United States Department of Agriculture
Natural Resources Conservation Service
Minnesota Go to Accessibility Information
Skip to Page Content





Snake River Watershed Project

The city of Warren has endured numerous floods throughout its history. In 1996 and 1997 alone the city suffered three major floods that caused 12.7 million dollars in damage. In 1997 the USDA Natural Resources Conservation Service (NRCS) was asked by the local sponsors, the city of Warren and Middle River-Snake River Watershed District, to resume planning on the Snake River Watershed Project. Planning on this project was started in the 1980’s but had been terminated at the sponsor’s request. In November 1999, the planning for this project was completed.

Main Street of Warren, Spring 1996

Main Street of Warren, Spring 1996
 


When complete, the Snake River Watershed Project will provide 100-year frequency flood protection for the city of Warren. The project consists of two main components, an excavated floodway around the city of Warren, and floodwater storage impoundment located upstream of the city. The floodwater storage impoundment was needed to ensure that flood levels would not be increased downstream of Warren or upstream of the floodway diversion structure.

Map Showing Floodway


The floodway safely carries flood flows around Warren

 

Map Showing Storage Reservoir

The floodway Storage Reservoir in Comstock Township will reduce peak flows downstream

 

Engineering and funding for the flood control components are being provided by the USDA-NRCS under the Public Law 566 Watershed Protection and Flood Prevention Program. The local sponsors are responsible for purchasing right-of-way, installing road crossings, and contracting for construction. The Middle River-Snake River Watershed District is also responsible for future operation and maintenance of the project.

Ground Breaking Ceremony

 
 
 
 
 
 
 
 
 
 

 

 
The Snake River groundbreaking ceremony for the watershed project was held on October 26, 2001.


Phase I of the project consisted of the lower mile of the floodway and outlet chute was awarded to KGM Contracting of Angora, Minnesota for the price of $562,000. This phase of the project was completed in August 2002.

Phase One Seed and Mulch

 
 
 
 
 
 
 
 
 
 
 
 
The Phase I Floodway is seeded and mulched



Rock for Floodway Outlet Chute

 
 
 
 
 
 
 
 
 
 
 
Rock is placed for the floodway outlet chute


Phase II of the project is the Off Channel Floodwater Storage Reservoir. In May 2002, the construction contract for this phase was awarded to Riley Brothers Construction of Morris, MN for a price of $4,362,000.

Phase Two

Out on the Phase II site are Bruce Julan, NRCS, Washington D.C.,
Ron Adrian, Middle River-Snake River Watershed District, and
Richard Nelson, Mayor, city of Warren
The off-channel storage structure portion of the project has been completed and was in operation in time for the spring thaw in 2005. The majority of the work was completed in the fall of 2004. The off channel storage area has a foot print of about 550 acres with a flood pool storage capability of about 6800 acre-feet. The earth embankment is close to 4.5 miles long with the highest fill section being approximately 22.5 feet high. More than 1.3 million cubic yards of earth fill was required to construct the embankment. Spring 2005 saw about 1400 ac-ft of water stored in the OCS. During the month of June the area saw heavy rains which brought the pool area back up around 1400 ac-ft.
 


Phase Two

Outlet Structure – Off Channel Storage

Phase Two
Inlet Structure to Off Channel Storage Area
Phase III of the Project includes the Snake River Diversion Structure and upper 3 miles of floodway. The diversion structure will allow low flows to continue through the city of Warren, but will divert high flows into the floodway. The diversion structure includes a fish passage structure to allow fish passage for a wide range of flow conditions. Phase III has been closely coordinated with the construction of three highway and two railroad crossings which has been constructed concurrently.

The diversion and floodway portion of the project is currently under construction.  One mile of floodway was constructed in 2001 and 2002 and another mile was constructed in 2003.  The final 2.2 miles was finished the summer of 2005.  The total floodway length was about 4.2 miles and the total excavated quantity was over 900,000 cubic yards.

 

Phase Three
Floodway excavation using the GPS equipped dozer

 

Phase Three
Floodway seedbed preparation after excavation

 

Phase Three
Installation of permanent turf reinforcement mat

 

Phase Three
Floodway after seeding and mulching
The last placement of concrete for the diversion structure was on November 30th 2005.  The diversion structure is 182 feet long, 26 feet high, and has a 10 foot deep cutoff wall.  It is also constructed to allow fish passage through the structure.  A total of 1,236 cubic yards of concrete was placed and over 400,000 pounds of steel reinforcement was used to construct the diversion.

The remaining work consists of backfill for the concrete structure as well as placing some riprap for protection upstream and downstream of the structure.  There is also some earthwork to be finished along with the final seeding and mulching.  It is expected that all work on the floodway and diversion portion of the project will be completed the summer of 2006.

 

Phase Three
Installation of reinforcing steel in cutoff trench

 

Phase Three
Preparation for placement of the main slab

 

Phase Three
The first 15 feet of the wall is in place

 

Phase Three
Forming the final wall placement.

 

Phase IV of the project will include the construction of wetlands and tree plantings required as mitigation for those lost during the construction of the project.

                                                                                             Last Modified 12/21/2005