skip navigational links United States Department of Labor
May 9, 2009        
DOL Home > OALJ Home > USDOL/OALJ Reporter
DOL Home USDOL/OALJ Reporter

General Exhibits, Inc., WAB No. 1972-11 (WAB Feb. 28, 1973)


CCASE: GENERAL EXHIBITS, INC. & RHOMBI-12, LTD. DDATE: 19730228 TTEXT: ~1 [1] WAGE APPEALS BOARD UNITED STATES DEPARTMENT OF LABOR WASHINGTON, D. C. In the Matter of: GENERAL EXHIBITS, INC. WAB Case No. 72-11 & RHOMBI-12, LTD. A Joint Venture, Prime Contractor TRIM CONSTRUCTION CORP. Subcontractor Compliance with Labor Standards Requirements of the Davis-Bacon and Related Acts under Contract No. DOT-FA72WA-2766, Transpo 72 Project, Dulles International Airport, Virginia by General Exhibits, Inc., and RHOMBI-12, Ltd., a Joint Venture (Prime Contractor), and Trim Construction Corporation Dated: (Subcontractor) February 28, 1973 General Exhibits, Inc., and RHOMBI-12, Ltd., a Joint Venture, Petitioner Appearances: Murray M. Chotiner, Esquire, Washington, D. C. for the Petitioner George E. Rivers, Esquire, Counsel for Construction Wage Standards, Office of the Solicitor, United States Department of Labor Thomas X. Dunn, Esquire, Associate General Counsel for the Building and Construction Trades Department, AFL-CIO and for the International Brotherhood of Electrical Workers, Washington, D.C.[1] ~2 [2] Mr. Thomas L. Jones, Labor Advisor, Federal Aviation Administration, Department of Transportation Before: Oscar S. Smith, Chairman, Wage Appeals Board, and Stuart Rothman, Member DECISION OF THE WAGE APPEALS BOARD In 1971, the Department of Transportation was authorized to establish and conduct an International Transportation Exposition to provide the United States Transportation industry and related science the opportunity to display their exportable products. Dulles International Airport, located in both Fairfax and Loudon Counties, Virginia, 29 miles west of Washington, D. C., was selected as the site for the Exposition (Transpo 72) scheduled to run from May 27 through June 4, 1972. Dulles Airport is owned by the United States government and operated by the Department of Transportation. To house the transportation exhibitors during Transpo 72, the Department of Transportation required a number of temporary structures. Accordingly, contracts were awarded by the Federal Aviation Administration (FAA), including the one currently in dispute involving the Petitioner. This was a negotiated contract effective December 10, 1971, in the amount of $384,000 for the furnishing of certain buildings. Instead of using a construction- type contract, including the usual provisions of the Davis-Bacon Act, the Contract Work Hours and Safety [2] ~3 [3] Standards Act (CWHSSA), the Copeland Act, and the Miller Act, FAA utilized a lease contract with no Miller Act payment bond requirements. It did include: a) Standard Form 23-A (Construction contract General Provisions); b) Standard Form 19-A (Labor Standards Provisions Applicable to Contracts in Excess of $2,000 -- i.e., Davis-Bacon Act, CWHSSA, and Copeland Act provisions); and c) Standard Form 32 (Supply Contract General Provisions). The contract described the work as: Lease, erect, and remove prefabricated buildings for use as business centers at the U. S. International Transportation Exposition (Transpo 72). On the contract form, the work was further described under the headings "Supplies/Services," "Quantity," and "Unit Price," respectively, as follows: 1. Lease single unit with minimum of 800 sq. ft. -- 20 at $3,600 each; 2. Lease double unit with minimum of 1,600 sq. ft. -- 13 at $7,200 each; 3. (a) Lease triple unit with minimum, of 2,400 sq. ft. -- 18 at $10,800 each (b) Lease triple unit with minimum of 2,400 sq. ft. (configural single/double) -- 1 at $10,500; and [3] ~4 [4] 4. Lease Reception Center with minimum of 3,000 sq. ft. -- 1 at $13,500 Despite the procurement arrangement being cast as a lease contract with overtones throughout of a supply contract, FAA included in the contract specifications Wage Determination No. AM- 1,842 of August 20, 1971, as modified by Modification No. 1 dated October 22, 1971. This was an area wage determination reflecting generally the Washington, D. C. prevailing wage rates. It specified that it was applicable to Montgomery and Prince Georges Counties, Maryland; City of Alexandria, Virginia; Arlington County, Virginia; and Dulles Airport for "Building Construction (excluding single family homes and garden-type apartments up to and including 54 stories), and Dredging." It contained, among others, the following classifications and wage rates (including fringe benefits) which are pertinent to the matters under consideration: Carpenter $7.37; Glaziers $7.44; Laborers $5.72; Composition Roofers $6.20; and Roofers Helpers $4.90. The lease contract specified a kind of structure parts of which were somewhat innovative in nature, using panels which formed unique geometric patterns in the roof called "rhombic." /FN1/ The panels used [4] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN1/ A "rhombus," says Webster's Seventh New Collegiate Dictionary is "an equilateral parallelogram having oblique angles." The top of the structure was composed of several panels joined together creating a surface of diverse angulations. [4] ~5 [5] for the roof or top of the structures were interchangeable with those used for the walls. According to the Petitioner, the panels and the structures were designed to be used mainly for residential housing. The prefabrication plan technique purportedly was such as to allow for disassembling, shipping, and re-using the panels for other buildings; such panels having been primarily used or were to be used, according to the Petitioner, for building camps and low-cost housing. The panels were covered with fiberglass, with an aluminum edge. They contained no additional roofing membrane or other weather protective material. To assemble, they were bolted one to another while on the ground, with the bolts going through predrilled pipe. The panels were not prefabricated to meet the Dulles job alone. The parts used for the roof or top were single (assembled on the ground) 63-foot configurations raised by crane and bolted to other configurations. The wall panels were plywood, joined by single headed nails, one edge of the panel to the adjacent panel. The panels were nailed together flat on the ground and raised into positions and nailed to the deck. The corners were nailed when joining the panels together. These panels also were pre-engineered and pre- constructed by carpenters and machines off-site at the prefabrication shop. One reason Petitioner accepted the Dulles contract was to be able to get publicity for what Petitioner considers a unique building technique for housing. These structures, however, when in the process [5] ~6 [6] of being erected, were notably fragile and unable to withstand high winds. /FN2/ In fact, when Petitioner's contract was terminated, the Philadelphia contractor who completed the job used standard modular construction methods. Although the rhombic concept looked elaborate, Petitioner stressed that the actual site assemble does [*] not [*] require any special skills. [*Emphasis in original*] The skills, Petitioner stated, are those utilized by the shop employees in Delaware where the prefabrication work was performed. The site assembly "roof" work was done under the supervision of "site architects" and "project managers." The tools used on site were socket wrenches for zinc bolts made specially for the Petitioner. As to the tops of the structures, after being assembled on the ground a crane lifted them up where they were simply secured to the walls by bolts. None of the other contractors at Dulles on the Transpo 72 project used the rhombic system. The Petitioner started its work under the contract at Dulles in January of 1972. Trim (the one subcontractor also found in alleged violation of the Davis-Bacon Act and CWHSSA) started its work in March of 1972. On April 24, 1972, the structures in the process of erection by Petitioner collapsed under a relatively mild 30-miles-per hour wind [6] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN2/ The WAB is not concerned with the performance or nonperformance of the contract but with the nature of the construction for Davis-Bacon purposes. [6] ~7 [7] and, on the same date, FAA terminated the Petitioners's contract. FAA thereafter awarded a contract for the needed structures to another firm which met the construction deadline, using standard modular housing techniques. From January, 1972, to April, 1972, the Petitioner submitted to FAA the payrolls require under the contract terms. They consistently showed "Laborers" at the contract rate of $5.72 per hour. Also shown were a Superintendent at $8.49 per hour, and Project Manager W. Macleod Snaith and several site architects who obviously were on salary and not deemed "laborers and mechanics" within the meaning of the Davis-Bacon and related Acts. Subcontractor Trim was on the job site only a short time. That firm never did submit payrolls. The record indicates that Trims's employees were paid $6.00 per hour. Counsel for Petitioner further stated that their were regular employees, employed year- round at $6.00 per hour, with 2-weeks paid vacation. Counting other fringe benefits, Counsel stated that their actual hourly pay would average $10.50 per hour. On March 2, 1972, the Petitioner requested approval by FAA of two classifications not contained in the contract wage determination, namely, "Panel Assemblers" at a basic rate of $5.19 per hour, and "Panel Assemblers Helpers" at a basic rate of $3.64 per hour. On March 8, 1972, the Contracting Officer approved the new classifications, but at $7.00 and $5.45 per hour, respectively. [7] ~8 [8] Some time thereafter, on receipt of complaints from the Carpenters Union regarding this job, the March 8th approval was withdrawn by the Contracting Officer and a field investigation was made by the Wage and Hour Division of the Department of Labor. As a result, those employees of the Petitioner who had been paid $5.72 an hour for "assembling prefabricated fiberglass panels into roof sections" were found due the Composition Roofers' rate of $6.20 per hour; and those employees of Trim who "installed wall and floor panel assemblies" at $6.00 per hour, were found due the Carpenters' rate of $7.37 per hour. A total of 26 employees of the Petitioner were found to be due a total of $1,241.64 in straight- time amounts under the Davis-Bacon Act; and 19 were found due $31.69 for overtime premiums under the CWHSSA. Liquidated damages under the CWHSSA of $100 were also computed. In addition, 15 employees of subcontractor Trim were found due $4,118.33 in straight-time back wages under the Davis-Bacon Act; and 11 employees were found due $971.60 under the CWHSSA, with liquidated damages computed at $1,400. * * * The question in this case important to Davis Bacon administration is whether the procurement arrangement between FAA and Petitioner was a lease. For if under the circumstances this arrangement was a straight lease by the government (for the short period of only about [8] ~9 [9] one month) of premises owned by the Petitioner the provisions of the Davis-Bacon Act would not apply. /FN3/ One of the Petitioner's contentions in this matter is that the procurement arrangement was a lease; -- FAA called it a lease because it was a lease. Petitioner cited the following language of the Comptroller General in 452 Comp. Gen. 47 (1962): We know of no case in which the Davis-Bacon Act has been interpreted to apply to agreements for use of occupancy of construction, as distinguished from actual acquisition. . . . The contention is a serious one. The FAA's characterization, the limited use and occupancy by the Government, the requirement of immediate removal by the contractor all lend credence to that view, [9] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN3/ The Department of Labor has rendered opinions regarding noncoverage of lease contracts (even though the situations involved alterations and repairs and event the construction of buildings). In Lease-purchase contracts "to build, lease and convey, a bidder agrees to execute a ground lease as lessee of Government-owned land; erect certain buildings on the land; and, upon completion of the buildings, execute a lease-purchase agreement which will provide for the vesting of title in the Government at or before the expiration of the leasehold term. Such contracts are agreements for construction of buildings to which the United States is a party and the leasing of the buildings is only incidental to the construction. The determination as to the applicability of the Davis-Bacon Act is dependent upon whether the work to be performed consists of public buildings or public works of the United States. . . . While the building may be constructed with private funds, the cost of construction is eventually paid for from appropriated funds." (See Comp. Gen. Dec. B-122382 of June 27, 1955.). [9][FN3 CONTINUED ON PAGE 10] In straight lease contracts involving construction financed entirely with private funds, the only relationship between the Federal Agency and the contractor is that of lessee and lessor. In an opinion of May 4, 1956, the Solicitor of Labor advised that "Under this arrangement, which materially differs from a lease-purchase situation, none of the labor standards generally applicable to Federally-financed or assisted construction would apply. This conclusion was predicated on the statutory scope of the Davis-Bacon Act which by its terms is applicable to contracts to which the United States is a party for the construction of public buildings or public works of the United States, which require or involve the employment of mechanics or laborers." [END FN3] ~10 [10] or to the view that this was a contract for supply and not construction. However, looking at the transaction as a whole, the substantive general conditions applicable to site work on Federally-owned property, the nature of the specifications for site work, the working drawings and the methods of payment, the Board concludes that the work in question was a public work of the United States and that the procurement arrangement was a contract for construction subject to the Davis-Bacon Act. The Petitioner applied for approval of two classifications not in the wage determination, namely, "Panel Assemblers" and "Panel Assembler Helpers." The construction character of the project and Davis-Bacon applicability were recognized by all concerned. Although it could have been possible that everyone was in error, in this case they were not. Although the FAA called the matter of a lease arrangement, it did include the Supply Contract forms, the Construction Contract forms and general conditions, and the pertinent Davis-Bacon wage predetermination, with subsequent modification. [10] ~11 [11] Even if arguably it was a lease, compliance with the Davis- Bacon Act became a condition of the lease and the contractor- Petitioner could not blithely disregard it. The Board agrees on this point with the FAA and the Wage and Hour Division that this was a contract calling for construction at the erection site and that this contract was subject to the provisions of the Davis-Bacon Act. Having determined that the work in question was covered under the Davis-Bacon Act, it is necessary to assess a number of related issues and, from this point on, the Wage Appeals Board is unable to concur in the conclusions of the investigation made by the Wage and Hour Division. The specifications called for fragile and temporary construction. The structures were scheduled to be used for the 10- day period of Transpo 72 and the government was to have possession for not much more than a month. Thereafter, they were to be dismantled and removed by the Petitioner. An examination of the specifications and drawings raises serious question whether such structures would have met the local building codes for temporary housing construction, let alone permanent housing To equate this kind of structures with, for example, the construction of the J. Edgar Hoover Building currently underway on Pennsylvania Avenue, N. W., in Washington, D. C.; -- that is, to apply the commercial or general building rates prevailing in Washington, D. C., to the temporary quasi-housing structures here involved, does not appear [11] ~12 [12] warranted. This project should have characterized as a project of a character similar to housing construction, and the Employment Standards Administration (ESA) should have adverted to appropriate wage determinations for housing when confronted with the issue of the rates applicable to this project. A wage rate survey of both Fairfax and Loudoun Counties of the rates currently prevailing on housing construction of the character here involved, including the construction in nearby Reston, Virginia, could have provided a sufficient basis for issuing a wage determination applicable to Petitioner's contract. In addition, Petitioner requested approval of two rates for the assembling of the panels, namely, "Panel Assemblers" at a basic rate of $5.19 per hour, and "Panel Assembler Helpers" at a basic rate of $3.64 per hour. Both these rates were less than the $5.72 rate predetermined for "Laborers." The FAA did approve an assembler's rate above the contract rate for roofers, but less than the contract rate for carpenters. It also approved a helper's rate above the contract rate for roofer's helper, but less that the laborer's rate. There is no explanation in the record of the basis for this action. The FAA subsequently withdrew this approval on receipt of complaints from the Carpenters District Council of Washington, D. C. The Board does not consider this to be an appropriate case to review the question [12] ~13 [13] whether the above additional classifications were justified and at what wage rates. Such a determination is not necessary for the disposition of this part of the case. /FN4/ The Wage and Hour Division investigator concluded that since every housing structure must have a roof, the roofers' rate was applicable when the prefabricated top panels were bolted together on the ground by use of a socket wrench and zinc bolts and noting more, and when, after the top panel sections were raised by crane into position, a socket wrench was used to secure the sections. While the Carpenters Council of Washington did enter a protest in this case with respect to wall panels and floor work, the record shows no complaints on the part of the Roofers Union. Had this Board been required to reach the question of misclassification of the work of bolting the structures' top panels together on the ground, the problem would not [13] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN4/ It is worth noting that the major construction of Dulles International Airport (dedicated in 1961) is long past. The case under consideration is not one where a large volume of Government construction carrying general building rates under unique and special circumstances is simultaneously in progress in immediately adjacent areas on the same site. [13] ~14 [14] have involved misclassification of roofers. The Board does not reach this question, nor will ESA have to back into this matter. In the investigation it was further developed that subcontractor Trim's employees were entitled to the contract rate for carpenters. As detailed in the contract specifications, the party walls between units were to "separate joints as well as transmit the roof load to the floor." The floor was to consist of "7'-4" x 21'-0 plywood stressed skin panels, which were to be supported by double 2" x 12" joists 10'-6" O.C." The joists were to rest on concrete blocks. The exterior walls facing the deck and runway were to be "5/8 CDX plywood, pained and lap joined, and 6'8" x 12'-0" aluminum sliding glass doors (0 x 0)." The two panels above the glass doors were to be 3/16" clear acrylic. The interior partitions were to be "free standing 8'-0" high 2" x 3" stud unfinished wall construction with 1/4" plywood on both sides." The exterior walls opposite the deck were to be "5/8" CDX plywood painted and lap joined. All doors in these walls . . . set in wood frames." Knockout panels above doors were to provide air conditioning placement by user. Openings from the 8' wall height to the roof line were to be 3/16" clear acrylic. The end walls of each [14] ~15 [15] combination of units were to be typical 5/8" CDX plywood painted and lap jointed. Even though the panels were pre-engineered and preconstructed at the shop, the specifications cited indicate that unless subcontractor Trim paid the appropriate rates prevailing for carpenters on projects of a character similar in the area there would be a violation of the Davis-Bacon Act. The Petitioner was not unaware of the requirement to pay the prevailing carpenter's rate inasmuch as it specifically requested relief in its request for approval of the panel assemblers' rates. It is not clear what the contractor and the FAA meant by panel assembly. The wall and floor erection using carpenters for on-site assembly work involving prefabricated wood or plywood components was without question quite distinguishable from the assembly of the panels composing the roof. /FN5/ The Employment Standards Administration did not make a wage predetermination during or after construction of the carpenter's rate prevailing on low-rise housing construction in Loudon-Fairfax Counties that would then have been used for this wage predetermination. Not [15] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN5/ The Petitioner stated that the panels used on the roof and on the walls were the same and interchangeable. Pictures of the structures during erection showed many structures, if not all with plywood wall panels. [15] ~16 [16] having done so, the ESA is confronted with the task of going back and establishing the appropriate rate prevailing at the time the work was done. It is noted that it was not possible for Counsel for ESA to show in this case how the rate in fact paid for this carpentry work ($6.00 per hour, exclusive of fringe benefits) compared with the appropriate prevailing rate for carpenters on low-rise housing construction. If ESA has the evidence necessary to establish this rate, it should apply it in this case. If it does not have such evidence, it may, under the facts and circumstances, that a nonenforcement position if it believes it administratively preferable to do so because of the inherent difficulty at this time of determining the appropriate rate in Loudon-Fairfax Counties applicable to this work. There remains in this case, therefore, only the question whether there was any misclassification in the wall and floor erection work. The Wage Appeals Board finds that on the basis of the record before it the work in question should have been paid for at the appropriate prevailing carpenter's rate. The ESA should see to it that such a rate is paid pursuant to usual enforcement methods or it may under the circumstances of this case take a nonenforcement position because of the administrative difficulties posed by an attempt to determine that rate after the erroneous positions taken by the several administrative agencies having Davis-Bacon Act jurisdiction. [16] ~17 [17] ORDER The case is remanded to ESA in accordance with this decision for disposition of the question whether the appropriate prevailing rate was paid for the wall and floor erection work. SO ORDERED Oscar S. Smith, Chairman Stuart Rothman, Member [17]



Phone Numbers