05/27/1986 - Request for a variance from decompression tables as delineated in 29 CFR 1926.803.

Standard Interpretations - Table of Contents Standard Interpretations - Table of Contents
• Standard Number: 1926.803

May 27, 1986

Mr. Michael Tomaro
President
Tomaro Contractors, Inc.
P.O. Box 1986
Cudahy, Wisconsin 53110

Dear Mr. Tomaro:

This is in response to your letter dated May 12, concerning your request for a variance from the Occupational Safety and Health Administration (OSHA) decompression tables as delineated in 29 CFR 1926.803.

Without regard to the adequacy of your application, your request to substitute the so-called National Institute for Occupational Safety and Health (NIOSH) decompression tables for those prescribed by the standard cannot be acted upon at this time by this office. The report has not as of this time been endorsed or published by NIOSH. Until such time as it may be endorsed we have no basis for judging its equivalence for purposes of safety and health as required for issuance for a grant of permanent variance.

I would point out, however, that your concern with the need for use of automatic decompression controllers to regulate pressure in the decompression lock may be founded since section 1926.803(g)(1)(iii) only requires these controls where the air pressure in the working chamber exceeds 12 psi.

No further action will be taken on your request for a variance. Please contact me at (202) 523-7193, if you have any question.

Sincerely,



James J. Concannon
Director
Office of Variance Determination


Standard Interpretations - Table of Contents Standard Interpretations - Table of Contents


Back to TopBack to Top www.osha.gov www.dol.gov

Contact Us | Freedom of Information Act | Customer Survey
Privacy and Security Statement | Disclaimers
Occupational Safety & Health Administration
200 Constitution Avenue, NW
Washington, DC 20210