ISSUE DATE: JULY 11, 2003

PROGRAM INFORMATION BULLETIN NO. P03-15

FROM:           RAY McKINNEY  RAY McKINNEY
                       Administrator for
                             Coal Mine Safety and Health

                        MARK E. SKILES  MARK E. SKILES
                        Director of Technical Support

SUBJECT:    Compliance with Diesel Particulate Matter Standard in
                        Underground Coal Mines for Nonpermissible Heavy-Duty
                        Diesel-Powered Equipment, Generators, and Compressors

Scope
This Program Information Bulletin (PIB) affects underground coal mine operators using diesel-powered equipment, manufacturers of diesel-powered underground mining equipment (including manufacturers of exhaust aftertreatment devices and systems), miners' representatives, and Mine Safety and Health Administration (MSHA) personnel.

Purpose
The purpose of this bulletin is to inform underground coal mine operators and Coal Mine Safety and Health (CMS&H) personnel about compliance requirements with 30 CFR Section 72.501(a) effective May 21, 2001; 72.501(b) effective July 21, 2003; and Section 72.503. This bulletin should be utilized in conjunction with PIB Number P03-14 on "Diesel Particulate (DP) Filter Use and DP Equipment Maintenance Information for Underground Coal Mines."

Information
MSHA published a final rule on Diesel Particulate Matter (DPM) emissions in underground coal mines in the Federal Register on January 19, 2001, (66 FR 5526). This bulletin describes the compliance requirements for underground coal mine operators who intend to operate nonpermissible heavy-duty diesel-powered equipment, generators, or compressors underground on or after July 21, 2003.

1. Aftertreatment devices must be installed on all nonpermissible heavy-duty diesel-powered equipment, generators, or compressors that emit more than 5.0 grams/hour when operated in an underground area of an underground coal mine as of July 21, 2003. Mine operators who do not comply will be cited for failure to implement DPM controls under 72.501(b).

2. MSHA will permit the operation of a nonpermissible heavy-duty machine introduced after July 21, 2003, for which an exhaust gas temperature profile must be run before the appropriate DPM filter can be selected. MSHA will allow operation of these machines without a filter for no more than 48 hours. However, the mine operator must first notify the local District Manager of the 48-hour period that the test will be run and provide the machine serial number. The operator must receive acknowledgement from the District Manager prior to placing the machine in the mine. In some instances, the District Manager may grant additional time up to 7 days to complete testing on a case-by-case basis for multi-use machines. Failure to obtain the acknowledgement and permission of the District Manager will result in a citation for violation of 72.501(b). The test allowance is not available for generators, compressors, or any other diesel-powered equipment.

3. The District Manager should be notified if the mine operator continues to be unable to meet the requirements of 75.500, 72.501(a) or (b), and 72.503. MSHA will provide compliance assistance with the DPM standards.

4. If the mine operator has installed aftertreatment devices, they must be maintained in accordance with 72.503.

5. If the mine operator does not have an aftertreatment device installed on or after July 21, 2003, MSHA will issue a citation. This citation shall require the mine operator to submit a compliance implementation schedule to the local District Manager. In establishing or extending an abatement period, the District Manager will consider whether the failure to install an aftertreatment device was due to: 1) non-availability from the engine manufacturer or exhaust aftertreatment device manufacturer, 2) a documented design problem, or 3) non-availability of an exhaust gas temperature profile for selecting an aftertreatment device. The mine operator's good faith efforts to install an effective aftertreatment device to meet the DPM emission requirements, as evidenced by purchase orders with delivery dates and active involvement in testing of feasibility and modification of aftertreatment devices will be considered in the abatement process.

6. The Program Information Bulletin issued on May 31, 2002, (PIB-P02-04) on the "Potential Health Hazard Caused by Platinum-Based Catalyzed Diesel Particulate Matter Exhaust Filters" identified some platinum-based particulate filters as a source for generation of increased emissions of nitrogen dioxide (NO2). This PIB remains in effect. MSHA can assist mine operators in choosing a filter that does not increase NO2. A list of acceptable filters is provided on the MSHA web site "Diesel Particulate Matter (DPM) Control Technologies" at http://www.msha.gov/01-995/Coal/DPM-FilterEfflist.pdf.

Background
MSHA's final diesel particulate rule for underground coal mines established new requirements for the emission limits for permissible and nonpermissible diesel-powered equipment over a phased-in schedule. This bulletin clarifies the compliance responsibilities of underground coal mine operators with 30 CFR Sections 72.501(a), 72.501(b), and 72.503.

Authority
30 CFR Part 72 Subpart D and 30 CFR Part 75 Subpart T

Issuing Offices and Contact Persons
Coal Mine Safety and Health, Health Division
Melinda Pon, (202) 693-9516
Pon.Melinda@dol.gov
Robert Thaxton, (202) 693-9515
Thaxton.Robert@dol.gov

Technical Support, Approval and Certification Center
George Saseen, (304) 547-2072
Saseen.George@dol.gov
Robert Reed, (304) 547-2043
Reed.Robert@dol.gov


Internet Availability
This information bulletin may be viewed on the Internet by accessing MSHA's home page at http://www.msha.gov by choosing "Statutory and Regulatory Information" and "Compliance Assistance Information."

Distribution Coal and All Volume Program Policy Manual Holders
Underground Coal Mine Operators
Special Interest Groups
Equipment Manufacturers




Back to Top   Back to Top www.msha.gov www.dol.gov


Mine Safety and Health Administration (MSHA)
1100 Wilson Boulevard, 21st Floor
Arlington, VA 22209-3939
Phone:    (202) 693-9400
Fax-on-demand: (202) 693-9401
Technical (web) questions: Webmaster
On-line Filing Help: MSHAhelpdesk@dol.gov
or call (877) 778-6055

Contact Us