The National Institutes of Health. Office of Community Liaison.
Home > Meeting Minutes

Community Liaison Council Meeting Minutes
May 18, 2006, 4:00–6:00 p.m.
Visitor Information Center, Building 45 (Natcher Building)
National Institutes of Health

HANDOUTS

  • March 16, 2006, CLC Meeting Minutes
  • February 16, 2006, CLC Meeting Minutes
  • May 2006 NIH News in Health
  • Biographical Informational Sheet—Juanita Holler-Mildenberg
  • Campus Perimeter Shuttle Schedule

WELCOME AND ANNOUNCEMENTS

By John T. Burklow, Acting Director, OCL, NIH

Mr. John Burklow called the meeting to order and announced that Juanita Holler-Mildenberg, Acting Director of the Office of Research Facilities, would give a presentation to answer a number of questions raised by the Council.

PRESENTATIONS

General Updates
By Ron Wilson, Acting Director, Division of Facilities Planning, ORF, OD, NIH

Mr. Ron Wilson reported that all temporary parking lots to be closed are on target and are in the process of being returned to green space. They will all be completed around mid-June and lot 41-C should be completed by the end of next week.

Mr. Wilson also reported that ORF, working through the Division of Physical Security, been able to turn down the lights during the evening hours at the Commercial Vehicle Inspection (CVI) station as suggested by some CLC members. Mr. Ralph Schofer mentioned that his constituents have often expressed concern about the lack of light between the Metro station and Cedar Lane on the walking path adjacent to Rockville Pike. The pathway is black asphalt and the glare of car lights in the pedestrian’s eyes, combined with the lack of light fixtures on the walkway, makes it difficult to see. Mr. Wilson replied that the illumination plan for the CVI station area could solve some of the problem. More discussion followed, with Ms. Ginny Miller asserting that this is a problem all up and down Rockville Pike on both sides. She suggested that this is a County and/or State Highway Administration problem. Mr. George Oberlander added that a similar situation exists on Old Georgetown Road. The problem is much broader than just around NIH, according to Mr. Tom Hayden.

Ms. Anna Franz of ORF updated the Council on the Building 36 demolition project by distributing a handout that summarized the project’s approach to demolition noise mitigation. The demolition is progressing well and should be completed by early September, possibly even sooner. There are four main types of equipment being used for the project. These include the "hoe-ram," which breaks slabs into large pieces; the "wap hammer," which pulls pieces apart after rebar isolation, a Bobcat with bucket, which is used to remove large pieces, and a crawler/excavator with grapple, which is used to remove debris. The rebar is cut into pieces and recycled, and a muncher processes debris, making it possible to recycle the concrete also.

Ms. Franz introduced Mr. Bob McDonald, Building 36 Project Officer for the demolition, who said that an extensive quality control plan was in place for the project and it is strictly followed. The project was designed to reduce noise and vibration to a minimum because of ongoing research in nearby buildings, as well as to avoid as much discomfort for the neighbors as possible. The best-value procurement was used; they priced less noisy methods, such as "munching" the entire building, but found this would add tremendous additional cost, on the order of $1 million. The hybrid or combination method being used offered the best value; it is not the quietest possible way to take the building down, but it offers the best combination of cost efficiency and noise reduction. Another consideration was the duration of the project; quieter methods take longer, and completing the project more quickly has value also. The material from the building is being processed so that most of it can be recycled. For example, all of the steel (from duct work, etc.) and the rebar can be recycled, and even the concrete itself. The processing is done off-site as much as possible; pieces are first reduced to movable size and then trucked off-site. Noise measurements are taken every day and the project has consistently been within County limits. Work begins at 6 a.m., but nothing noisy is allowed before 8 a.m. Noise earlier than that is not intentional. Every attempt is made to keep the noise down in the early hours and end by 4 p.m.

Mr. Schofer asked how they separate rebar from concrete. Mr. McDonald explained that the muncher eats the concrete off the rebar, shaking the slab until only rebar is left. A market exists for concrete rubble; it can be used as highway bed filler and reprocessed into aggregate for new concrete, etc. Mr. Steve Sawicki said that at times, the noise levels became nearly unbearable in his neighborhood. It is loud and constant. He wondered why they had not used implosion and taken the building down all at once. Mr. McDonald answered that they had looked at implosion, but had concluded that the building was not tall enough to break things up sufficiently. Even after the building was destroyed, slabs would still have to be broken up on the ground. They looked at every possible demolition method and decided that the present method was the way to proceed. Mr. Oberlander asked if their sound measurements took all the ambient noise into account, or just that from the demolition. Mr. McDonald said the measurements include noise from Porter, etc., and from the demolition, but noise from Old Georgetown Road cannot be considered. Once the project is completed, the site will be maintained as a fenced construction site, with grass planted to maintain the soil. Mr. McDonald explained that congressional language states the area is intended to be maintained in an interim condition until Porter, Phase II, construction funding is approved. The cleared site will not be used for a parking lot, but the staging area will be maintained rather than restored and torn up again. Mr. Schofer asked why NIH did not simply remain in the building when it found out it could not proceed with the Porter, Phase II, construction. Mr. McDonald pointed out that it would have cost a great deal of money to re-occupy the building, and NIH had already undergone considerable expense to move people out.

ORF Initiatives
By Juanita Holler-Mildenberg, Acting Director, ORF, OD, NIH

Ms. Juanita Holler-Mildenberg explained that the ORF is responsible for and has the authority to manage and maintain the NIH physical plant. She believes it is taken care of well. Ms. Mildenberg said that during the period when NIH’s budget was being doubled, construction was robust. The budget increases resulted in requirements for new facilities. Thus the Clinical Research Center, a very large, state-of-the-art hospital, was built; the Family Lodge was replaced by the new Children’s Inn; a new Fire Station replaced the outmoded and ineffective, antiquated facility; a new electrical substation was built; and Building 50 was built; all largely within a five-year period. Most of this construction was in research and support areas. Administrative expansion was handled mostly with off-campus leases. These were consolidated into a few places, such as the Twinbrook and Executive Boulevard complexes and the Rock Spring area.

Present construction includes the CVI station and the Gateway Center, with its 350-vehicle underground parking lot. These facilities are intended to allow access to NIH and provide the needed security. Both are in the buffer zone because of security regulations as a result of 9/11. All vehicles or persons entering the campus must now be checked. Both facilities must therefore be on the perimeter of the campus outside the security fence. Ms. Mildenberg assured the Council that no other facilities are planned for placement in the buffer zone. NIH does have three major building priorities. These are Porter, Phase II, a new animal holding facility, and the Building 10 core renovation project. However, with present funding, none of these is likely to start within the next three to five years. The FY2007 budget for the physical plant is the same as in 2006: no money is allocated for new construction. The budget allows for maintenance of the current infrastructure, including essential safety and repairs, changes necessary to comply with handicapped access regulations, and projects aimed at keeping the existing facilities completely operational.

Ms. Lesley Hildebrand wondered why money was allocated for demolition, but none for the replacement construction of the Porter, Phase II, building. Ms. Mildenberg replied that money had been requested for Phase II but none had been approved. The federal budget is tight because of many things, including the war in Iraq, Hurricane Katrina relief, etc.

Ms. Mildenberg reported that the NIH Master Plan was updated in 2003, and the total projected employee capacity on the Bethesda campus is about 22,000. Some Council members have expressed concern about growth on campus. She reported that in the late ’90s, 17,400 employees were housed on the Bethesda campus, but in 2005, there were roughly 18,000. In other words, growth has nearly stopped, directly as a result of budget cuts. Leased facilities in the region formerly housed about 5,600 employees, but this has grown to about 9,800, and these facilities include approximately 3.3 million square feet. Thus, the main campus has not grown, but administrative increases have caused growth in the surrounding area. Ms. Mildenberg told the Council that NIH cannot predict when the 22,000-employee ceiling will be hit. She noted that it is difficult to predict the future. For example, a pandemic flu or some other such emergency could necessitate rapid growth. Nonetheless, the intent is still to not exceed 22,000 employees on the Bethesda campus.

In response to a Council question about what lessons NIH has learned to prevent another Porter-like noise problem, Ms. Mildenberg said that her office is always learning from projects. On all future construction, they are looking at design specifications and where mechanical housings are placed and are being especially careful about quality control of the construction. NIH has well-qualified individuals who can assess projects. Some proposals are excellent but follow-through is lacking. She acknowledged that NIH Project Officers must be part of the process, and they are being trained in oversight. Assessment of contractor work is a critical step, and failure to perform sometimes results in termination, but this can be very costly. Good quality control is important to the whole process. The Council discussed the Porter Building noise problem and the length of time involved to mitigate the issue. There is a perceived resistance by the NIH to correcting things. Ms. Mildenberg agreed that there had been some problems, but noted that every project was different. The trick is to bring lessons back into the system so problems are not repeated.

Another Council question was if any other federal agencies had offices on the Bethesda campus. Ms. Mildenberg answered that only the Food and Drug Administration (FDA) had any presence, with about 450 employees in the Center for Biologics Evaluation and Research (CBER). They are scheduled to leave in 2014. She told the Council it would be difficult to ask them to leave earlier. FDA is a sister HHS agency and the group is relatively small. They have been on the campus for years, and FDA’s budget is just as tight as NIH’s; besides, they do similar research, so their presence is logical. NIH has no plans for any other agency to come onto campus.

Ms. Mildenberg told the Council that the new Gateway Center is scheduled for completion between March and April 2007, and the new Vehicle Inspection Station will open in mid-October of this year. She assured the Council that the hours of the new facilities would be the same as at present, so she anticipates no new disruption once they open. Mr. Schofer wondered if the Commercial Vehicle Inspection hours could be scheduled to be outside peak traffic hours. She answered that if you attempt to schedule deliveries at specific times, you pay a premium price. Mr. Oberlander asked if NIH had any intent to consolidate any of the leased facility personnel onto campus. She assured the Council that NIH has no such plans but that if the budget continues flat or declines, it might be necessary to reduce staff. And if enough space opened up, they could perhaps pull people to the campus to save money. In any case, the number of employees on the Bethesda main campus should not exceed 22,000.

NIH Reforestation Plan Update
By Kenny Floyd, Director, Division of Environmental Protection, ORF, OD, NIH

Mr. Lonnie Darr showed a photograph of the area in 1951, where the 310-acre NIH campus had 85.47 acres of forest and the Cedar Lane woods were still in place. A photograph from 1998 showed development reduced this area to 55.18 acres of woods. In 2004, a tree inventory was completed, with more than 6,000 individual trees on the campus mapped. Despite some infill planting and natural regeneration, the canopy had been reduced by about 6 acres to 49.89 acres. This apparent reduction, Mr. Darr explained, was probably more due to better resolution than to actual tree loss. The campus in 2006 still has about 50 acres of woods. He estimated that by 2023, the period covered by the current Master Plan, the campus will have roughly 110 acres of woods. In 1951, many of the trees had just been planted. These are now more mature. The NIH works hard to keep trees in good condition. Mr. Darr pointed to lots of reforestation near Building 10, and said that areas along the hillside are to be enhanced. He said that even though the campus has lost around 400 trees due to the visitor’s center, mostly white pines, they are all replaced at slightly more than a 1-to-1 ratio. NIH works very hard, retagging trees, keeping the inventory up to date, noting what needs to be removed, and planting new trees.

Ms. Miller noted that along the Old Georgetown Road corridor the campus was unattractive because you don’t see many trees. Mr. Darr replied that this area has lots of lawn. He pointed out that an effort was being made to reduce the amount of turf in the buffer zone, but this takes time, especially on a limited budget. He expressed hope that the whole corridor is a priority for reforestation. Mr. Oberlander suggested that the NIH should add reforestation priorities to their Master Planning. Mr. Wilson replied that the open space character is planned. At the present, more of a lawn treatment is the plan for the Old Georgetown Road side. To change this, they would have to modify the Master Plan.

Ms. Deborah Michaels asked if the new Commercial Vehicle Inspection Station, in the buffer zone, would be landscaped with trees along the road. Mr. Wilson answered that the site plan has a substantial landscaped buffer along Rockville Pike, with a berm, and will provide a nicer frontage, a softer edge to the campus. Mr. Darr mentioned that deer are usually a big problem with reforestation projects. Ms. Hildebrand asked what the projected forest canopy cover would be in 2023 and wondered if a plan for this already existed. Mr. Darr answered that a plan was in place. NIH will make a concerted effort to fill in, and with natural growth, maximize the canopy cover on campus. He said the approved forest conservation plan projected 110.75 acres by 2023, approximately double the canopy cover today. This means that although the County requirement is around 20%, the NIH will then have roughly 35% canopy cover. Mr. Oberlander commented that he had seen roses on the retaining wall near the Clinical Center and noted how beautiful they were.

Noise Abatement Update
By: Kenny Floyd, Director, Division of Environmental Protection, ORF, OD, NIH

Mr. Kenny Floyd showed a map of all the noise-sampling points, both on campus and off. He showed photographs of sampling devices on the roof of Building 37, aimed toward Porter. He gave the Council a list of things the NIH needed to consider for mitigation, noting that quite a number of buildings were affected. Many are things like silencers and acoustical louvers that can be accomplished relatively quickly. He mentioned that they are behind in obtaining recommendations from the consultant. He must review the list to see which projects can go forward. Mr. Floyd showed a picture of things already done. These include machinery mounted on spring-like vibration dampers and a similar noise-dampening joint on stacks. He explained that the NIH technical people will select the recommendations on which they can move forward, and the projects they select will be fast-tracked through design and implementation. The next phase of the noise study will be the modeling, which will continue into summer, with final recommendations based on the model. These will include short- and long-term projects. Ms. Hildebrand commented that this project seemed very slow; she would have appreciated a better response from the consultant. The CLC Noise Committee also feels left in the dark a bit. They feel the updates have been insufficient and would really have appreciated better organization so they could have provided real input. Mr. Floyd agreed that the consultant has not been as responsive as desired; he said he was following up with steps he could take to move him forward.

South Lawn Update
By Tony Clifford, Chief Engineer, NIH, OD, ORF

The consultants working with Mr. Tony Clifford have planned a complete survey of the southwest portion of campus, including underground utilities and anything that has an impact on the project. They will include a hydrologic analysis and a profile of the soil for drainage and absorption. This survey will be completed by June 26, 2006. Mr. Clifford mentioned that the county drain line was getting worse, causing erosion and threatening damage to a nearby large tree. Solving this problem is complicated by the tree and must involve the County. By July 17 they will also have completed an assessment of safety aspects of the field. The consultant wants to hold a workshop with community representatives to obtain their input. The time for this will be determined by their availability. By July 31, a draft report will be ready for comment by the community. He hopes to have a formal presentation ready by August, with the final report ready to submit to NIH by September. Mr. Clifford reiterated that the consultant wants interaction with the community. He believes the survey will establish the facts and a work group will spend time looking at the site with the consultant and will then spend time around the table to discuss options and solutions. The consultant agrees with Mr. Clifford that the County must be involved, but it needs a clear understanding of the problem first. Mr. Sawicki commented that they needed to make sure the County does not slow or impede progress. Mr. Clifford said to be fair to the County, that it is not resistant. Ms. Miller noted that this time line seemed too long. Mr. Clifford clarified that it included time for interaction with the community, and he wants to be sure the Council and the community have time to comment on the draft plan. Mr. Oberlander asked for assurance that Mr. Clifford would keep the Council informed. Mr. Clifford replied that he certainly would, both at the monthly meetings and in the work group sessions. Ms. Michaels asked if they needed to collect data during rainy periods and drought, etc. Mr. Clifford answered that this was not necessary. He thinks the previous contractor did not understand the water source. The Council wondered if the projected August report would be full and complete. Mr. Clifford answered yes; he is hoping for a pretty straightforward solution. He added that the field will be accessible to people for the summer, he does not plan to replant the grass. He pointed out that soccer players were the biggest problem; their cleats are ripping up the grass, which unfortunately never really got started. Ms. Hildebrand wondered where the workshop would be held and Mr. Clifford answered that it would be somewhere convenient for Council members. The consultant suggested that the workgroup include a visit to the field as a part of the first meeting so all can clearly see the issues and concerns. Seeing the field and the issues first hand would be more productive than looking at drawings.

CLC ROUND ROBIN

Mr. Burklow acknowledged that this was the first time the Council has had a formal meeting since the death of John Dattoli. He died very suddenly, of a heart attack, leaving his wife and three children. Mr. Burklow said that Mr. Dattoli; was an outstanding NIH employee and will be sorely missed. Mr. Burklow announced that a fund has been established for the education of the children. Ms. Amy Blackburn has more information for any who would like to contribute.

Mr. Burklow also announced that a selection has been made for the new director of the OCL. His name is Dennis Coleman, and he was previously mayor of Half Moon Bay, California. Mr. Burklow said he is well qualified and in the interviews had shown a keen insight into the demands and needs of the job. He has a law degree and as both a Councilman and a mayor of Half Moon Bay, he has had to deal with community issues. Mr. Burklow announced that Mr. Coleman will join the NIH by late summer.

Mr. Burklow also thanked Mr. Hayden and Mr. Wilson for their work on the intersection of South Drive and Old Georgetown Road. He noted that their persistence had paid off: the State will install a left-turn light, sidewalks and crossing buttons, and a dip for wheelchairs and bicycles and will square off the crosswalk. The schedule is to start the project in September and have it completed in November. On the North Drive side, they will block off the side streets so the illegal left turns will no longer be possible within the next 60 days. Finally, Mr. Hayden said that rumors that the perimeter shuttle would be discontinued are not true; the shuttle will continue to run on its current schedule. The perimeter shuttle ridership is being monitored daily and adjustments may be made in the future. Any changes to routing, scheduling and times would be brought before the CLC prior to implementation. Changes to the route would be based on sound financial and business data.

ADJOURNMENT

The formal meeting ended at 6:15 p.m.

ACTION ITEMS

  • Mr. Floyd will follow up with the noise consultant and report developments to the CLC.
  • Mr. Clifford will work with the hydrographic consultant to complete the survey of the South Lawn and report back to the CLC.
  • Mr. Clifford will notify the South Lawn committee and the CLC at large of the proposed workshop, and a time and place will be determined and announced.

FUTURE MEETING TOPICS

  • Campus Tour to include
  • Edmond J. Safra Lodge (Family Inn)
  • Commercial Vehicle Inspection Facility

CLC Members Present
Amy Blackburn, OCL, OD, NIH
Marian Bradford, Camelot Mews Citizens Association
John Burklow, Acting Director, OCL, OD, NIH
Anthony Clifford, ORF, OD, NIH
Lesley Hildebrand, Huntington Terrace Citizens Association
Nancy Hoos, Sonoma Citizens Association
Deborah Michaels, Glenbrook Village Homeowners Association
Ginny Miller, CLC Co-Chair, Wyngate Citizens Association
George Oberlander, Huntington Parkway Citizens Association
Lucy Ozarin, M.D., Whitehall Condominium Association
Sharon Robinson, OCL, OD, NIH
Stephen Sawicki, Edgewood Glenwood Citizens Association
Ralph Schofer, Maplewood Citizens Association
Randy Schools, Recreation and Welfare Association, NIH
Deborah Snead, Bethesda-Chevy Chase Regional Services Center
Ronald Wilson, ORFDO, NIH
J. Paul Van Nevel, NIH Alumni Association

Guests
Lonnie Darr, Geographic Information Systems
Kenny Floyd, ORF, OD, NIH
Anna Franz, ORF, OD, NIH
Tom Hayden, ORS, OD, NIH
Chief Alvin Hinton, Security, ORS, OD, NIH
Joan Kleinman, Congressman Van Hollen's Office
Robert McDonald, ORF, OD, NIH
Brad Moss, ORS, OD, NIH
Shelly Pollard, OCPL
Terry Taylor, Palladian Partners, Inc.
Chris Williams, Gazette News

back to top