Caithness Big Sandy Project, Wikieup, AZ, DOE/EIS-0315

The EIS is on hold pending further review. See below.

Caithness Big Sandy Project DOE/EIS-0315-S1 (Supplement Analysis)

Big Sandy Energy requested transmission service to interconnect a proposed 720-MW generating facility near Wikieup, AZ., with the Mead-Phoenix Project 500-kV transmission line. Western is partnering with the Bureau of Land Management in Kingman on this project.

The powerplant plan includes a proposed high-pressure natural gas pipeline, permanent access road and water pipelines that would cross BLM-administered land. Because the project could "significantly affect the quality of the human environment," studies must be done to identify environmental effects.

Project updates:

BLM and Western have delayed issuing the Supplemental Draft EIS at the request of the applicant, Caithness Energy.

Contact information:
NEPA Document Manager
Environmental Manager
Desert Southwest Customer Service Region
Western Area Power Administration
P.O. Box 6457
Phoenix, AZ 85005-6457
602-352-2592
Fax: 602-352-2630