A&E Rating
Guidelines for all Phases (1-5)
A&E Rating Guidelines
|
Unsatisfactory
|
Performance
does not meet contract requirements. Completion did not occur in a timely or
cost effective manner. The evaluated performance element contains a serious
problem(s) for which corrective actions were unacceptable or non-responsive.
|
Poor
|
Performance
marginally meets contract requirements. The evaluated performance element has
problems for which proposed or completed corrective actions were marginally
satisfactory.
|
Good
|
Performance
meets contract requirements. The evaluated performance element was
accomplished with problems for which proposed or completed corrective actions
were satisfactory.
|
Excellent
|
Performance
meets contract requirements. There were no substantive issues. All corrective
actions were completed in a timely and effective manner.
|
Outstanding
|
Performance
exceeds some contractual requirements to the Government’s benefit. Examples
include design/construction phase services: completed under budget; ahead of
schedule; exceptional security management; quality, completeness and
coordination exceeded contract requirements; and exceptional project and
design team management. (Note: Rating only given when contractor clearly