Nuclear Power Deployment Scorecard
Powering Future Decades
Current Scorecard - January 7, 2009
What's New
- Westinghouse and Shaw Group signed an EPC contract with Progress Energy January 5, 2009 for two AP1000 units in Levy County, Florida.
- NRC docketed five COL applications in December:
- PPL, for an EPR at Bell Bend in Berwick, Pennsylvania, on December 19, 2008.
- Constellation, for an EPR at Nine Mile Point in Oswego, New York, on December 12.
- Ameren UE, for an EPR at Callaway near Fulton, Missouri, on December 12.
- Entergy, for an ESBWR at River Bend in West Feliciana Parish, Louisiana, on Dec. 4.
- Luminant for two APWRs at Comanche Peak near Glen Rose, Texas, on December 2.
- Luminant provided notice of intent to prepare an EIS and conduct environmental scoping for its Comanche Peak COLA on December 18.
- On December 17, Électricité de France agreed to acquire half of the nuclear generation business of Constellation Energy for $4.5 billion.
- Westinghouse awarded Chicago Bridge & Iron a second contract for $150 million to build two AP1000 containment vessels on December 17.
- NRC published notice for hearing to intervene in the Progress COL application at Levy County December 8.
- GE-Hitachi notified NRC of intentions to renew the ABWR Design Certification on December 5. The rule is set to expire June 11, 2012.
- DTE provided notice of intent to prepare an EIS and conduct environmental scoping for its Fermi COLA on December 3.
Quick Statistics
- Early Site Permits issued—3
- Permits under review—1
- COL applications submitted—17
No. reactors submitted—26
- COL applications docketed—17
No. reactors docketed—26
- Total expected license applications—23
Expected number of reactors—34
- Certified reactor designs—2
- Reactor designs under review—4
- Announced plant locations—21
- Companies applying for COL—20
|
|
Number of Planned Reactors (34)
Vendor Technology Under Consideration
General Electric
- Advanced Boiling Water Reactor (ABWR) – 1,356 MWe (certified 10CFR52 App A)
- Economic Simplified Boiling Water Reactor (ESBWR) – 1,560 MWe
Westinghouse
- Advanced Passive Pressurized Water Reactor (AP1000) – Twin units 1,117 MWe each (certified 10CFR52 App D)
AREVA
- United States Evolutionary Pressurized Water Reactor (US EPR) – 1,600 MWe
Mitsubishi Heavy Industry
- United States Advanced Pressurized Water Reactor (US APWR) – 1,700 MWe
|
|
Status of License Applications (23)
Announced Nuclear Locations
- Amarillo (TX)—Amarillo Power
- Bell Bend (PA)—PPL (formerly Susquehanna)
- Bellefonte (AL)—Tennessee Valley Authority
- Elmore County (ID)—Alternate Energy Holdings
- Callaway (MO)—AmerenUE
- Calvert Cliffs (MD)—UniStar
- Clinton (IL)—Exelon
- Comanche Peak (TX)—Luminant
- Fermi (MI)—DTE Energy
- Grand Gulf (MS)—Entergy
- Shearon Harris (NC)—Progress Energy
- Levy County (FL)—Progress Energy
- Nine Mile Point (NY)—UniStar
- North Anna (VA)—Dominion Energy
- River Bend (LA)—Entergy
- South Texas Project (TX)—STP Nuclear
- V.C. Summer (SC)—SCE&G
- Turkey Point (FL)—Florida Power & Light
- Victoria County (TX)—Exelon Generation
- Vogtle (GA)—Southern Nuclear
- William States Lee III (SC)—Duke Energy
|
|
|
|
|
Nuclear Scorecard |
|
|
|
|
|
Nuclear Power Deployment Scorecard |
|
|
Early Site Permit (ESP) > |
|
- Three site permits issued by NRC (Clinton, Grand Gulf, North Anna)
- One site permit application under NRC review (Vogtle)
- Submission of three other ESP applications expected in 2010-2012
|
|
Combined Construction and Operating License (COL) > |
|
License Applications Submitted to NRC
- Seventeen COLAs docketed (Bell Bend, Bellefonte, Callaway, Calvert Cliffs, Comanche Peak, Fermi, Grand Gulf, Harris, Lee, Levy Co., Nine Mile, North Anna, River Bend, STP, Summer, Victoria, Vogtle)
- No outstanding COL applications pending acceptance
- Submission of 6 additional COLs expected in 2009-2010; none for the remainder of 2008
|
|
|
Status of Reference R-COLs
- All five R-COLs have been submitted and are undergoing Phase 1 of the Safety Review (Bellefonte, Calvert Cliffs, Comanche Peak North Anna, South Texas Project)
|
|
Reactor Design Certification (DC) > |
|
- Two advanced reactor designs certified by NRC (ABWR and AP1000)
- Four reactor designs undergoing NRC review (ESBWR, US-EPR, AP1000 amend., and US-APWR
|
|
New Nuclear Plant Orders > |
|
Long-Lead Equipment Orders
- Nine utilities have ordered large, long-lead nuclear component forgings from three reactor vendors
- Four steel containment shells and 24 reactor coolant pumps have been ordered for AP1000 units
- Two domestic large component facilities being built
- Japan Steel Works is the only manufacturer of ultra-large forgings; worldwide-capacity limited
|
|
|
Engineering, Procurement, and Construction Contracts (EPC)
- Four EPC contracts initiated (Vogtle, V.C. Summer, STP, and Progress)
- Plant engineering is in progress; completion required to start construction
|
|
New Nuclear Plant Construction, Operation, & Deferral > |
|
- No utility has committed to constructing a new advanced reactor
- TVA has resumed construction of Watts Bar Unit 2 with completion scheduled in 2013
|
|
Federal Financial Incentives > |
|
Standby Support (Risk Insurance)
- Final 10 CFR Part 950 Rule issued August 11, 2006
- Two Notices of Intent to Request a Conditional Agreement and one formal request received by DOE
|
|
|
Production Tax Credits
- Internal Revenue Bulletin 2006-18 published May 2006
- IRS considering revised guidance
|
|
|
Nuclear Power Loan Guarantees
- The Department is authorized, before September 30, 2009, to guarantee $18.5 billion in loans for nuclear power projects.
- Fifteen power companies have submitted applications by the Part II deadline of December 19, 2008, requesting a total of $93 billion in loans to be guaranteed. The applications cover 10 sites with a total of 16 reactors, capable of providing 22 GW in generating capacity.
|
|
|
Scorecard Legend |
|
|
Implementation proceeding according to plan and schedule |
|
Progress being made; however, issues or uncertainties exist that could impede progress |
|
Unlikely to realize objectives absent significant management attention |
|
No dates or end state established |
|
Indicates change in status or progress since last evaluation |
|
Regulatory Demonstration completed. No further government assistance is warranted. |
|