February 24, 1999
COMMISSION VOTING RECORD
DECISION ITEM: | SECY-98-144 |
TITLE: | WHITE PAPER ON RISK-INFORMED, PERFORMANCE-BASED REGULATION |
The Commission (with all Commissioners agreeing) approved the subject paper. Commissioner McGaffigan also disapproved in part. The results are recorded in the Staff Requirements Memorandum (SRM) of February 24, 1999.
This Record contains a summary of voting on this matter together with the individual vote sheets, views and comments of the Commissioners, and the SRM of February 24, 1999.
___________________________ Annette L. Vietti-Cook Secretary of the Commission |
Attachments: | 1. Voting Summary 2. Commissioner Vote Sheets 3. Final SRM |
cc: | Chairman Jackson Commissioner Dicus Commissioner Diaz Commissioner McGaffigan Commissioner Merrifield OGC EDO PDR DCS |
VOTING SUMMARY - SECY-98-144
RECORDED VOTES
APRVD | DISAPRVD | ABSTAIN | NOT PARTICIP |
COMMENTS | DATE | |
---|---|---|---|---|---|---|
CHRM. JACKSON | X | X | 6/30/98 | |||
COMR. DICUS | X | X | 11/9/98 | |||
COMR. DIAZ | X | X | 8/12/98 | |||
COMR. McGAFFIGAN | X | X | X | 11/13/98 | ||
COMR. MERRIFIELD | X | 11/2/98 |
COMMENT RESOLUTION
In their vote sheets, Chairman Jackson and Commissioners Dicus, Diaz, and Merrifield approved the staff's recommendation and some provided additional comments. Commissioner McGaffigan approved in part and disapproved in part. Subsequently, the comments of the Commission were incorporated into the guidance to staff as reflected in the SRM issued on February 24, 1999.
I approve the issuance of SECY-98-144, "White Paper on Risk-Informed, Performance-Based Regulation" provided the phrase "however, this does . . . limits." in paragraph #5 on page 6 is deleted.
Commissioner Diaz's comments on SECY-98-144
I approve issuance of the "White Paper on Risk Informed and Performance-Based Regulation," with edits (attached).
Commissioner McGaffigan's Comments on SECY-98-144
It is important that the staff, the industry and the public have a common understanding of the terms "risk-informed," "risk-based," and "performance-based." However, I found several sections in the draft white paper that needed strengthening, editing and/or deletion. These are shown on the attached redlined version of the paper.
I added to the paper some important concepts from the September 30, 1998 letter from the ACRS to the Chairman titled "Impact of Probabilistic Risk Assessment Results and Insights on the Regulatory System." These concepts included discussions on the principal strengths and weaknesses of deterministic and risk-informed approaches to regulatory activities, the complementary relation between defense-in-depth and PRA, and the transition that will be necessary as the NRC adopts more risk-informed approaches.
Also, I added some words from the NEI 96-04,Industry White Paper titled "Enhancing Nuclear Plant Safety and Reliability Through Risk-Based and Performance-Based Regulation," regarding bases for objective performance criteria that would be established in performance-based regulatory approaches.
To add more clarity, I made several editorial changes regarding the use of some terms that were in some sections used inappropriately. In particular, these terms were "traditional" and "deterministic," and "analysis" and "approach."
I attempted to revise two paragraphs in section 6 on performance-based inspection and performance-based assessments. Both of these paragraphs seemed out of place in a paper devoted mostly to defining terms and concepts for use in rulemaking or licencing activities. I found that the paragraph on performance-based inspection could lead to confusion regarding the inspection of prescriptive regulations. Inspectors should not have to judge the importance of the prescriptive process(es) mandated by a regulation. If the prescriptive process or methodology in a regulation is not important, then that regulation should be a candidate for a performance-based rule change. The NRC's current licensee assessment processes are already performance-based. Therefore, the paragraph on performance-based assessments is not needed. For these reasons, I have deleted the two paragraphs.
For the reasons stated above, I vote to both approve and disapprove this paper as described in the attached redlined version.
Risk-Informed, Performance-Based Regulation
The NRC has established its regulatory requirements, in both reactor and materials applications, to ensure that "no undue risk to public health and safety" results from licensed uses of Atomic Energy Act (AEA) materials and facilities. The objective of these requirements has always been to assure that the probabilities of accidents with the potential for adversely affecting public health and safety are low. For reactors, these probabilities were not quantified in a systematic way until 1975 when the Reactor Safety Study (WASH-1400) was published. For non-reactor activities, such quantification is still evolving. Consequently, many most of NRC's regulations were developed without the benefit of quantitative estimates of risk. The perceived benefits of the deterministic and prescriptive regulatory requirements was were based mostly on experience, testing programs and expert judgment, considering factors such as engineering margins and the principle of defense-in-depth. The principal strengths of the traditional regulatory system are its caution ("what if we are wrong") and the resulting development of the principle of defense-in-depth as well as its large experience base. The principal weakness is its inability to quantify the risk significance of structures, systems, components and operator actions.
There have been significant advances in and experience with risk assessment methodology since 1975. Thus, the Commission is advocating certain changes to the development and implementation of its regulations through the use of risk-informed , and ultimately performance-based approaches. The Probabilistic Risk Assessment (PRA) Policy Statement (60 FR 42622, August 16, 1995) formalized the Commission's commitment to risk-informed regulation through the expanded use of PRA. The PRA Policy Statement states, in part, "The use of PRA technology should be increased in all regulatory matters to the extent supported by the state of the art in PRA methods and data, and in a manner that complements the NRC's deterministic approach and supports the NRC's traditional defense-in-depth philosophy." The principal strengths of PRA are the quantification of risk and the identification and ranking of the major accident sequences and risk-significant structures, systems, components and certain operator actions. The principal weakness is incompleteness, i.e., the inability to identify all potential threats to the system and to develop adequate models for some identified threats.
The principles of defense-in-depth and PRA can complement each other well. When the uncertainties in the PRA are too large for regulatory decision-making (especially due to incompleteness), the principle of defense-in-depth can be invoked to deal with these uncertainties.
To understand and apply the commitment expressed in the PRA Policy Statement, it is important that the NRC, the regulated community, and the public at large have a common understanding of the terms and concepts involved; an awareness of how these concepts (in both reactor and materials arenas) are to be applied to NRC rulemaking, licensing, inspection, assessment, enforcement, and other decision-making; and an appreciation of the transitional period in which the agency and industry currently operate.
The transition to a risk-informed regulatory framework is expected to be incremental. Many of the present regulations are based on deterministic and prescriptive requirements that cannot be quickly replaced. Therefore, the current requirements will have to be maintained while risk-informed and/or performance-based regulations are being developed and implemented. Furthermore, it is expected that a number of licensees will, for a variety of reasons, be unwilling to embrace a new regulatory system. Therefore the NRC and industry should be prepared to accommodate a two tier system, i.e., a modified version of the current regulatory process and a risk-informed system.
1. | Risk and Risk Assessment: This paper defines risk in terms that can be applied to the entire range of activities involving NRC licensed use of AEA materials. The risk definition takes the view that when one asks, "What is the risk?" one is really asking three questions: "What can go wrong?" "How likely is it?" and "What are the consequences?" These three questions can be referred to as the "risk triplet." The traditional definition of risk, that is, probability times consequences, is fully embraced by the "triplet" definition of risk. |
The first question, "What can go wrong?" is usually answered in the form of a "scenario" (a combination of events and/or conditions that could occur) or a set of scenarios. | |
The second question, "How likely is it?" can be answered in terms of the available evidence and the processing of that evidence to quantify the probability and the uncertainties involved. In some situations, data may exist on the frequency of a particular type of occurrence or failure mode (e.g., accidental overexposures). In other situations, there may be little or no data (e.g., core damage in a reactor) and a predictive approach for analyzing probability and uncertainty will be required. | |
The third question, "What are the consequences?" can be answered for each scenario by assessing the probable range of outcomes (e.g., dose to the public) given the uncertainties. The outcomes or consequences are the "end states" of the analyses. The choice of consequence measures can be whatever seems appropriate for reasonable decision-making in a particular regulated activity and could involve combinations of end states. | |
A risk assessment is a systematic method for addressing the risk triplet as it relates to the performance of a particular system (which may include a human component) to understand likely outcomes, sensitivities, areas of importance, system interactions and areas of uncertainty. From this assessment the important scenarios can be identified. | |
2. | |
Since risk assessment methods were first used to gain a better understanding of the risk associated with some of the activities and facilities that NRC regulates, substantial event data and increased sophistication and experience in the use of certain risk assessment methods (e.g., Probabilistic Risk Assessment (PRA), Integrated Safety Assessment (ISA), and Performance Assessment (PA)) has been acquired. Accordingly, there is now the opportunity to enhance the traditional approach by more explicitly addressing risk and incorporating the insights thus gained. | |
While the traditional deterministic approach to regulation has been successful in ensuring no undue risk to public health and safety in the use of nuclear materials, opportunities for improvement exist. Given the broad spectrum of equipment and activities covered, the regulations can be strengthened and resources allocated to ensure that they are focused on the most risk-significant equipment and activities, and to ensure a consistent and coherent framework for regulatory decision-making. The "risk-informed" and "risk-informed, performance-based" approaches to regulation described below, if properly applied, would provide such a framework. | |
3. | "Risk Insights" |
Risk insights have already been incorporated successfully into numerous regulatory activities, and have proven to be a valuable complement to traditional deterministic approaches. Given the current maturity of some risk assessment methodologies and the current body of event data, risk insights can be incorporated more explicitly into the regulatory process in a manner that will improve both the efficiency and effectiveness of current regulatory requirements. | |
Text Moved Here: 1 | |
"Risk-Based": A "risk-based" approach to regulatory decision-making is one in which a safety decision is solely based on the numerical results of a risk assessment. This places heavier reliance on risk assessment results than |
|
End Of Moved Text | |
5. | "Risk-Informed" Approach: A "risk-informed" approach to regulatory decision-making represents a philosophy whereby risk insights are considered together with other factors to establish requirements that better focus licensee and regulatory attention on design and operational issues commensurate with their importance to public health and safety. A "risk-informed" approach enhances the |
Risk-Informed and Defense-in-Depth: The concept of defense-in-depth(4) has always been and will continue to be a fundamental tenet of regulatory practice in the nuclear field. Risk insights can make the elements of defense-in-depth more clear by quantifying them to the extent practicable. Although the uncertainties associated with the importance of some elements of defense may be substantial, the fact that these elements and uncertainties have been quantified can aid in determining how much defense makes regulatory sense. Decisions on the adequacy of or the necessity for elements of defense should reflect risk insights gained through identification of the individual performance of each defense system in relation to overall performance. | |
Text Was Moved From Here: 1 | |
"Performance-Based": A regulation can be either prescriptive or performance-based. A prescriptive requirement specifies particular features, actions, or programmatic elements to be included in the design or process, as the means for achieving a desired objective. A performance-based requirement relies upon measurable (or calculable) outcomes (i.e., performance results) to be met, but provides more flexibility to the licensee as to the means of meeting those outcomes. A performance-based regulatory approach is one that establishes performance and results as the primary basis for regulatory decision-making, and incorporates the following attributes: (1) measurable (or calculable) parameters (i.e., direct measurement of the physical parameter of interest or of related parameters that can be used to calculate the parameter of interest) exist to monitor |
|
A performance-based approach can be implemented without the use of risk insights. Such an approach would require that objective performance criteria be based on deterministic safety analysis and performance history. This approach would still provide flexibility to the licensee in determining how to meet the performance criteria. Establishing objective performance criteria for performance monitoring may not be feasible for some applications and, in such cases, a performance-based approach would not be feasible. | |
As applied to licensee assessment, a performance-based approach focuses on a licensee's actual performance results (i.e., desired outcomes), rather than on products (i.e., outputs). In the broadest sense, the desired outcome of a performance-based approach to regulatory oversight will be to focus more attention and NRC resources on those licensees whose performance is declining or less than satisfactory. | |
7. | "Risk-Informed, Performance-Based": A risk-informed, performance-based approach to regulatory decision-making combines the "risk-informed" and "performance-based" elements discussed in Items 3 and 6, above, and applies these concepts to NRC rulemaking, licensing, inspection, assessment, enforcement, and other decision-making. Stated succinctly, risk-informed, performance-based regulation is an approach in which risk insights, engineering analysis and judgment, and performance history are used, to (1) focus attention on the most important activities, (2) establish objective criteria |
The definitions and concepts in this paper have proven suitable for application to nuclear power plants and certain non-reactor activities (e.g., PA of geologic repositories). While different in detail, these activities are similar in terms of system complexity and the application of probabilistic methods to the determination of safety. In simpler situations, the concepts and definitions should prove equally suitable provided that NRC adopts a flexible framework for the implementation of risk-informed, and ultimately performance-based regulation across the full spectrum of the materials, processes, and facilities regulated by the NRC.
1. CDF is the frequency of the combinations of initiating events, hardware failures, and human errors leading to core uncovery with reflooding of the core not imminent.
2. LERF is the frequency of those accidents leading to significant, unmitigated releases from containment in a time-frame prior to effective evacuation of the close-in population such that there is a potential for early health effects.
3. Risk curves are estimates of the probability that a given consequence will be exceeded.
4. Defense-in-depth is an element of the NRC's Safety Philosophy that employs successive compensatory measures to prevent accidents or mitigate damage if a malfunction or accident occurs at a nuclear facility. The defense-in-depth philosophy ensures that safety will not be wholly dependent on any single element of the design, construction, maintenance, or operation of a nuclear facility. The net effect of incorporating defense-in-depth into design, construction, maintenance, and operation is that the facility or system in question tends to be more tolerant of failures and external challenges.