly, providing concrete reinforcement. Under "electrical work" providing conduit, duct banks, and pull boxes. MARTA PROJECT CE-330 EAST LAKE DRIVE TO WEST TRIN[I]TY PLACE This project is described in MARTA's brief as follows: Contract CE-330 (75-GA-160) involves the construction of 4,000 feet of rapid transit line, 1,100 feet at grade and 2,900 feet of double box concrete subway section. It includes site clearance and grubbing; cut and cover excavation; decking over of Howard Street and Adair Street for street traffic; protection and relocation of existing sanitary sewer and water lines and installation [20] ~21 [21] of new storm water system with pertinent drainage structures; construction of concrete double box subway section, 18 feet high and 30 feet wide with center wall and 18-inch thick exterior walls; backfilling over the box, grading, seeding and fencing the site; and restoration and paving of streets, curbs and sidewalks. Without elaboration upon the requirements of the specifications [] for the work, the 2900 foot cut and cover subway portion are detailed in the specifications and include sections dealing with steel doors and frames, finish hardware, fire protection system [,] ventilation system, basic electrical materials and methods, distribution equipment, and grounding. [21] ~22 [22] THE BOARD SEPARATES THE CONSIDERATION OF THE APPLICABLE WAGE PREDETERMINATION FOR EACH PROJECT CE-540 AND CE-330 It is the understanding of the Board that Project CE-540 has been advertised for bids, MARTA is much concerned about an award at an early time going so far as to tinker with basic Davis-Bacon administration requirements. It suggested a set of wage rates of its own that bidders could use for bid calculations, subject to numerous conditions and contingencies. The Board has concluded under the circumstances to dispose forthwith of the wage rate issue pertaining to CE-540 while giving further consideration to the wage rate issue concerning CE-330. No inference of any kind as to the disposition of the wage issue in CE-330 would be justified. [22] ~23 [23] AN ADJUSTMENT OF THE BOARD'S AUGUST 14 DECISION IN THE METHOD OF MAKING THE WAGE PREDETERMINATION SURVEY AND CALCULATING THE APPROPRIATE WAGE RATES TO BE PAID ON PROJECT, CE 540 ESA claims that the Board strayed from the regular method by which the ESA conducts its surveys in its instruction of August 25, 1975. /FN6/ This is not the case, but the Board seeks as plain and practical an approach under routine survey methods insofar as such methods will achieve a practical result and will be based upon a representative number of employees in each craft and a representative number of projects over which there is no major remaining dispute as to similarity with project CE 540. [23] ?????????????????? /FN6/ ESA's position on reconsideration appears to be that when Congress enacted the Davis-Bacon Act, it was interested only that projects be considered to be building, heavy, or highway for project similarity purposes. In pursuance thereof, this is what ESA says it now does. The Congress could have had no such schematic arrangement in mind. First, highways did not much enter into the picture in the thirties. They did not come to the fore until the Federal Aid Highway legislation of the fifties. In the thirties, the "heavy" work category as something different from building and commercial projects was hardly thought of. As a working rule under mass production methods ESA has justification for producing the [] three schedules, building, heavy and highway in normal operations. But in the case of a challenge, the test has always been an examination of project characteristics project by project within the structure of the construction industry in the locality. In Davis-Bacon Act administration, substance, not labels, must in the end be the test. [23] ~24 [24] 1. ESA is firm in its position that the work in CE 540 is within the category of work it calls "heavy." The Board has no quarrel with ESA's determination that this project should be considered "heavy" work for wage determination purposes. 2. CE 540 is work in one segment of a planned electrified railway system. Projects most like it would be similar work on other rapid rail transit systems in the Atlanta area. It is the nature of the problem before the Board that there is none. That being the situation, the types of projects more closely related to CE 540 would appear to be other railroad projects, related railroad work and related basic heavy work. This would include, by way of example, track relocation, new road bed construction, new spur construction and connections, railroad bridges and underpasses, etc., whether or not such structures serve both highway and railroad needs. 3. A careful but expedited recheck of the survey used for wage determination 75-GA-160 should be made. The survey recheck should carefully examine the developmental sequences on railroad and related heavy construction [24] ~25 [25] operations to make certain that all crafts which have worked on such projects are fairly accounted for. If only the peak payroll for all crafts is used by the time the largest number of employees are on a job it appears that a number of employees such as ironworkers may have been left out altogether. We find little in the data submitted with respect to a realistic ironworkers rate, but the projects submitted for wage data purposes could not be built without one. For instance the ESA survey of project Fulton 6, Marietta Bridge over Southern Railroad which is described by MARTA as a "structural steel superstructure," reflected no ironworkers, and the survey of the airport project,a $4,400,000 cut and cover reinforced concrete tunnel reflected one reinforcing ironworker at $2.50 and one structural ironwork at $3.60. These rates correspond to the range of rates paid laborers on this job. 4. The survey recheck although expedited should examine all known work clearly identified as heavy work. This would include, by way of example, such projects as cut and cover flumes for diverting the Flint River at the Atlanta Airport and the projects already included in the wage determination of May 12, 1975 for 75-GA-160. [25] ~26 [26] The Board takes note of the uncooperative attitude as reported by the North Georgia BTC of at least one principal contractors' association early this year in supplying labor organizations with which it deals with project data to be used for Davis-Bacon survey data. Full cooperation when backed by Marta at this stage should be assured. The North Georgia BTC will have the opportunity if it proceeds with the required expedition to establish its claim that much railroad projects and other uncontested heavy type construction projects in the Atlanta area are done at the negotiated building rates. 5. The Board notes from wage data submitted in this case that projects already included in the survey leading to 75-GA-160, May 12, 1975, reflect loose if not illusive classifications of work and of crafts. For example, there may be projects in which "carpenters" are paid anywhere from $2.60 to $5.00 an hour, and iron workers are paid at laborers' rates. ESA must approach that kind of wage data with skepticism, must look for the true journeymen's rates exclusive of learners and apprentices and must not be taken in by misclassifications of work or by underpayments. [26] ~27 [27] ESA should certainly disregard rates taken from Davis-Bacon jobs on other projects which reflect misclassification or underpayment. The finally established wage schedules may not achieve perfect balance between crafts, but they are going to have to make common sense in the construction business for CE 540. 6. The survey recheck will exclude all water treatment and sewage disposal plants. /FN7/ It will exclude at this step of the survey recheck of all work on highway heretofore excluded by ESA. It is the Board's preference and direction that ESA exhaust all material in the "heavy" data base to develop an appropriate wage schedule for CE-540 so that recourse to highway bridge contracts heretofore excluded will be necessary only as a matter of last resort. 7. With respect to the above six survey recheck items, the Board, in effect, is directing ESA to revert to the methods and practices existing prior to the protest by the North Georgia BTC over ESA's non-use of water treatment and sewage disposal plants.[27] ?????????????????? /FN7/ Footnote 8 of the Board's opinion of August 14 identified these projects that were included in the ESA survey. It now appears questionable that Projects Fulton 5 and Fulton 14 are water treatment of sewage disposal plants. If these or any others listed in footnote 8 are, in fact, not water treatment or sewage disposal plants the Board is not asking that they be excluded. [27] ~28 [28] If the survey recheck yields the substantial and sufficient data based upon which a practical "heavy" wage predetermination can be made for project CE-540 with crafts showing a sensible relationship to each other ESA will not have to inquire further to secure a large base for wage data information. 8. If upon completion of the survey recheck under the foregoing seven items, ESA concludes that the reported and collected information is not reasonably sufficient to depict the local employment situation on a "heavy" project such as CE-540, ESA is authorized to expand the survey to include the major bridge projects on highway work awarded under separate bridge contracts. The Board does not share the views that have been expressed that if any such bridge projects enter into the wage data base for the "heavy" work on contract CE-540, it inevitably follows that later such higher "heavy" wage rates will become the mode for subsequent highway bridge projects. In this respect we cannot see that the situation will change much from the time when, as the Board understands the situation, highway work found its way into "heavy construction" wage rate schedules such as AR-4051 of November 1, 1974. [28] ~29 THE "TWO COUNTY DETERMINATION" ISSUE The Board concluded in its August 14 decision that separate wage determinations for Dekalb County and Fulton County would be in accordance with ESA practice. See WAB 71-04, Virginia Segment C-7, Metropolitan Rapid Rail Transit System. /FN8/ The Labor Department does not ask that a separate rate be established for the City of Atlanta and one for the rest of Dekalb County or for the City of Decatur alone. The Department submits that the City of Atlanta is in both counties. Although the county is most frequently found to be the appropriate local political subdivision for wage predetermination purposes often some lesser or a larger area is used. The Board concludes that there may not be sufficient projects in either County taken alone for similarity comparisons to yield a representative number of employees in each craft. Accordingly, ESA is authorized under the [29] ?????????????????? /FN8/ In Sweet Home Stone Company, WAB 75-01 and -02 decided by the Board on August 14, 1975, ESA advised the Board that it had explicitly provided two schedules one "heavy" and one not heavy for separate projects closely related in time, place and function at the W. D. Mayo Lock and Dam on the Arkansas River. [29] ~30 [30] circumstances and at its election to use a two-county schedule for project CE-540 if it concludes that there is not a sufficiently representative number of employees engaged upon the work in either one of the Counties to provide a sensible survey base. THE BOARD'S REVIEW FUNCTION ISSUE The Board cannot agree with Counsel for the BTD on the review functions of the Board in WAB proceedings. The Board's review authority is not so limited. Suffice it to say that where the issue as here is whether the ESA properly included in its wage survey "projects of a character similar to the contract work" such a matter is not only a proper subject of Board review, it is a run of the mill matter. A comparison of the factual particulars of CE 540 taken from the specifications with the factual particulars of water treatment and sewage disposal plants will speak for itself. Such a comparison should dispel from the mind of anyone conversant with the construction industry that these are not projects of similar construction characteristics. The Board, which values the judgment of the principal associations of contractors and labor organizations that bring problems to it, thinks that the attack upon the Board's right to review in this situation creates an [30] ~31 [31] erroneous impression. The problem here is simply that the North Georgia Building and Construction Trades Council took a shot at garnering in all work on the entire planned MARTA system by claiming that water treatment and sewage disposal plants were only "heavy" type construction, and not building type construction. But ESA itself did not accept that entire package. It said some parts of these unitary projects were not building construction. But ESA has never explained the formula upon which it made its calculations dividing the work. These water treatment and sewage disposal plants cannot be readily separated and there is no evidence any separation was tried. And ESA did not conclude that CE 540's characteristics were to be determined by the characteristics of other parts of the planned MARTA system which may not be like CE-540. As the Board said in its initial decision: The facts have not changed enough to justify the conclusion that the classification of heavy work has in some inexplicable way swung all the way from the highway side of the wage pendulum to the building side. The acceptance of the change in labels by ESA was not an exercise of a "fair choice of judgment" as counsel for BTD suggests. It is the kind of error that this Board sits to [31] ~32 [32] correct. This is particularly so (1) where the consequences of such an error are far reaching, and (2) where the error is compounded by the claim made at the time that all of the planned MARTA system as an entity must be in the same category of work. The Board in its initial decision pointed out that such a claim had alarming felo-de-se qualities. SUPPLEMENTAL CONCLUSION 1. Except as modified under the "Adjustments for CE-540" and the "Two County Determination" headings herein, the Board's decision of August 25, 1975, is unchanged. A decision on CE-330 will be made with reasonable dispatch. 2. There is nothing in the Board's August 14, 1975, decision that would preclude ESA from issuing wage determinations based upon building and commercial rates on segments of the MARTA system where ESA finds such rates to be warranted under its usual administrative practices. MARTA likewise or other interested parties will be able to challenge if they wish any such predeterminations without prejudice by reason of the August 25, 1975, decision. 3. The Board observes as it did in its initial decision, that all parties would be in a better position to make future plans if they would mutually assess the situation with a view of arriving at some understanding instead [32] ~33 [33] of continuing with some of the things brought up at the Atlanta hearing. The Board cannot go beyond such a suggestion. Because of MARTA's intention to be its own general contractor for much of the work it necessarily will become involved under contract administration with required Davis-Bacon standards and in their enforcement. The Board still observes that for both labor and management locally there must be a better way to run the railroad. ORDER The Employment Standards Administration is directed to proceed forthwith in accordance with Davis-Bacon Act procedures and the directions herein to come up with a new project wage rate schedule for MARTA Project CE 540. All parties and intervenors in this proceeding are requested to cooperate fully with ESA in its review so that a pragmatic set of wage rates under Davis-Bacon Act requirements will be established for CE 5400. SO ORDERED: (s) Oscar S. Smith, Chairman (s) Clarence D. Barker, Member (s) Stuart Rothman, Member [33]



Phone Numbers