October 23, 2003
MEMORANDUM TO: |
William D. Travers
Executive Director for Operations |
FROM: |
Annette L. Vietti-Cook, Secretary /RA by Andrew L. Bates
Acting For/ |
SUBJECT: |
STAFF REQUIREMENTS - BRIEFING ON DECOMMISSIONING ACTIVITIES AND
STATUS, 9:30 A.M., TUESDAY, OCTOBER 7, 2003, COMMISSIONERS' CONFERENCE
ROOM, ONE WHITE FLINT NORTH, ROCKVILLE, MARYLAND (OPEN TO PUBLIC ATTENDANCE) |
The Commission was briefed by the NRC staff on the current status of
NRC's decommissioning program. In addition, representatives from two nuclear
power plants which are undergoing decommissioning and an independent inspector
briefed the Commission on their experiences with the decommissioning process.
Future annual program briefings should include participation by public
stakeholders whenever possible.
The NRC staff should:
-
Revise the attachment to the current decommissioning report to be
a stand alone document. For sites listed in the document, provide
a consistent format for presenting the data (particularly for the
current appendixes 5 and 6). Provide an informational copy of the
revised document to the Commission and make it publicly available.
|
(EDO) |
(SECY Suspense: 2/1/04) |
-
Provide the Commission with an integrated paper that provides recommended
changes to the decommissioning program and the associated annual report.
This paper should address, among other issues: (A) expansion of the
focus and the level of detail in the annual decommissioning program
report with the intent of developing it as a primary communication
document (e.g., NUREG with updates on all complex decommissioning
sites), (B) other recommended changes to the format of the report
(e.g., use of NRC web-site information and inclusion of information
on all complex decommissioning sites), and (C) recommended elimination
of the Site Decommissioning Management Plan designation.
|
(EDO) |
(SECY Suspense: 2/1/04) |
-
Provide a summary of the extent of regulatory exemptions that have
been granted to facilities in SAFSTOR.
-
Provide information on decommissioning criteria used in France and
the development of regulations there similar to NRC's License Termination
Rule (LTR). This information can be provided in the trip report following
the French Bilateral and Convention.