Bureau of Reclamation Banner

CHANDLER POWERPLANT



Chandler Powerplant

Chandler Powerplant


Plant Contact: Gerald Kelso , Area Manager
Upper Columbia Area Office
Telephone Numbers: Phone: (509) 588-3317
Fax: (509) 454-5611
E-Mail Address: gkelso@pn.usbr.gov
Reclamation Region: Pacific Northwest
NERC Region: Western Electricity Coordinating Council, Northwest Power Pool Area
PMA Service Area: Bonneville Power Administration
Project Authorization: The Congress authorized the Yakima Project, Kennewick Division, on June 12, 1948, under Public Law 629, 80th Congress (62 Stat. 382).
Project Purposes:

The Yakima Project provides irrigation water for a comparatively narrow strip of fertile land that extends for 175 miles on both sides of the Yakima River in south-central Washington. The irrigable lands presently being served total about 465,000 acres.

The Kennewick Division is a combined irrigation and power development. It includes the 12,000-kilowatt Chandler Powerplant and 19,171 acres of irrigable land.

Plant Facts: The Chandler Powerplant includes two 6.0 megawatt, 4160 volt hydropower generators, and two 2,600 horsepower pumps which operate from a 10.6 mile canal, diverting up to 1,500 cubic feet per second of water from the Prosser Diversion Dam.
Plant Purpose: The powerplant has not historically supplied project power for irrigation pumping, but it is planned to install electric pumps to replace the existing hydraulically powered pumps at the powerplant.
Plant History: The powerplant was constructed in 1956 as part of the Yakima Project.
Present Activities: Normal operations
Future Planned Activities: None
Special Issues: None
River: Chandler Power Canal
Plant Type: Conventional
Powerhouse Type: Above Ground
Turbine Type: Francis
Original Nameplate Capacity: 12,000 kW
Installed Capacity: 12,000 kW
Year of Initial Operation: 1956
Age: 49 years
Net Generation:
(FY 2005)
31,485,240 kWh
Rated Head: 118 feet
Plant Factor:
(FY 2005)
30.35 percent
Remotely Operated: No
Production Mode: Intermediate


Click here for graphs and charts of Chandler Powerplant performance.

Click here for information on the Yakima Project.


Revised April 20, 2006             Hydropower Site Map             Help