Maximo Implementation Project Team
Home | Team | Processes | Documents | Dates | Issues
Our Objective:
To implement Maximo 6 by September 25, 2006 to support the NCI-Frederick's core business requirements within:
- Facilities Maintenance
- Engineering
- Property Accountability
- Supply Warehouse
- Service Contract Management
News
- 9/2: More Dates Added
- 9/2: Project Schedule Status Updated in Documents
- 9/2: Training Material Drafts Published in Documents
- 9/1: 350 Conference Room A Secured for Train-the-Trainer Training
Note: Team will need to secure 10-12 laptops for training activities.
- 8/10: More Dates and Documents Published; Schedule Revised and Updated
- 7/14: More Dates and Documents Published; Schedule Updated
- 7/10: Integration with External NCI-F Systems has Started
- 6/30: New Dates and Documents Published
- 6/29: Remote Access Arranged for MRO Team
- 6/28: Software Installation Complete and Verifed
- 6/26 Data Mapping and Migration has Started
- 6/24: Hardware Installed and Configured
- 6/16: Workshops Concluded - Thanks to All Participants
- 6/15: Partial Reciept of Hardware
- 6/6: Hardware Ordered; ETA: 6/22
- 6/2: Software Installation CD's Received
- 6/1: MaxIPT@css.ncifcrf.gov E-Mail list created for Maximo IPT Core Team.
- 6/1: System Administrator's Guide posted to Documents Repository.
- 6/1: Workshop Documents posted to Documents Repository.
- 5/31: Team Website launched.
- 5/31: MS Project Viewer acquired.
- 5/31: Immersion training confirmed for week of June 19th.