skip navigational links United States Department of Labor
May 9, 2009        
DOL Home > OALJ Home > USDOL/OALJ Reporter
DOL Home USDOL/OALJ Reporter

BELL HELICOPTER FACILITIES II, WAB No. 66-04 (WAB Dec. 28, 1966)


CCASE: BELL HELICOPTER FACILITIES DDATE: 19661228 TTEXT: ~1 [1] WAGE APPEALS BOARD U.S. DEPARTMENT OF LABOR In the Matter of: BELL HELICOPTER FACILITIES II WAB Case The determination of the prevailing wage No. 66-04 rates applicable to the construction of an assembly plant and related construction at Dated: Bell Helicopter Facilities at Saginaw, December 28, 1966 Tarrant County, Texas Before: Oscar S. Smith, Chairman, Clarence D. Barker and Stuart Rothman, Members. DECISION AND ORDER This is a proceeding held in response to a petition, dated November 14, 1966, filed by the Texas Heavy-Highway Chapter of the Associated General Contractors of America for review of an opinion of the Solicitor of Labor, dated October 18, 1966, upon remand to him of the above-styled case on September 22, 1966. In his opinion of October 18, 1966, the Solicitor found that the record did not permit him to make specific findings as to how the term "prevailing wage rate," as defined in section 1.2(a) of the applicable rules of the Secretary of Labor, was applied to prevailing wages found for carpenters, laborers, and operating engineers engaged in paving work on the project involved. The pertinent facts involved and the essential positions of interested persons are set forth in our September 22, 1966 decision, and, therefore, need not be restated. The Board has re-examined the record, and has given careful consideration to the additional arguments presented by interested persons on December 2, 1966, and to additional statements submitted. The hearing examiner relied upon all the wage rates paid on the following projects: General Motors Chevrolet Assembly Project, the General Dynamics Project, the American Cyanamid Project, the Bell Helicopter Plant at Grant Prairie, the Bell Helicopter Plant at Hurst, and "to a lesser extent" the Turnpike Municipal Stadium. The hearing examiner concluded in his decision that the building construction rates prevailing at the time of opening bids were applicable to all the construction activities at the Bell Saginaw Plant. The six projects were the ones the hearing examiner considered to be "projects of a character similar" to the Saginaw Plant. The Wage Appeals Board does not question in these proceedings the validity of the generally applicable principle as enunciated by the hearing examiner, as follows: The Davis-Bacon Act requires that predeterminations be made according to wages prevailing on projects of a character similar to proposed contract work in the city, town, village, or other civil subdivision in which the work is to be performed. Thus, as in many past cases, the question has arisen as to the proper basis of comparison, where, as here, the controverted work is but part of an overall planned undertaking. If the work is considered alone, separate from the project to which it is related, data for a determination may be gleaned merely by looking to like work in the area. However, if the work is viewed in the context of the undertaking of which it is a part, information as to prevailing wage rates in the area is properly to be sought by looking to projects in the area which are of a character similar. We are not unmindful of the rule that erroneous conclusions of law may always be set aside upon review while factual findings to be rejected in a review procedure must lack the support of substantial evidence. As noted, we do not take issue with the applicable principle as stated by the hearing examiner. Nor do we question the principles announced by the Solicitor regarding his wage determination for the Houston Manned Space Craft Center (Hearings on H.R. 9656 and 9657. Special Subcommittee on Labor of the House Committee on Education and Labor, 87th Cong., 2d Sess., (1962) p. 209). In Houston, it was recognized (p. 211) that the keystone in administering the Davis-Bacon Act is the protection of local prevailing wage practices. In Houston, unlike here, the matter of size, as well as the extent to which heavy construction was related to building construction, were described by the Solicitor as having significance under local prevailing wage practices. We do question the sufficiency of the evidence relied upon by the hearing examiner regarding what rates were paid to the laborers and mechanics employed in the three disputed classifications on the six comparable projects. The evidence is essentially testimony of witnesses that building rates prevailed as to all work, including paving, "from property line to property line" on the six projects considered similar in their respective decisions. However, neither the decision of the Solicitor nor the hearing examiner alludes to any conflict with the documentary evidence of wage payments. If the oral testimony is to be viewed consistently with the documentary evidence, it can only mean that there was a predominance of building rates (union rates) over heavy and highway (nonunion) rates on the whole projects involved. There is nothing to indicate with sufficient clarity or convincing force that there was any predominance of the building rates in the case of the individual classifications involved for the performance of paving work. We are left with the conclusion that the record considered as a whole does not have sufficient evidence to support the findings that the laborers and mechanics employed in the three disputed classifications for the work in question as a part of the projects selected for comparison were predominantly paid building trades rates. ORDER The portion of the decision of the Solicitor of Labor, dated March 23, 1966, affirming the decision of the hearing examiner, relating to the prevailing wage rates for carpenters, laborers, and operating engineers, is hereby vacated. [END]



Phone Numbers