skip navigational links United States Department of Labor
May 9, 2009        
DOL Home > OALJ Home > USDOL/OALJ Reporter
DOL Home USDOL/OALJ Reporter

Vinnell Corp., WAB No. 73-07 (WAB Sept. 14, 1973)


CCASE: AMERON, INC. DDATE: 19730914 TTEXT: ~1 [1] WAGE APPEALS BOARD UNITED STATES DEPARTMENT OF LABOR WASHINGTON, D. C. In the Matter of: Applicability of the Davis-Bacon and Related WAB Acts to Certain Fabrication Activities of Ameron, Inc., Subcontractor to Vinnell Case No. 73-07 Corporation, Prime Contractor on U.S. Department of the Interior, Bureau of Dated: September 14, 1973 Reclamation Contract No. 14-06-D-7223, Navajo Indian Irrigation Project, New Mexico. Vinnell Corporation and Ameron, Inc. Albuquerque, New Mexico APPEARANCES: Robert R. Tinnin, Jr., Esquire for the Petitioners, George E. Rivers, Esquire, Counsel for Construction Wage Standards, Office of the Solicitor and Counsel for the Assistant Administrator, Wage and Hour United States Department of Labor Thomas X. Dunn, Esquire, Associate General Counsel for the Building & Construction Trades Department, AFL-CIO and for the International Brotherhood of Electrical Workers, Washington, D.C. [1] ~2 [2] BEFORE: Oscar S. Smith, Chairman, Wage Appeals Board, Stuart Rothman and Clarence D. Barker, Members DECISION AND ORDER This case /FN1/ is before the Wage Appeals Board on the Petition of Vinnell Corporation and Ameron, Inc., prime contractor and subcontractor, respectively. Vinnell Corporation was awarded a contract in the sum of $14,753,240 by the Bureau of Reclamation on January 19, 1972 for the construction of siphons, a tunnel, a concrete-lined canal, and an access road. Under the contract Vinnell is required to furnish and install some 16,000 lineal feet of pipe having an inside diameter of approximately 17-feet in 20-feet sections, each valued at about $12,000 and weighing about 150 tons (reportedly the largest pipe ever produced in the U.S.). The purpose of the project is to syphon, pipe channel, and cause water from Navajo Lake to reach approximately 110,000 acres of Navajo Indian land so that such land can be irrigated. The specifications gave Vinnell the option to construct the pipe in place by traditional construction processes or he could elect to fabricate the pipe in prestressed sections. Vinnell elected to furnish and place concrete cylinder prestressed pipe and contracted with Ameron, Inc., to [2] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN1/ This case may be cited as the Navajo Indian Irrigation Project, New Mexico, WAB 73-07. [2] ~3 [3] fabricate and install the pipe. Ameron constructed the fabrication plant about 8 miles south of Bloomfield, New Mexico. It is located adjacent to the route of the pipe line project. Enormous-sized equipment is necessary to handle the forms and the pipe sections during placing and tamping the concrete, steam curing the sections to the required strength, wrapping the core with steel wire under high tension, coating the wrapped core with a mortar encasement and then steam curing each to its required strength. The adequacy of highways and the bridge, railroad, and highway restrictions relating to size and weight of loads, resulted in a need for the pipe manufacturer to erect the fabrication facilities near the work-site. Special equipment is required to tilt the upright sections onto special transportation equipment and move the units directly to the point of installation. The fabrication facilities of Ameron and the site construction headquarters of Vinnell are designated by signs as construction areas, and the only separation between them is a fence. Ameron is manufacturing the concrete pipe exclusively for use on the irrigation project and has not manufactured any other product at this location. Currently, the pipe plant is about 1-1/2 to 2 miles from where the pipe is to be laid in the ditch. As construction progresses, the distances will vary from 1-1/2 to 12 miles. Aside from 4 employees being paid not less than the predetermined craft construction rates (a field mechanic, 2 laborers and an operating engineer who constitute the pipemobile crew that transport the pipe to and install it in the ditches), Ameron's employees are paid for fabrication of the pipe [3] ~4 [4] in accordance with a production agreement with Laborers Local Union No. 16. This agreement although specifically bargained for manufacturing activities at the Bloomfield operation. Vinnell has agree to the Statewide construction agreements of the Operating Engineers and the Laborers, as has also Ameron with respect to its installation work (e.g., the pipemobile crew). The rates and classifications in these Statewide construction agreements differ substantially from the rates and classification negotiated between Ameron and the Laborers Union for plant fabrication work in New Mexico. Petitioners question the March 9, 1973, decision of the United States Department of the Interior, Bureau of Reclamation, directing the contractor to require Ameron to classify and pay its employees engaged in the fabrication of the prestressed pipe above-described in accordance with the Davis-Bacon Act requirements of the contract. The ESA predetermination specified prevailing wage rates for traditional on-site construction work. The Bureau of Reclamation's directive to Vinnell Corporation of March 9, 1973, is based upon a ruling of January 22, 1973 by the United States Department of Labor, Employment Standards Administration. In its March 9, 1973 determination the Bureau reversed its prior determination of June 12, 1972, that work performed at Ameron's pipe fabrication facility located near Bloomfield, New Mexico, was not subject to the Davis-Bacon Act because the facility was considered to be an off-site manufacturing facility. [4] ~5 [5] Counsel for the Assistant Administrator, Employment Standards Administration, Wage and Hour Division (ESA) has set forth the principal issue in this matter as follows: . . . "whether under the provisions of the Davis-Bacon Act and the applicable regulations of the Secretary of Labor the activities of Ameron, Inc., in the manufacture and fabrication of pipe adjacent to the installation or project site constitute those of a subcontractor or a materialman." It would appear that Counsel for ESA has predicated the issue on acceptance of the idea that fabrication of prestressed concrete pipe in 20-feet sections, 17-feet in diameter, and weighing 150 tons is a manufacturing process. On this basis he then states the issue to be whether such manufacturing "adjacent to the installation or project site" constitutes the work of a subcontractor or a materialman. The Wage Appeals Board views the issue somewhat more basically: -- Is the disputed work covered under the Act and, if so, what classifications and wage rate apply? This case presents difficult questions stemming from alternative technologies now available within the construction industry. Such questions must be approached with caution on a case-by-case basis. Caution also must be exerted against possible abuse in a case in which a contractor seeks to remove traditional and customary on-site construction work to process such work at another location -- allegedly "off the site" -- under a non-sustainable claim that by so doing, the work has been removed from Davis-Bacon Act coverage. The original Congressional purposes of the Davis-Bacon and related [5] ~6 [6] Acts continue unabated and undiminished, but it was never the purpose of the Act that, by requiring payment of the prevailing wages to laborers and mechanics for construction on the construction project sites, all existing processes, manners and means of effectuating construction work were to be placed in a straitjacket barring forever fundamental technological changes with attendant changes in the composition of the working force necessary to prosecute such developments. A fair balance must be achieved between what is permissible as basic fundamental changes in technology, and what may be discerned to be actual abuse of Davis-Bacon principles. The way this case was structured for presentation to the Wage Appeals Board, it appears to the Board that the parties in seeking a decision from the Board on the question whether the disputed work was done "on the site of the construction project" believe that they will be a long way toward bolstering their respective positions as to whether Ameron's assignment of the work under the Laborers' plant fabrication contract was proper or improper, or whether, stated another way, certain of that work should or should not have been awarded to the Operating Engineers and possibly to other crafts. As we have said before, the Wage Appeals Board has not been established and is not normally in the business of resolving jurisdictional disputes. As a fallout of a Board decision, a jurisdictional dispute may possibly be resolved in some circumstances. The Wage Appeals Board cannot say that under no circumstances would it resolve a matter which may be considered jurisdictional, [6] ~7 [7] if such a dispute went to the very heart of Davis-Bacon administration. However, the Board believes that this is not such a case. Accordingly, it will not determine the appropriate assignment of the work. /FN2/ Counsel for ESA cites to the Board, as he did to the Bureau of Reclamation, the Department's All-Agency-Memorandum #86 of February 11, 1970 as reflecting "essentially" the Department's position with regard to what constitutes the "site of the work" for Davis-Bacon purposes: The `site of the work' is limited to the physical place or places where the construction called for in the contract will remain when work on it has been completed and to other adjacent or nearby property used by the contractor or subcontractor in such construction which can reasonably be said to be included in the `site' because of proximity. For example, if a small office building is being erected, the `site of the work' will normally include no more than the building itself and its grounds and other land or structures `down the block' or `across the street' which the contractor or subcontractor uses in the course of his performance on the particular contract. In the case of larger contracts, such as for an airport or a dam, the `site of the work' is necessarily more extensive and includes the whole area in which the contract construction activity will take place. Fabrication plants, `mobile factories', batch plants, borrow pits, job headquarters, tool yards, etc., are part of the `site of work' provided they are dedicated exclusively or nearly so to performance on the contract and are so located in proximity to the actual construction location that it would be reasonable to include them. [7] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN2/ It should be noted that this Board does not hesitate to review the appropriate classification or misclassification of employees but this is for wage rate purposes as distinguished from work assignment or union representation purposes. [7] ~8 [8] But Counsel for ESA points out that the statutory definition remains unchanged with respect to dams, highways, pipelines, etc., and meant to include the site of the work for a canal which is extensive and could include a larger area in which the contract construction activities will take place. The Wage Appeals Board has no difficulty in agreeing with Counsel for ESA that under the facts and circumstances of this case Ameron's current Bloomfield operation is "on-site work" and the work of fabricating the prestressed concrete pipe falls under Davis-Bacon Act coverage. Apparently Vinnell Corporation believed likewise as reflected in its May 17, 1972 letter to the Project Construction Engineer, submitting the April 30, 1972 agreement between Laborers Local 16 and Ameron covering Ameron's pipe manufacturing facilities in New Mexico, and requesting approval by the Bureau of special craft wage rates (not otherwise specified in the subject construction contract) for the manufacture of concrete prestressed pipe at the Bloomfield site. /FN3/ * * * * Ameron advises that it is phasing out its Albuquerque operation (where apparently there is little or no current or project demand for 17-feet diameter and similar large pipe) and relocating in the Bloomfield or so-called [8] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN3/ It is clearly a part of the project under judicial concepts involving the Fair Labor Standards Act. See Archer v. Brown & Root, Inc., 241 F.2d 663, concerning prestressed concrete sections of the Lake Pontchartrain Causeway, 25 miles long, the world's longest bridge. [8] ~9 [9] Four Corners area because of this area's alleged future potential for large pipe fabrication projects. However, Ameron has failed to demonstrate that its current Bloomfield fabrication operation is that of a materialman serving the general public. Ameron is not manufacturing and stockpiling standard pipe for general sales at Bloomfield. Rather, it set up this facility adjacent to Vinnell's facilities after receiving its $9,000,000 subcontract from Vinnell and it currently is geared up to fabricate only these huge prestressed concrete 20-feet long sections of pipe weighing some 150-tons each called for by the Vinnell contract. The entire output of the Bloomfield facility is this unusually large pipe for the Vinnell contract on the job in question. Ameron's contract and present total commitment is to do this fabrication of prestressed pipe. Whatever future work may be undertaken by Ameron, the pipe fabrication plant was located at Bloomfield to make this pipe for this irrigation project, and any plans beyond that remain conjectural at this time. It appears from its position of the ESA and the Petitioner that once the Board would conclude that the work in question is performed on the site of construction, that's all there is, and the Board has decided all issues in this dispute en banc. But the ESA and Petitioner have avoided any reference to the appropriate classification of the work and corresponding wage rates. It was suggested at the July 27, 1973 hearing and it is indeed a serious contention that once it is determined that the prestressed concrete pipe sections are being fabricated on the project site, the employer should [9] ~10 [10] use wage rates of, for example, iron workers for inserting reinforcing rods, carpenters for certain form work, laborers for various types of unskilled labor, operating engineers for handling and moving equipment usually assigned to operating engineers, and since there is a considerable amount of concrete and cement work, the usual assignments should also be made to cement masons and other crafts as if the work were performed under the conventional construction option. The Wage Appeals Board must when presented with a case look at the whole matter and seek to achieve a result which under the circumstances will be in keeping with the purposes of the Davis-Bacon Act and fair to all within the strict mandate of the Act that government contracting shall not be used to downgrade achieved prevailing wage rates. But the Board also believes that the Davis-Bacon Act is not a negative act imposing the dead hand of the past upon currently recognized and accepted fundamental changes is construction technology. This is so particularly when it can be plainly perceived that the purpose of prosecuting the work under such technological changes is not to subvert or circumvent the remedial purposes of the Act. The Board has encountered no particular difficulty in finding the disputed work a part of the irrigation project performed at the site. It is equally significant to consider what are the appropriate classifications and wage rates for this work. Wage rates for the fabrication of this kind of pipe are reflected in the Laborers rates negotiated April 30, 1972 at Albuquerque by Ameron, Inc., New Mexico Operations, and Laborers Local [10] ~11 [11] Union No. 16, with Statewide jurisdiction, and covering Ameron's "pipe manufacturing facilities in New Mexico". At the same time, the same Laborers Local has construction agreements with other firms and covering work on the site apart from pipe fabrication. With respect to the latter, there is no indication in the record that Laborers Local 16 ever raised any issue at Bloomfield that construction laborers rates should supplant the pipe fabrication schedule it had negotiated Statewide with Ameron. The Board concludes that under the circumstances of this case it would not effectuate the purposes of the Davis-Bacon Act to require that the subcontractor's established work classifications for the fabrication of 17-feet prestressed concrete pipe in 20-feet sections must be abandoned when the subcontractor comes onto the project site and that he must reclassify employees as though he performed the work under the other option. We cannot conclude that on this canal and irrigation project in the Four Corners area of New Mexico the pipe-fabricating subcontractor is required to use classifications and pay wage rates different from the job classifications and wage rates which in fact have heretofore been utilized to perform this type of fabrication work within this geographical area. Nor does the Wage Appeals Board see how it would effectuate the purposes of the Davis-Bacon Act to require this subcontractor utilizing the processes upon which the rates of pay and working conditions have been negotiated with Laborers Local 16 in a preexisting agreement to pay a higher set of wage rates negotiated by the same union and reflecting rates [11] ~12 [12] prevailing in the locality for work when performed in a traditional and customary way on the site of construction. /FN4/ * * * * The Wage Appeals Board having considered the entire record before it, including the written and oral statements of the parties and labor organizations of interest, has reached the following conclusions and requests the Assistant Administrator, ESA, to observe the following procedures: 1. The work of manufacturing or fabricating the prestressed concrete sections 17-feet diameter, 20-feet long, and weighing 150 tons apiece, is work covered under the provisions of the Davis-Bacon Act and the definitions of coverage set forth in Regulations, Part 5 of the Secretary of Labor, and as such requires the predetermination of appropriate wage rates. 2. The work in question is performed or prosecuted "at the site" of the project under the circumstances here involved. 3. The contractor and his subcontractor are entitled to use the same processes, manner and means of manufacture or fabrication used by the subcontractor in the past and at the wage rates prevailing in the area for work so prosecuted. The locality under the circumstances is and includes the Four Corners area of New Mexico (as well as Albuquerque where the contract was initially signed). The wage rates applicable are [12] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN4/ Under the circumstances of this case, the wage rates prevailing for all the plant work in question are the negotiated rates inasmuch as these are the rates paid in the Four Corners area of New Mexico and there is simply no evidence of record of any other rates pertaining to this type of work. [12] ~13 [13] those negotiated by this subcontractor and Laborers Local Union 16 of Albuquerque and specifically covering the "Company's pipe manufacturing facilities in New Mexico" (including the Four Corners area.) There are no other wage rates for this work in this area and these rates have in fact been paid in the past in the locality for this type of work. 4. The Contract specifications gave this contractor and his subcontractor the election to prosecute the work by (a) traditional construction means using concrete form work and pouring in place, or (b) by using a changed technology of fabricating prestressed concrete pipe in 20-feet sections 17-feet in diameter, and weighing 150 tons per section. The contractor in electing to prosecute the work by a process and means different in nature from the more traditional in place construction methods did not violate the contract provisions by paying rates prevailing for such work done under option (b). The bargained rates under the circumstances in this area constitute the prevailing rates for the plant fabrication work at this time. If in the future Ameron should get other contracts, Davis-Bacon coverage, if any, and the rates for these contracts must stand on the facts at that time. 5. The ESA Administrator shall determine and establish a schedule of wage rates for a classification of work identified as "prestressed concrete pipe (fabrication only.)" The Wage Appeals Board does not in this decision make a determination that any particular craft or class of employees is entitled to the assignment of the disputed work; only that the work in question shall be performed at the prevailing wage rates at which such work has been heretofore performed in the Albuquerque - Four Corners area of New Mexico even though it is concluded that said work is under the circumstances work performed at the site of project construction and is hence subject to a wage predetermination. [13] ~14 [14] The Bureau of Reclamation and ESA shall process this matter under the classification and reclassification procedures of the contract and regulations. SO ORDERED Oscar S. Smith, Chairman Stuart Rothman, Member Clarence D. Barker, Member [14]



Phone Numbers