September 3, 1998
COMMISSION VOTING RECORD
DECISION ITEM: | SECY-98-188 |
TITLE: | A PROPOSED SIMPLIFICATION OF THE RULEMAKING PROCESS FOR CERTIFICATE OF COMPLIANCE RULEMAKINGS |
The Commission (with all Commissioners agreeing) approved the subject paper as recorded in the Staff Requirements Memorandum (SRM) of September 3, 1998.
This Record contains a summary of voting on this matter together with the individual vote sheets, views and comments of the Commissioners, and the SRM of September 3, 1998.
___________________________
John C. Hoyle |
Attachments: | 1. Voting Summary 2. Commissioner Vote Sheets 3. Final SRM |
cc: | Chairman Jackson Commissioner Diaz Commissioner McGaffigan OGC EDO PDR DCS |
VOTING SUMMARY - SECY-98-188
RECORDED VOTES
APRVD | DISAPRVD | ABSTAIN | NOT PARTICIP |
COMMENTS | DATE | |
---|---|---|---|---|---|---|
CHRM. JACKSON | X | X | 8/17/98 | |||
COMR. DIAZ | X | X | 8/12/98 | |||
COMR. McGAFFIGAN | X | X | 8/7/98 |
COMMENT RESOLUTION
In their vote sheets, all Commissioners approved the staff's recommendation and some provided additional comments. Subsequently, the comments of the Commission were incorporated into the guidance to staff as reflected in the SRM issued on September 3,1998.