www.OSHA.gov | |
Regional and Area Office Alliances > Region V > Alliance Final Report |
![]() ![]() |
|||||||||||||||||||||||||||
FINAL AREA OFFICE ALLIANCE REPORT MESSER CONSTRUCTION CO. Columbus Area OSHA Office July 30, 2006 |
||||||||||||||||||||||||||||
I. Alliance Background Date Signed. December 28, 2004 Alliance Overview. To educate, share best practices, address near misses, and share accident information with all construction trades on the Federal building upgrade project. Implementation Team Members. Chris Matthewson (Compliance Assistance Specialist)-OSHA Allan Dinsmore (Project Executive)-Messer Construction Co. Brandon Herdman (Safety Coordinator)-Messer Construction Co. Alison Muth (Director of Safety)-Messer Construction Co. II. Implementation Team Meetings All meetings were held on site at the Bricker Federal Building and at each meeting employees’ input and safety and health suggestions were discussed. January 10, 2006: Eye and hand protection February 7: Housekeeping and general construction Safety March 7: Ergonomics-Back Safety and Lifting April 4: Electrical Safety-The Basics May 2: Ladder Safety June 6: No meeting was held due to the fact the job was almost completed and only five workers left on site. III. Activities and Products Evaluation Period. This final report covers from January 2006 until the end of the alliance, June 29, 2006. Alliance Activity.
This report outlines the success that has been achieved during the whole project including the last 6 month period. Total hours worked for the project was 115,000. During the entire job there were only five recordable injuries with no loss time injuries. OSHA has opened the safety and health communication lines between Messer Construction Co. and GSA. The construction trades believe this is one of the safest jobs they have worked. There have been positive responses from the various trades on this project regarding how fast safety and health issues are addressed and corrected. The trades have been very positive and assisted the company’s safety coordinator in collecting photographs of the jobs depicting their best practices. The photographs are in the Power Point presentation which is attached. All the work was completed by contractors during the second shift. Worker fatigue was overcome because the trades emphasized the importance of safety to their fellow contractors. There were five OSHA recordable injuries, which included lacerations, foreign object in the eyes, and back sprain. There were no lost time injuries. The DART rate was 0.00 for the whole project. The CAS worked very closely with Messer Construction Co. and the contractors. The contractors were appreciative that the CAS attended the monthly safety meetings and offered his assistance in resolving safety and health issues.
V. Upcoming Milestones The alliance has covered all training issues that were suggested by the contractors and workers, keeping safety in the forefront of all discussions. The alliance Power Point was completed with all updates and was distributed to all contractors. GSA, who oversaw this project, has recommended this project for a GSA federal award. The project was within budget and was completed two months ahead of schedule. The job was officially to be completed June 29, 2006. Report Prepared by: Chris Matthewson For more information, contact the Office of Outreach Services and Alliances at 202-693-2340 or go to www.osha.gov.
|
||||||||||||||||||||||||||||
![]() ![]() |
www.dol.gov | |
Contact Us | Freedom of Information Act | Customer Survey Privacy and Security Statement | Disclaimers |
||
Occupational Safety & Health Administration 200 Constitution Avenue, NW Washington, DC 20210 |