News January-March 2004
News Release: March 3, 2004 | View Printable PDF Version |
Docket Numbers: RM02-1-001 |
Commission Reaffirms Interconnection Rule, Clarifies Pricing
Policy
The Federal Energy Regulatory Commission today reaffirmed its July
2003 rule (Order No. 2003) that sets standard procedures and agreements
for the interconnection of generators larger than 20 megawatts—a
move designed to facilitate development of needed infrastructure
for the nation’s electric system.
Interconnection plays a crucial role in bringing much-needed generation
into national energy markets to meet the growing needs of electricity
customers, the Commission said today in standing by the legal and
policy considerations detailed in its earlier decision.
The rule requires the approximately 176 investor-owned public utilities
that own, control or operate interstate transmission service to
offer non-discriminatory, standardized interconnection service.
It amends Order No. 888’s pro forma tariff to help remedy
remaining undue discrimination under the open access required by
Order No. 888.
Responding to requests for clarification of its pricing policy for
network upgrades, the Commission made it clear that the transmission
provider continues to have the option to charge the interconnected
customer a transmission rate that is the higher of the incremental
cost rate for the network upgrades required to interconnect its
generating facility or an average embedded cost rate for the entire
transmission system (including the cost of the network upgrades).
The Commission emphasized that allowing transmission providers to
charge the
higher of an incremental cost rate or an embedded cost rate ensures
that other transmission customers, including the transmission providers’
native load, will not subsidize network upgrades required to interconnect
merchant generation.
This policy recognizes that all customers benefit from a stronger
transmission infrastructure, more reliable service and more competitive
power markets, the Commission said.
The Commission granted rehearing on two aspects of Order No. 2003’s
method for reimbursing generators for the cost of financing network
upgrades needed to complete the interconnection.
First, the Commission will no longer require the transmission provider
to provide credits to the interconnection customers for all of the
transmission delivery services it takes on the system; instead credits
are provided only for the transmission delivery service taken by
the interconnecting generating facility. Second, the Commission
will allow the transmission provider to choose, five years from
the commercial operation date of the generating facility, whether
to reimburse the interconnection customer at that time for any remaining
balance of the cost of financing network upgrades and accrued interest,
or continue to provide credits beyond five years until no balance
remains.
The Commission also concluded, as it did in Order No. 2003, that
it would accord additional flexibility to interconnection pricing
proposals that are filed by an independent transmission provider.
An independent transmission provider does not have an incentive
to discourage new generation by competitors, and should be afforded
more flexibility in manner of cost recovery.
Action on a proposed companion rule that applies to interconnection
of small generators-- those smaller than 20 megawatts -- is still
pending before the Commission and will be addressed in the near
future.
Today’s order is effective 30 days after its publication in
the Federal Register.
View Printable PDF Version |