U.S. Department of Labor
Office of Administrative Law Judges
101 N.E. Third Avenue, Suite 500
Ft. Lauderdale, FL 33301
DATE: JUNE 24, 1992
CASE NO: 88-ERA-15
In The Matter of
ANDREW BARTLIK,
Complainant
v.
TENNESSEE VALLEY AUTHORITY,
Respondent
BEFORE: E. EARL THOMAS
ADMINISTRATIVE LAW JUDGE
REVISED RECOMMENDED DECISION
Andrew Bartlik filed a complaint on December 23, 1987, with
the U.S. Department of Labor (DOL), alleging a violation of the
Energy Reorganization Act of 1974, as amended (ERA), 42 U.S.C.
§ 5851 (1988). After investigation, the DOL's Wage and Hour
Division determined on March 11, 1988 that the Tennessee Valley
Authority (TVA) had discriminated against Bartlik because of his
identification of safety problems in TVA's Sequoyah nuclear plant
fire prevention program. After a full hearing, a Recommended
Decision and order, issued September 21, 1989, concluded that the
Wage and Hour determination should be sustained and recommended
the payment of compensation by TVA.
The case was transferred to the Secretary of Labor, and
briefs were filed by June 8, 1990. Complainant filed a Petition
for Writ of Mandamus in U.S. District Court and a Remand Order
(RO) was issued by the Secretary on December 6, 1991, directing
the response to various questions raised in that Order. The
initial recommended decision and order (RDO) was drafted
primarily from the administrative law judge's notes which were
made contemporaneous with the hearing.1
The Remand order
directed that certain inferences and conclusions drawn in the
[Page 2]
1 Trial courts (and many
administrative tribunals) generally
do not provide citations to testimony or documents in decisions
because findings usually state ultimate facts, not the evidence.
See Mining Co. v. Taylor, 100 U.S. 37; Miller v. Life Ins. Co.,
79 U.S. 285; Wilson v. Merchant's Loan & Trust Co., 183 U.S. 121;
Grayson v. Lynch, 163 U.S. 468; Fanning v. Murphv, 126 Wis. 538,
105 N.W. 1056. In fact, in many courts, testimony is not even
transcribed unless an appeal is taken. The implementing
regulations at 29 C.F.R. § 24.6 require that the administrative
law judge "issue a recommended decision within 20 days after the
termination of the proceedings at which evidence was submitted."
Normally, transcript is not received within this time frame.
2 Bartlik was hired under an
individual staff augmentation
contract. TVA argued that his contract was not extended or
reissued because the TVA had switched to a managed task contract
by September, 1987 in which engineers were chosen by the
contractor. The Secretary found this issue "largely irrelevant"
as the change in contracting methods was not alleged to be a
subterfuge for eliminating whistleblowers. RO at 3, N.3. While
it is true that the primary purpose for this change was not to
eliminate particular employees, it nonetheless gave management a
chance to clean house and simultaneously shift supervisory
responsibility to outside contractors.
3 A Condition Adverse to
Quality Report (CAQR) was the
documentation required to identify and report safety deficiencies
or nonconforming conditions in the plant design.
4 Although the NRC Report,
admitted as Respondent Exhibit
21-B, found that Revision 7 arose out of TVA's calculational
review process, there was no evidence presented as to which
manager directed this re-evaluation.
5 Sheehy was assigned to the
Nuclear Engineering Branch, and
Bartlik was assigned to the Mechanical Engineering Branch.
6 Pennell reported to Mr.
Kirkebo, who at that time was
Director of Nuclear Engineering.
7 Mr. Hosmer submitted
Revision 6 to the NRC on October 1,
1987, despite the fact that Revision 7 previously had been
adopted by TVA. Tr. 549-551. When he met with the NRC on
December 8, 1987, Hosmer told them he was not aware that
Revision 7 was the effective TVA document. Tr. 608-609,
see CX 28.
8 Some names are mentioned
only to point out the size of the
group and the apparent significance of the meeting.
9See statement of George
P. Cooper on March 3, 1988.
10NRC Regulation of
TVA: Hearings Before the Subcomm. on
Oversight and Investigations of the House Comm. on Energy and
Commerce, 99th Cong., 2d Sess. 22 (1986).
11 The memorandum of J.A.
Kirkebo on March 24, 1987,
acknowledged the transition from general service contracts to the
new managed task contracts, but stated that TVA anticipated
"establishing additional task completion contracts to accomplish
the remaining work at Browns Ferry, Sequoyah, and Bellefonte for
which TVA resources are not available."
12 At that time, Mr.
Michlink was on loan from Wilson's
Nuclear Engineering Branch to Sequoyah, and was functioning as a
contract administrator for John Hosmer. Tr. 168, 169.
13 The Remand Order notes
that Michlink submitted a managed
task package for Hosmer to Fox for approval of Appendix R work.
RO at 10.
14 Davidson drafted the
proposal identifed as CX 18 after the first one was
lost. Tr. 178.
15
"Deliverables" is apparently an engineering term used by
witnesses through the hearing to refer to a product or service.
16 Dr. Fox also testified that
he had not heard of Bartlik
until December 23, 1987. Tr. 708.
17 One of the stated
purposes for the change in contracting
methods was to transfer supervisory responsibility. No doubt the
avoidance of personnel problems was also a major consideration.
18 Robert Bryans was the
United Engineers Project Manager for
Sequoyah. In November, 1987, George Cooper asked him to hire
Bartlik under a managed task contract. Tr. 808.
19 The number of contractors
during the transition period was
reduced from about 100 to 20, Tr. 657, but as previously
mentioned, there was an actual increase in the number of
engineers.
20 Mr. Michlink testified that
there were only five staff
augmentation contracts approved for Sequoyah as of March, 1988,
but previously he had told the Department of Labor investigator
that there were 50 to 60 by that time.
21 For the period from
September, 1987 to October, 1988,
177 personal services contracts were sent to ONP in Chattanooga
for disposition. Of these 177 contracts, 155 were approved, nine
were disapproved, ten were canceled, two were released and one
was declined. CX 30, 34.