NUCLEAR POWER SERVICES, INC.,
STONE & WEBSTER ENGINEERING CORP.,
TEXAS UTILITIES ELECTRIC CO., INC.,
RESPONDENTS.
BEFORE: THE SECRETARY OF LABOR
FINAL DECISION AND ORDER
The Administrative Law Judge (ALJ) in this case arising
under the Employee Protection Provision of the Energy
Reorganization Act of 1974, as amended (ERA), 42 U.S.C. § 5851
(1988), submitted a Recommended Decision and Order (R. D. and O.)
recommending that the complaint be dismissed. The facts are well
summarized in the R. D. and O. at 2-4.
1 George Boerum, personnel manager
for Stone & Webster,
testified that Stone & Webster made employment offers to 79 of
110 engineers. T. 579-80.
2 The ALJ dismissed the
complaint against TUEC for terminating
Complaint, and against Stone & Webster for refusing to hire him
in August 1985, as untimely because Complainant did not file his
complaint with the Department of Labor until February 18, 1986.
ALJ Order Granting Partial Summary Judgment Dismissing Complaint,
June 17, 1987. The hearing held by the ALJ was limited to
whether TUEC and NPSI had blacklisted Complainant causing Stone &
Webster not to hire him in January 1986. I agree with the ALJ's
findings on timeliness. In addition, however, the findings of
the ALJ discussed in the text, from which he concluded that the
Respondents did not blacklist Complainant, apply as well to the
questions of whether TUEC's negative recommendation and Stone &
Webster's refusal to hire in August 1985 were motivated by an
intent to retaliate against Complainant for protected activities.
Indeed, the ALJ held that "there was neither blacklisting nor
discrimination within the meaning of the Act." R. D. and O. at
6.
3 The ALJ found that
Complainant did not engage in protected
activity because he did not pursue his technical concerns about
construction of the Comanche Peak plant when he first made them,
but only characterized them as safety concerns after Stone &
Webster failed to hire him in August 1985. R. D. and O. at 5.
In addition, the ALJ found that Complainant's activities of
making internal complaints and threatening to go to the NRC are
not protected activities in the Fifth Circuit, where this case
arises, under Brown & Root, Inc. v. Donovan, 747 F.2d 1029, 1036
(5th Cir. 1984). The Secretary has reiterated in a number of
cases, respectful disagreement with the holding in Brown & Root,
and in cases arising within the Fifth Circuit has found internal
complaints protected. Bivens v. Louisiana Power & Light, Case
No. 89-ERA-30, Sec. Dec., June 4, 1991, slip op. at 4-5; Lopez v.
West Texas Utilities, Case No. 86-ERA-25, Sec. Dec., July 26,
1988, slip op. at 5-6; Willy v. The Coastal Corporation, Case No.
85-CAA-1, Sec. Dec., June 4, 1987, slip op. at 3. Because I
agree with the ALJ on the merits of this case, United States
Postal Serv. Bd. of Governors v. Aiken, 460 U.S. 711, 715-16
(1983), I do not address here the internal complaints issue.
4 Some of the ambiguity over the
existence of a settlement
may have been caused by confusion over who represented
Complainant and who represented TUEC at the critical time
at issue. Complainant was represented at the 1987 hearing before
the ALJ by Michael D. Kohn and Stephen M. Kohn, attorneys who
were at the time associated with GAP; attorneys Harvey J.
Wolkoff and Katrina Weinig of Boston represented TUEC at the
hearing. Ms. Garde and Mr. Wooldridge held settlement
negotiations in June 1988. On July 5, 1988, Complainant issued a
notice that Billie Garde no longer represented him and that his
sole legal representative was Michael D. Kohn, who by that time
had formed his own private firm with Stephen M. Kohn. Michael
Kohn and Stephen Kohn made certain representations on
Complainant's behalf with respect to settlement of this case
which are described in the text infra. Among other things,
Michael Kohn wrote a letter to another attorney, Jack R. Newman,
who represents TUEC in the licensing proceedings on the Comanche
Peak plant. In addition, Louis Clark and Richard Condit,
attorneys with GAP, contacted Complainant by mail and by
telephone in early July 1988 regarding a settlement offer by
TUEC. Mr. Clark was under the impression that GAP still
represented Complainant.
5 Complainant contends that the
"material terms of the Hasan
settlement are identical" to two other cases settled and approved
by the Secretary. Complainant's Response to OSC at 4-5. But
both of those cases were submitted for review and approval with
signed settlement agreements between the parties and signed
releases from the respective complainants. Radelich v. Ebasco
Services, Inc., Case No. 88-ERA-24, Sec. Order, Aug. 3, 1989;
Goese v. Ebasco Services, Inc., Case No. 88-ERA-25, Sec. Order
Dec. 8, 1988.