skip navigational links United States Department of Labor
May 9, 2009        
DOL Home > OALJ Home > USDOL/OALJ Reporter
DOL Home USDOL/OALJ Reporter

THOMAS J. CLEMENTS INC., 1982-DBA-27 (ALJ June 14, 1984)


CCASE: THOMAS J. CLEMENTS DDATE: 19840614 TTEXT: ~1 [1] [84-12.WAB ATTACHMENT] U. S. Department of Labor Office of Administrative Law Judges 211 Main Street - Suite 600 San Francisco, California 94105 (415) 974-0514 FTS 8 454-0514 In the Matter of THOMAS J. CLEMENTS, INC. CASE NO. 82-DBA-27 Respondent Dennis B. Cook, Esq. Thierman, Simpson & Cook 50 California Street, Suite 2840 San Francisco, California 94111 For the Respondent Sandra K. Rogers, Esq. U.S. Department of Labor Office of the Solicitor 450 Golden Gate Avenue San Francisco, California 94102 For the Department of Labor Before: VIVIAN SCHRETER MURRAY Administrative Law Judge DECISION AND ORDER This proceeding arises as a result of a dispute arising on July 8, 1980 with regard to the payment of prevailing wage rates, overtime pay and proper classification with respect to laborers and mechanics employed by Thomas Clements, Inc., who performed work on two construction rehabilitation projects, identified as Hud Project Nos. 136-35541-PM-EC-L8 (Little Oak) and 136-35560-PM-EC (Park Village), which projects were performed with federally assured loans and therefore are subject to labor standards requirements. This matter was duly referred to the Secretary of Labor for determination under the procedures provided under Reorganization Plan No. 14 of 1950 (64 Stat. 1267), the Davis Bacon Act, as amended (40 U.S.C. [sec] 276(a), et seq.), Contract Work Hours and Safety Standards Act, as amended (40 U.S.C. [sec] 327, et seq.), and the applicable regulations (29 C.F.R. Part 5) issued thereunder. [1] ~2 [2] A hearing in this matter was held November 2 and 3, 1983 in Sacramento, California at which time the parties were respectively represented by legal counsel. The principal issues presented for decision are whether employees hired by Thomas J. Clements, Inc. performed construction work subject to labor standards requirements including Davis[-] Bacon and if so: 1. Whether they were properly classified under the applicable wage determination. 2. Whether the Department of Housing and Urban Development (hereinafter HUD), the contracting agency approved the use of "independent contractors" for the performance of project work, and if so with what affect. 3. Whether mechanics and laborers employed at the Park Village and Little Oak Apartments projects were entitled to wages determined under the Davis[-] Bacon and related Acts. 4. Whether the partial payment of $44,723.60 made by Thomas Clements on September 4, 1980 constituted a compromise and settlement of the backwage claims which exceeded $200,000, at that time. 5. Whether the equitable doctrine of laches has any application in the instant proceeding. 6. Whether and to what extent, if any, Thomas J. Clements, Inc., Thomas J. Clements and the owners of the properties are liable for any back wage assessment. Findings and Conclusions Background Real Property Equities Company, in which Thomas J. Clements and Barbara McNece were partners purchased the Park Village Apartments in Stockton, California and the Little Oak Apartments Sacramento, California, in early 1978. Subsequently two limited partnerships were formed in which Thomas J. Clements and Barbara McNece were, in each instance, the general partners. The purpose of such limited partnerships was apparently to contract to purchase, own, manage and operate real property. Real Property Equities Company sold Little Oak Apartments to the Little Oak Investors, a limited partnership and sold the Park Village Apartments to the Park Village Investors, a limited partnership. [2] ~3 [3] It is clear from the testimony of Clements, consistent with the powers accorded the general partners in limited partnerships, that the general partners, conducted the business, acting for and on behalf of the limited partnership. The limited partnerships each employed Thomas J. Clements, Inc., a wholly owned corporation consisting of its President, and sole shareholder Thomas J. Clements, as managing agent, whose duties, consisted of construction, the collection of rents and maintenance of the properties. On September 6, 1978 and November 30, 1978 respectively, Thomas J. Clements as general partner of the respective limited partnerships entered into a contract with Concept Interior Designs, a contractor licensed under the laws of the State of California. Such contracts were executed in consideration and anticipation of the owners (the limited partnerships) obtaining federally secured mortgage loans, which the owners represented by Thomas J. Clements and Barbara McNece did. (Exs. 2, 7; Resp. Exs. C, D in Support of Motion for Summary Judgment and Tr. 183-186). Construction rehabilitation commenced in early 1979. There is however, no indication to what extent, Concept Interior Designs, the prime contractor rendered performance under the FHA approved contracts. It may he assumed that to the extent that he performed he did so in compliance with applicable [l]abor standards and is otherwise without liability for the back wages here at issue, since he is not a party to this action. It does appear that Thomas J. Clements and persons employed by him for the purpose, commenced work on both projects from or shortly after construction and rehabilitation commenced. Applicability of Davis[-]Bacon and related [l]abor standards Counsel for the respondent's contention that the absence of an express written contract incorporating or applying the Davis[-] Bacon Act and related Labor standards to the construction rehabilitation contracts renders such Labor standards inapplicable is untenable. Where the projects' mortgages are insured by the Federal Housing Administration, pursuant to the National Housing Act (12 U.S.C. 1715(c)), the contractor is required to pay laborers and mechanics prevailing wage rates as determined by the Secretary of Labor. Any questions concerning applicability of the Davis[-] Bacon provisions and related labor st[a]ndards were removed when the application and the contract were approved. FSG Contrac[tin]g Co./Hercules Electrical Co., Inc., 76 DB 110, 22 WH 1311 (1976). Such standards are contained in the supplementary conditions of the contract and are incorporated therein. See, C 5, C 4cc - Article I - Labor Standards. Additionally, neither the testimony nor the conduct of Clement[]s indicates or even suggests, that he questioned the applicability of such provisions to the project work. (Govt. Ex. 5) (42 U.S.C. 1437(j)). In this regard Clements testified that [3] ~4 [4] there was a retention arrangement between the owners of the projects i.e. the two limited partnerships and HUD, that is, a withholding of funds by the contracting agency to ensure in part that prevailing wages would be paid. (Tr. 202-204; Resp. Ex. B). Since Clement[]s, as general partner of the limited partnerships, represented the owners in his dealings with HUD, he is in no position to plead ignorance to or disavow the terms of the contracts and the Laws applicable thereto, particularly where his testimony shows prior similar contracts with the government and a clear understanding of the purposes for which monies are withheld by the contracting agency. Personnel employed by Respondent Counsel for the respondent asserts that the controversy in this case arose because respondent's maintenance employees worked side by side with the construction workers during the course of construction and were therefore improperly determined to be entitled to the prevailing wage for on-site construction workers. The evidence indicates, however, that the government recognized that certain maintenance personnel were in fact performing maintenance work on both projects and did not seek Davis[-]Bacon wages for such persons, when so engaged. Where such persons were in fact performing construction and rehabilitation work on vacant apartments, which were clearly a part of the construction and rehabilitation project, the government did impose the labor standards mandated by Davis[-]Bacon and related acts. Accordingly, workers listed on Exhibit G4, who were employed in construction work, on the Little Oak project in Sacramento, California from November 3, 1978 to May 23, 1979 were determined to be laborers and mechanics within the meaning of the applicable law and were required to be paid no less than the basic hourly wage and fringe benefit amount specified in the wage rate information (Exs. 4, G-1). Likewise, the workers employed on the Park Village project in Stockton, California from February 2, 1979 to November 15, 1979 were determined to be working as laborers and mechanics within the meaning of the Act and were required to be paid no less than the applicable wage rate. (G-9, G-6). All of the aforesaid persons were employees of the respondent. Unrefuted evidence presented by the government establishes beyond reasonable doubt that the workers for whom back wages were sought were actually performing work on the construction and rehabilitation project. The assertion that some of the work for which back wages are sought was routine maintenance work appears to rest primarily on the testimony of Mr. Clements, to the effect that such work might in different circumstances be performed as routine maintenance, for example, removal of a defective bath tub and its replacement with a new tub. The testimony of Ms. Meadows, respondent's construction bookkeeper on the Sacramento project and [4] ~5 [5] later general bookkeeper and personnel officer, shows that Ms. Meadows in conjun[c]tion with her supervisor Ms. Werner, the chief financial officer, determined the nature of the work performed by each worker and the time spent on each particular job. Such determinations are fully supported by recourse to other relevant documents such as the contractor's mortgage cost break down and the employees['] time sheets. The fact that work performed in the course of the construction and rehabilitation of the apartment units might, [*] in other circumstances [*], have been performed in the course of maintenance is irrelevant where the work actually performed in these circumstances was part of the renovation construction contract. [*] [EMPHASIS IN ORIGINAL] [*] Workers who performed such work are entitled to wages consistent with applicable labor standards. The mere presence of workers on the site did not determine their wage. It was determined by the nature of the work performed. Daily timesheets devised by Ms. Meadows on the Little Oak project were headed "for construction employees only" and were utilized to further separate maintenance personnel from project personnel. Ms. Meadows was advised and instructed by the compliance officer on that project as to the correct manner of classifying employees for purpose of Davis[-]Bacon wages. At the time of hearing she demonstrated an impressive grasp of the basis upon which differentiation is properly made, as opposed to the manifest inadequacy and confusion of Mr. Clements in this regard (Tr. 200, 201). While the daily time sheets of Little Oak which were under Ms. Meadows['] control provided an adequate record, the time sheets kept on the Park Village project were woefully inadequate, consisting of the record of hours worked with little or no indication of the work performed. However, the testimony of the witnesses presented at hearing, who worked on that project, establishes that the work performed was not maintenance work but clearly within the planned renovation of the project and was performed in apartments which were totally vacant. Additionally, there is no showing that there were any maintenance personnel at the Park Village project, apart from Mr. Groves, who performed maintenance work at times, as acknowledged by the government, and at other times, performed project work. (Tr. 243-245; G-12). Mr. Groves further volunteered at the close of his testimony that when DOL investigators appeared on the site the foreman would tell the workers to drop the tools of their trade and do something else, indicating a clear attempt on the part of the respondent to evade his responsibility under the Davis[-]Bacon Act. Ms. Meadows who determined which workers performed project work at the Park Village project consulted with the construction foreman and supervisors of whom, one was the brother of Thomas J. Clements, in order to ascertain the actual nature of the work which the workers were performing and determined their w[a]ges accordingly. (Tr. 119, 120). [5] ~6 [6] It would appear that the respondent believes that it is the responsib[i]lity of the compliance officer in the first instance, to provide classification and wage schedule and determine the wages which the workers are to be paid. The inclusion of such schedule in the contract is the duty of the contracting officer (HUD/FHA), and was properly included in the instant case ( 29 C.F.R. Part I; Govt. Ex. 6). The respondent could have applied to the Administrator for reconsideration or modification of any classification which he deemed to be incorrect. He did not do so nor did he challenge the government's wage determinations or dispute them in any way prior to July 8, 1981, or prior to completion of the projects and may not now attempt to modify them in this forum. Douglas Construction Co./Grandstaff Roofing and Supply Co., 80 DB-267 (1981). The duty of the compliance officer is to determine whether or not the contractor is in compliance with the applicable wage schedule. It is the respondent's duty to have kept accurate records for such investigating officer's inspection so that his records in conjunction with a check of the employees can be used as a basis for determining the respondent's compliance. The respondent's attempt to shift his regulatory and contractual recordkeeping duties to the government and to present that dereliction of duty as a defense is frivolous. Where a contractor fails to maintain adequate and accurate records showing hours worked and accurately stating the work classification for his employees he may not complain that the necessarily reconstructed facts lack precision but bears the burden of showing that each employee was paid the proper hourly rate. Employees should not be penalized for the employer's failure to properly maintain the required records. Anderson v. Mount Clemens Pottery Co., 328 U.S. 684, 687 (19[46]); Shultz v. Hinojosa, 432 F.2d 259 (5th Cir. 1970). Respondent also appears to believe that the test for correctness of classification is dependent upon the skill or experience of the employee performing the work. It is well established that such test for correctness of classification is actual work performed not the degree of skill or experience possessed by the employee. FSG Contracting Co., supra; Titan Atlantic Construction Co., 78 DB-125 (1978). The evidence presented by the government gains credibility by a showing that the compliance officers as well as the respondent's employees, principally, Ms. Meadows and Ms. Sheree Werner were scrupulous and diligent in their efforts to determine the workers' wages consistent with the actual work performed as is demonstrated by the relevant evidence. Mr. Groves who performed both maintenance and project work at different times was determined to be due back wages only for the project work not for the maintenance work. Respondent's contention that as the projects progressed there was an increasing need for maintenance work is contrary to common sense in this context and equally contrary to the relevant credible evidence of record. [6] ~7 [7] Independent Contractors - Estoppel Respondent's contention by his attorney that the contracting agency approved the use of independent contractors is without meaning in the context of the Davis[-]Bacon Act and applicable regulations which provide, in relevant part, that every person paid by a contractor or a subcontractor in any manner for his labor in the construction, prosecution, completion, or repair of the building or work financed in whole or in part by loans, grants or guarantees from the United States is "employed" and receiving wages regardless of any contractual basis alleged to exist between them (29 C.F.R. [sec] 5.2(i)). 29 C.F.R. [sec] 5.5(a)(1) provides in relevant part that all mechanics and laborers employed or working upon the site of a work such as that herein will be compensated weekly at a computed wage rate not less than that contained in the applicable wage determination regardless of any contractual relationship which may be alleged to exist between the contractor and such laborers and mechanics. The mere approval of independent contractors to work on the site does not constitute approval of the payment of less than the minimum wage imposed under the Davis[-]Bacon and related Acts for mechanics and laborers. The indicia which would determine whether or not a person employed was an independent contractor need not be reviewed since employment of any workman on the projects at lower than the wage rates required by law, would be contrary to the law whether or not they were independent contractors, within the legal meaning of that term. The language of the Act as amended in 1935, (49 Stat. 1012), is clear and unambiguous. It manifests the intent of Congress to prevent circumvention of the law by creation of a contractual arrangement which would rebound to the detriment of the employee. (S. Rep. No. 1155, 74th Cong., 1st Sess., p. 3; H. Rep. No. 1756, 74th Cong., 1st Sess., p. 3). Even in an appropriate case, which this is not, since the respondent does not contend that HUD approved the hiring of independent contractors at wages lower than those imposed by Davis[-]Bacon and related labor standards, the doctrine of estoppel may not be invoked against the government where it would result in defeating the effective operation of policies embodied in legislation designed to protect the public. McComb v. Home Makers Handicraft Cooperative, 176 F.2d 633 (4th Cir. 1949) cert. den. 338 U.S. 900. The Davis[-]Bacon Act is not an Act for the benefit of employers but for the benefit of their employees. Bushman Construction Co., v. U.S. (1958), 164 F.2d 239; U.S. v. Binghamton Construction Co., 74 S. Ct. 438, 347 U.S. 171 (1954), rehearing denied, 74 S. Ct. 625, 347 U.S. 940. It is likewise well established that an employee cannot waive or bargain away the payment of wages and rights secured to him by law. Brooklyn Savings Bank v. O'Neil, 324 U.S. 697, 702, 65 S. Ct. 895, 900 (1945), although the evidence shows (Resp. D) and Clements does not [7] ~8 [8] deny that he obtained such written waiver under threat of discharge. Partial Payment, Whether Compromise and Settlement The respondent voluntarily made partial payment on the assessed underpaid wages on September 4, 1980 (Resp. Exs. B, C) and specifically stated that failure to pay the full amount was due solely to economic inability, f[o]stering the Department of Labor's belief that their assessment was undisputed, until July 8, 1981. This is abundantly clear from the correspondence which passed between Clements and the Department of Labor between September 4, 1980 and March 4, 1982. (Resp. Exs. B, C, E, F, G submitted in support of Motion for Summary Judgment). Clements testified in this regard that such payment ($44,720.60) was made from his own personal funds (Tr. 206), and later stated that they were the funds of Thomas J. Clements, Inc. which were intended as a good faith gesture "to pay off the prevailing wage they [DOL] had found we owed and [he] hoped it would satisfy the entire debt." (Tr. 212). To maintain, as does counsel for the respondents' that there was an accord and satisfaction or more accurately a compromise and settlement of a dispute that had not yet arisen, and did not arise until approximately ten months after the voluntary release of the partial payment by Clements is untenable. As late as June 15, 1981 the Assistant Administrator of the Department of Labor wrote to Clements specifically stating the government's understanding that Mr. Clements was not disputing the amount of back wages and requested remittance of the balance. The credible evidence in this case establishes beyond doubt that there was not a compromise and settlement in September, 1980, nor any basis therefore. Applicability of the Equitable Doctrine of Laches Counsel for the respondent also claims that the instant legal action is barred by application of the Equitable Doctrine of Laches. It is well established that the Equitable Doctrine of Laches will rarely be invoked to bar an action at law where the applicable statute of limitations has not run. Counsel's argument is premised on his misconception that the statute of limitations applicable herein commenced to run in May 1979, or thereabouts, when the wage underpayments occurred. The Department of Labor apprised Clements of the underpaid wages but since the respondent manifested no intention to dispute the government's back wage assessment until July 8, 1981, the government had no reasonable basis to proceed at law. It is equally well established that acknowledgement, a new promise or part payment made, either before or after the statute of limitations has run revives the cause of action. Gee v. CBS, Inc., 471 F.2d 600, aff'd 612 F.2d 572 (1979); U.S. v. Glenn Falls Insurance Co., 546 F.2d 643 (S.D.N.Y., 1982). Partial payment made by Clements on September 4, 1980 was voluntarily made and was not accompanied by any correspondence or indication that Clements did not intend at some future time to [8] ~9 [9] satisfy the total amount of the outstanding demand. Accordingly, such statement commenced the running of the statute of limitation, under the Portal[-]to[-]Portal Act, anew. The order of reference was filed and service was made on the respondent by mail on April 28, 1982 well within the statutory limitations. None of the facts or circumstances in this case warrant application of the Equitable Doctrine of Laches. The government was led to believe whether intentionally or unintentionally by the respondent that the respondent intended to pay the full amount of the back wage assessment and did so believe until July 8, 1981, long after completion and final payment had been made on both projects. Even if that were not the case, the defense of laches may generally not be invoked against the government when it acts to enforce a public right or protect a public interest. Citizens and Land Owners v. Miles City/New Underwood Power Line v. Secretary, U.S. Department of Energy, 683 F.2d 1171 (8th Cir. 1982). Laches requires more than delay, it requires a lack of diligence on the part of the plaintiff and a showing of prejudice on the part of the defendant. City of Davis v. Coleman, 521 F.2d 661 (9th Cir. 1975). Notwithstanding counsel's assertion that respondent was severely prejudiced by a delay which he characterizes as unreasonable, there is no evidence to sustain that contention. The relevant evidence was preserved in records made at the time of the occurrence to a great extent and otherwise by reconstruction, which would not have been necessary had the respondent kept complete records as required by applicable law. The witnesses who appeared at hearing manifested no significant loss of memory with regard to these events and one or more remembered well the respondent's attempts to circumvent their rights under the applicable law. That testimony is credible, and is in fact, supported by documentary evidence. The nature of the evidence in this case precludes the application of any equitable doctrine in favor of the respondent. Clements['] operations throughout, in one guise or another, were designed to circumvent laws intended to protect the workers employed on government projects. Liability Counsel for the respondent argues that Thomas J. Clements, Inc., a corporation and the "principal contractor" is alone liable for any back wage deficit under applicable laws, that no liability can be found against the owners and essentially that there is an insufficiency of documentary evidence relevant to the contractual relationships of the respondents to support any other conclusion. I do not concur, at least, not in this context. Clement's testimony in conjunction with the applicable provisions of law [9] ~10 [10] governing limited partnerships, which are creatures of statute, and not at all obscure, in their effects, and the application of another equitable doctrine are, I believe, sufficient to impose liability on the owners, to the extent allowed by law and on Thomas J. Clements personally, as general partner in both limited partnerships, who was personally served in this matter. There is at least no doubt that personal liability may be imposed in appropriate case against the general partner in a limited partnership. United States v. Haddon Haciendas Co., 541 F.2d 777 (9th Cir. 1976). Concept Interior Designs was the prime "contractor" and Clements was clearly not his subcontractor. Thomas J. Clements, Inc. is and was at all relevant times a property management firm, according to Clement's testimony which is consistent with that firm's letterhead; not a building contractor. Thomas J. Clements as general partner in both limited partnerships was authorized under the contract with HUD (G-5) to perform work on the project as an owner. He may well hold a contractor's license in his own name. Clement's testimony that there was a kind of retention policy between the owners of the projects and HUD (Tr. 202, 203; Resp. Ex. C) and that such monies were used in fact to assure payment of the prevailing wage rates (Tr. 204; Resp. Ex. C) and evidence that he released such funds for the purpose shows that Thomas J. Clements['] work on the project was performed in exercise of the owners right to do so and on no other basis. Thomas J. Clements, Inc. was not an owner and could not have exercised that contractual right or released money withheld from the owners, notwithstanding the fact that the corporate presence, Thomas J. Clements, Inc. was much in evidence on both projects. It will be noticed, however, that on the authorization to release funds, signed by Clements, he is not designated "Pres. Thomas J. Clements," but rather "company official" which is a totally meaningless title. Only a general partner in the limited partnership had the power to act on behalf of the owners. Respondent's contention to the contrary only indicates the unity of interest existing between Thomas J. Clements and Thomas J. Clements, Inc. Thomas J. Clements, as general partner in both limited partnerships is an owner of both projects and may not deny his liability, which is unlimited as is that of Barbara McNece, who was not however served in this action and accordingly may not be found personally liable. In California, a partnership may be sued in its own name but a judgment is binding on the partners only if specifically named in the complaint and personally served. Fazzi v. Peters, 68 Cal. 2d 596, 440 P.2d 242 (1968). [10] ~11 [11] Under California law, general partners are general agents of limited partners for the general purpose of conducting business subject only to the statutory exemption of limited partners from direct obligations to creditors beyond their stated financial commitment. West's Ann. Cal. Corp. Code, [secs] 15501, 15507, 15509, 15517 (3, 4); Donboy, Limited v. U.S., 301 F.2d 200 (9th Cir. 1962). A limited partnership is a creature of statute, whose protections and privileges are available only upon compliance with the statutory requirements. Essentially, the Act limits liability of the special or limited partners to the extent of their commitment, insulating them from liability on obligations to third parties and creditors. They share in the profits and an interest in the assets of the business; the conduct of the business is in the hands of the general partners alone, whose liability with regard to such operation is unlimited as to partnership and personal assets. U.S. v. Haddon Haciendas Co.. 541 F.2d 777 (9th Cir. 1976). Clements may be regarded as functioning in a dual capacity; as owner, when he executed contracts and hired employees to work on the projects and as Thomas J. Clement's Inc., property manager when he collected rents and hired and paid personnel who were actually hired to perform and did perform maintenance work, i.e. non-project work. These separate roles are not clearly distinguishable in the functional and practical sense; nor were the funds belonging to each entity maintained separately. The evidence shows that persons, who actually worked on the construction and rehabilitation projects and who were characterized as "maintenance people" and "independent contractors" were paid with funds received from rental of some of the apartments, which was ownership income and FHA contract funds. (Tr. 197, 198). The overall record indicates that the funds of Thomas J. Clements, Inc. were simply FHA funds and rental income funds which were filtered through the Thomas J. Clements, Inc. payroll account. Clements, testified that the monies placed in escrow and subsequently released to the Department of Labor in September, 1980, were his personal funds and subsequently that they were the funds of Thomas J. Clements, Inc. All in all there is no showing that Thomas J. Clements, Inc., is anything more than the alter ego of Thomas J. Clements. There is a distinct unity of interest and every indication that Thomas J. Clements, Inc., has no assets, apart from those of Thomas J. Clements. In the State of California as in every other state the Courts will pierce the corporation veil where failure to do so will produce an unjust result. Associated Vendor, Inc. v. Oakland Meal Co., 210 Cal. App. 2d 825, 26 Cal. Rptr 806 (1962); H.A.S. Loan Service v. McColgan, 2 N.C. 2d 518, 133 P.2d 39 (1943); Swanson v. Levy, 500 F.2d 859 (9th Cir. 1975); First Commonwealth Company, Inc., a corporation, et al., defendants, 409 F.Supp. 1396 (8th Cir. 1973). [11] ~12 [12] Thomas J. Clements and Thomas J. Clements, Inc. share the same name. The corporation has one officer, Thomas J. Clements and one shareholder, Thomas J. Clements. It apparently has no capital or other assets apart from those of Thomas J. Clements, and performed property management services of limited extent only for the limited partnerships in which Thomas J. Clements was a general partner. FHA funds advanced to the limited partnerships for project work were placed in the payroll account of Thomas J. Clements, Inc. and used to pay employees working on government funded projects, who were hired by Thomas J. Clements, as owner and representative of the limited partnerships. The unity of interest and ownership in the instant case are manifest and extensive to a degree that Thomas J. Clements is not distinguishable from Thomas J. Clements, Inc., save in the nominal sense. Their assets and interests are so com[m]ingled that Clements does not ordinarily distinguish between the corporate entity which bears his name and himself, as his testimony shows. The corporate entity in this instance is a mere label which counsel for the respondent seeks to interpose as a shield to protect the respondent from the personal liability which flows from his ownership interests in the two FHA projects, with the intent of frustrating the intent of the applicable legislation to the detriment of the mechanics and laborers, such legislation was designed to protect. That inequitable result will not be countenanced under applicable law. Associated Vendor Inc. v. Oakland Meal Co., supra. However, even if there were any indication of the existence a separate corporate entity, it would be without material effect the instant case since a preponderance of the credible evidence compels the conclusion, that Thomas J. Clement's function as contractor on both projects stemmed solely and directly from his ownership interest, as a contractual right attributable thereto. Accordingly, I find that the limited partnerships, Little Oak Investors and Park Village Investors are liable to the extent allowed by law and that Thomas J. Clements is personally liable as general partner in each of the aforesaid limited partnerships, for the wage underpayment, as determined by the Department of Labor. I conclude that: 1. This matter is properly before me under [t]he provisions of 29 C.F.R. [sec] 5.11(b). 2. The work performed on Projects Nos. 136-35541-PM-EC-L8 and 136-35560-PM-EC, construction projects is subject to payment of the prevailing wage rates of the Davis[-]Bacon Act, 40 U.S.C. [sec] 276(a), the labor standards requirements of 12 U.S.C. [sec] 1715(c) and 42 U.S.C. [sec] 1437 and the regulations promulgated thereunder. [12] ~13 [13] 3. The persons identified in Exhibit G-4 are laborers and mechanics who were employed by Thomas J. Clements, owner, contractor and who performed construction and rehabilitation work on the Little Oak Project in Sacramento, California (HUD Project No. 136-35541-PM-EC-L8) and are accordingly entitled to be paid at least, at the applicable hourly wage rate as set forth in Exhibit G-1. 4. The persons identified in Exhibit G-9 are laborers and mechanics who were employed by Thomas J. Clements, owner, contractor and who performed construction and rehabilitation work on the Park Village Project in Stockton, California (HUD Project No. 136-35560-PM-EC) and are accordingly entitled to be paid, at least, at the applicable hourly wage rate as set forth in Exhibit G-6. 5. Respondents failed to compensate identified persons employed on the Little Oak Project at the required wage rate resulting in a current underpayment of back wages in the amount of $36,046.94, which is due the identified employees. /FN1/, /FN3/ 6. Respondents failed to compensate identified persons employed on the Park Village Project at the required wage rate resulting in a current underpayment of back wages in the amount of $125,138.06, which is due the identified employees. /FN2/, /FN3/ 7. Thomas J. Clements, owner/contractor and general partner in Little Oak Investors and Park Village Investors, both limited partnerships, having exercised the contractual rights of the owners on both projects, on behalf of such limited [13] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN1/ Exhibit G-4 shows total unpaid wages due Little Oak employees to be $50,471.66, on 4/6/81. /FN2/ Exhibit G-9 shows total unpaid wages due Park Village employees to be $155,433.94, on 6/24/80. /FN3/ It is assumed that a prorate[d] reduction in thos[e] amounts by $14,424.72 and $30,295.88 respectively, was made by the Department of Labor when Respondent made partial payment of $44,720.60. [13] ~14 [14] partnership and having by failure to comply with applicable Labor standards, incurred back wage underpayments, which he has not fully satis[fi]ed is liable as a general partner and having been personally served in this matter is personally liable for the total amount of the existing back wage underpayment, to the extent that such obligation is not satisfied out of reachable partnership assets. 8. Little Oak Investors, a limited partnership is liable, to the extent allowed by law, for back wage underpayments in the amount of $36,046.94. 9. Park Village Investors, a limited partnership is liable, to the extent allowed by law, for back wage underpayments in the amount of $125,138.06. Wherefore, it is Ordered that Thomas J. Clements, on behalf of the Little Oak Investors, the Park Village Investors and himself pay to the Employment Standards Administration, U.S. Department of Labor the sum of $205,905.60 for distribution to identified employees according to their entitlement. Any of said amounts not distributed to said employees or their legal representative, within three years from the date of receipt thereof by the Employment Standards Administration, U.S. Department of Labor, because of inability to do so, shall be covered into the Treasury of the United States as miscellaneous receipts. Dated this 14th day of June, 1984 at San Francisco, California. VIVIAN SCHRETER MURRAY Administrative Law Judge VSM:brt [14]



Phone Numbers