RMP Schedule
Draft RMP/EIS Contents Page
Proposed RMP/Final EIS Contents Page
The revised tentative schedule for the Butte RMP is shown below.
Butte RMP Tentative Schedule |
Task |
Approximate Date |
Draft RMP/EIS to Public/Start
Public Comment Period |
June 8, 2007 |
Public Meetings |
July 2007 |
90-Day Public Comment
Period ends |
October 9, 2007
|
Proposed Final RMP/EIS to Public/Start Protest Period |
September 26, 2008 |
30-Day Protest Period ends |
October 27, 2008 |
Record of Decision and Approved RMP
(if unprotested) |
December 2008 |
Record of Decision and Approved RMP
(if protested) |
April 2009 |