U.S. Department of Labor Office of Administrative Law Judges
1111 20th Street, N.W.
Washington, DC 20036
87-ERA-27
In the Matter of
MILTON SHUSTERMAN,
Complainant
vs.
EBASCO SERVICES, INC,
Employer
Milton Shusterman, Pro Se
" For the Claimant
Robert S. Hoshino, Jr., Esq.
Christopher Luis, Esq.
For the Employer
Before: GLENN ROBERT LAWRENCE
Administrative Law Judge
RECOMMENDED DECISION AND ORDER
This proceeding arises under the Energy Reorganization Act,
Public Law 95-601, Section 210, 42 U.S.C. § 5851, which contains
employee protection provisions, commonly referred to as whistleblower
protection provisions, Generally, the provisions prohibit an
employer from discharging or otherwise discriminating against any
employee who engaged in protected activities.
The Complainant, Milton Shusterman, inititated these proceedings
by filing a letter of complaint with the Wage and Hour Division of
the United States Department of Labor on March 23, 1987. In his
complaint he alleges discriminatory employment practices by EBASCO in
violation of the whistleblower provisions. He contends that his
discharge on March 4, 1987 constitutes unlawful retaliation for his
refusal to falsely qualify several nuclear construction material
[Page 2]
vendors.
Pursuant to 29 C.F.R. Part 24, the Wage and Hour Division
conducted an investigation into the alleged violation. On May 1,
1987, the Wage and Hour Division notified the employer in writing
that a fact-finding investigation had been conducted and that it was
found that there was a direct connection between the protected
activity and the employees termination. The employer timely filed an
appeal from this determination by telegram to this office on May 6,
1987.
A hearing was held July 6 through July 9, 1987 in New York.
Pursuant to consent of the parties, the time period within which the
Secretary of Labor may issue his Decision and order was extended 90
days from August 3, 1987 the date the transcript was received.
The following findings of fact and conclusions of law are based
upon my observation of the credibility and demeanor of the witnesses
and upon an analysis of the entire record, arguments of the parties,
applicable statutes, regulations, and case law.
Findings of Fact and Conclusion of Law and Discussion
1. Claimant is a graduate electrical engineer.
2. He commenced work as a senior engineer with Ebasco on August 7,
1978. (T 65)
3. He was the Vendor Evaluation Group Leader of the Quality Assurance
Engineering Department from September 1980 until July 1983.
Claimant had overall responsibility for the operation of that
department and the Vendor Evaluation System. He scheduled audits of
all suppliers of nuclear safety materials and equipment to verify
quality assurance programs were implemented according to the code.
4. In May 1981, Mr. Shusterman found that the James C. White Company
was not producing tube tracks as required by the Code of Federal
Regulations (10 CFR 50, appendix B-Quality Assurance Program) (T 68).
He testified that he was asked to delete his findings. No report was
made to the Nuclear Regulatory Commission. On January 8, 1982 other
qualified auditors found the parts satisfactory (T 77). Mr.
Shusterman signed a letter on January 8, 1982 that after the re-audit
the vendor was satisfactory (T 97).
[Page 3]
5. In February 1982, Mr. Shusterman made a vendor evaluation of
Cardinal Industrial Products corporation. The vendor was found to be
unsatisfactory. The Company continued to use the vendor by placing
them on the supplemental vendor's list.
6. In February 1982 he conducted an audit on Automatic Switch Co. He
gave them an unsatisfactory rating. Nevertheless, his finding was
by-passed and purchases were made from the vendor. Claimant made no
report to the Nuclear Regulatory Commission (T 140).
7. Similar problems developed with Namco and ITT. General Controls.
He was largely by-passed in those activities and vendor approvals
were obtained through other means. Complainant in this case also did
not report the possible violations, as noted above, to the, Nuclear
Regulatory Commission.
8. In July 1983, he asked to be reassigned as he stated he could not
go along with the approval of unsatisfactory vendors.
9. Though he continued to work in quality assurance, he no longer
performed vendor evaluations.
10. The years claimant spent from 1984 to 1987 appeared to be rather
unproductive. He was given some relatively low skill work and he
declined on one or more occasions to take assignments that required
traveling and temporary duty (T 689).
11. Brian Gibson of Ebasco Inc. Quality Assurance Auditing manager
on January, 1987 was assigned to rate all members of Mr. Shusterman's
section in anticipation of a reduction in force inasmuch as their-6
was experienced a substantial over run in January and February 1987.
The rationale of the rating scheme was set out in R1 through R 5.
12. In summary the ratings included employees; 1. A. Performance,
1. contribution this year; 2. contributions last year, 3. skill,
ability, experience or education; B Marketability, 1. Meets todays
market, 2. meets future markets; C, Potential: 1. versatility, 2.
leadership, 3. salary bracket.
13. Mr. Shusterman was rated as follows:
A. 1. 1986 had field assignment in Colorado; some support in New
York office, many weeks in New York an Ohio. Some contribution to
Department revenue, Numerical Rating (NR): 2
[Page 4]
2. overall for past three years contribution to Department not
substantial; considerable time in ohio due to lack of work. Not a
self starter. Contributes only when given specific well defined
tasks, prefers to work alone or with person(s) of his choice. NR: 1
3. Skill strengths are in Supplier Evaluation; extensive
experience; does detailed audits, extensive preparation. Current
demand for supplier audits/evaluations in nuclear field very low,
also minimal in non-nuclear areas. Skills in some demand in Non-HQ
locations; refused consideration for Comanche Peak assignment. NR:2
B. 1. As noted in A. 3, has skills but current market conditions
show small demand. NR:O
2. Do not foresee significant change in market, either HQ or
site; HQ-based audits and supplier evaluations in Nuclear not likely
to increase. Non-nuclear evaluations not good prospect also. NR:O
C. 1. I have not seen a capability for growth on M.S. Part in
current department area of business. Potential in another discpline
is unknown. NR:O
2. Has not shown particular indication of leadership or
management capability; accepts specific, well-defined tasks only. NR:O
3. Is currently 3rd quintile. NR:O
D. Appraisal for 19877, based on current and past experience will no
be higher (better) than 3. NR;l
E. Although accepted certain site assignments in past, was only when
it was clear that there was no other work available, and the alternative
might be be work. Has since referred consideration for Comanche
Peak either short term or six months basis. NR:1
Total NR:7
10. Claimant was terminated March 4, 1987 as one of 4 reductions in
force (RIF) out of a group of 19. There were 17 employees rated
above the claimant.
Discussion and Conclusion
The appropriate legal standard for whistleblower cases filed
[Page 5]
under 42 U.S.C. § 5851 is essentially that of a "but for" test.
Whistleblower cases arising under the Energy Reorganization Act may
be analogized to certain cases arising under the National Labor
Relations Act. See Consolidated Edison Co. of New York v. Donovan
673 F.2d 61 (2d Cir. 1982). Thus, the standard in Wright Line, a
div. of Wright Line, Inc., 251 NLRB 1083 (1980), aff'd sub. nomNLRB
v. Wright Line, 662 F.2d 899 (1st Cir. 1981), applies to whistle-
blower cases. That standard requires the complainant to make a prima
facie showing that supports the inference that that the employee's
protected conduct was a "motivating factor" in the employer's decision.
In other words, the employee would not have been adversely
treated but for his engaging in the protected activity.
The evidence does not support the view that claimants protected
activity was the motivating factor in his discharge. The employer's
witnesses credibily testified otherwise. Further , it was over 4
years since he had a conflict with his employer over quality assurance.
Its strain's credibility to believe, as the complainant
argues, that the employer was in affect, waiting in ambush those 4
years for an opportunity to retaliate against him.
Complainant, did not report the employer to the Nuclear Regulatory
Commissioner nor any Government authority as far as the record
discloses. Further, he more or less concedes that he was not threatened
directly or by implication (T 679). He was not told, though he
had numerous conversations with this supervisors, that he must change
his findings or he would in any way be affected in his employment
status. Rather, it was he who took the initiative to remove himself
from the area of conflict. The employer agreed to this request and it
would appear from this record made an effort to find him employment
with the company in other areas. However, there wasn't that much
work available and the complainant, for perhaps his own good reasons
seemed to decline offers of expanded activity such as the assignment
to Comanche Peak, Texas.
His refusal to perform expanded activities were not shown to be
in support of any protected activity or an effort to avoid committing
inproprieties. it does not appear that the employer's activities in
offering such assignments or its other efforts during the last 4
years were in any manner pretextual or motivated by amimus in the
comtemplation of the whistleblower statute.
Complainant has not shown the other three employee who were RIFED
with him were RIFED on other then proper grounds. Rather, the
[Page 6]
contention of Mr. Shusterman that one or more of the other RIFED
employees (T 684) were RIFED as a cover for the retaliatory discharge
of the Complainant is not crebible (T 684).
The lengthly testimony on how the employees were rated as a basis
for the RIF is subject to argument. However, the witness who rated
the 19 employees seemed reasonable in his findings. Though Mr.
Shusterman could have been rated higher in several categories there
appeared to be no animus or retaliatory motive in the ratings he was
given. Certainly his inclination to refuse other activities was for
his own convenience. These refusals were a reasonable basis for
rating him down.
Further, the ratings seemed to reflect an honest business
judgment rather than any hostile motive. one could argue that the
chain of circumstances that began with the complainant's rejection of
the quality assurance work resulted in his being RIFED 4 years later.
However, this would appear to be a philosophical abstraction and
entirely too remote and lack certainty from a legal standpoint. The
evidence and testimony at this hearing did not establish that the
complainant was RIF'ed for retaliatory motive.