Home > Electronic Reading Room > Document Collections > Commission Documents > Staff
Requirements Memoranda (SRM) > 2003
> SECY-03-0114
July 17, 2003
MEMORANDUM TO: |
William D. Travers
Executive Director for Operations |
FROM: |
Annette L. Vietti-Cook, Secretary /RA/ |
SUBJECT: |
STAFF REQUIREMENTS - SECY-03-0114 - FINAL RULE, 10 CFR PART 140,
"FINANCIAL PROTECTION REQUIREMENTS AND INDEMNITY AGREEMENTS" |
This is to advise you that the Commission has not objected to staff issuance
of the final rule subject to the changes noted in the attachment.
Attachment: Changes to the Final Rule in SECY-03-0114
cc: |
Chairman Diaz
Commissioner McGaffigan
Commissioner Merrifield
OGC
CFO
OCA
OIG
OPA
Office Directors, Regions, ACRS, ACNW, ASLBP (via E-Mail)
PDR |
Attachment
Changes to the Final Rule in SECY-03-0114
Changes to Federal Register Notice
-
On page 1, Summary paragraph, revise line 6 to read ' ... increased
to $95.8 94.5 million per ....' Revise
line 8 to read ' ... change of 14.2 12.59
percent in the ... (CPI) from December 1997 September
1998 through ....'
-
On page 2, paragraph 1, revise line 7 to read ' ... $300 million
(which, as the statute requires, reflects the maximum commercial
insurance available effective January ....' Revise line 9 to
read ' ... plan. These limits on secondary financial
protection are currently ....'
-
On page 3, revise line 3 from the top to read ' ... change (since
December 1997 September 1998) in the CPI
....' Revise line 5 from the top to read ' ... December 1997
September 1998 through March 2003 is 14.2
12.59 percent.' Delete the sentence in lines 5 and
6 (This number is derived ... CPI index.) Revise line 8 to read '
... will increase to $95.8 94.5 million
per reactor ....'
-
On page 3, 1st full paragraph, revise line 4 to read '
... $95.8 94.5 million per reactor ....'
-
On page 6, paragraph (4), revise line 9 to read ' ... no more than
$95,800,000 94,500,000 with respect to
any ....'
Approved for Publication
- In paragraph 2, revise line 4 to read ' ... 1 year), to $95.8
94.5 million per reactor ....' Revise line 6 to read
' ... change (since December 1997 August 1998)
in the ....'
Notice of Final Rule Signed by the EDO
- In paragraph 1, revise line 3 to read ' ... incident to $95.8
94.5 million per reactor ....' Revise line 4 to read
' ... change (since December 1997 August 1998)
in the ....'
|