MMS -- Minerals Management Service Home -- MMS Pacific O.C.S. RegionSearchTopic IndexAbout MMSWhat's New -- News & Updates U.S. Department of the Interior
Minerals Management Service Pacific O.C.S. Region

Skip to Main Content
Contact Information
Library
Organization
What's New

Intern Programs
Kids and Education

Environmental Info


Fisheries Biology
Rocky Intertidal Ecology
Lease Info
Boundaries/Maps
Lease -- Summary Report

Offshore Info

Annual Reserves Report

Facts & Figures
G & G Permits Online
Notices to Lessees
OCS Regulations
Platform Information
Resource Reports
Revenue Information
Safety Alerts
Safety Awards



Freedom of Information Act
Privacy Act/Disclaimers
Accessibility
Public Connect



Support Our Troops Logo with Eagle and Flag

Take Pride in America Flag Logo



        Questions?
   Need more information?
           Please Write:
 Pacific Public Information

            Comments
     about our website?
    Contact Web Master

Safety Alerts


Pacific OCS Region Safety Alert graphic

                                                                                  Notice No. 10
April 16, 1993

LIFTING OPERATIONS

During repositioning of a sand bin with a crane on a Pacific Outer Continental Shelf Region (POCSR) platform recently, two of the pad eyes broke and one end of the bin fell and punctured holes in the platform deck. In addition, there have been a number of rigging failures during cargo transfers between supply vessels and POCSR facilities during the last few years, some of which resulted in cargo losses overboard. To prevent recurrences of these types of accidents, the Minerals Management Service (MMS) has identified safety measures to be followed:

1. When bins or other containers are moved by crane, operators should ensure that the stresses on the pad eyes, due to (1.) the weight of the bin and its contents, (2.) the configuration of the slings, and (3.) the dynamic offshore conditions, do not exceed design capacity for the pad eyes. The design criteria, with applicable safety factors, must be taken into account along with any visible corrosion or weakening of critical parts of the transfer containers.

2. With respect to the rigging failures, operators must follow the measures specified in American Petroleum Institute Recommended Practice for Operation and Maintenance of Offshore Cranes, API RP 2D, which is incorporated by reference into MMS's regulations at 30 CFR 250.20, Safe and workmanlike operations, (c) Crane operations. The sections on handling, attaching, moving, and holding the load are particularly pertinent to this matter.

Our Safety Alert Notice #8, dated January 28, 1993, entitled "Lifting Operations," highlighted the measures relevant to a fatal accident involving a load which dropped due to a parted sling.

Careful consideration of all lifting operations is necessary because of the tragic results that can come about due to equipment failures or lapses of attention or judgment.