December 3, 2003
COMMISSION VOTING RECORD
DECISION ITEM: |
SECY-03-0200 |
TITLE: |
RENEWAL OF FULL-POWER OPERATING LICENSES FOR MCGUIRE NUCLEAR STATION,
UNITS 1 AND 2, AND CATAWBA NUCLEAR STATION, UNITS 1 AND 2 |
The Commission (with all Commissioners agreeing) approved the subject
paper as recorded in the Staff Requirements Memorandum (SRM) of December
3, 2003.
This Record contains a summary of voting on this matter together with
the individual vote sheets, views and comments of the Commission.
|
___________________________
Annette L. Vietti-Cook
Secretary of the Commission |
cc: |
Chairman Diaz
Commissioner McGaffigan
Commissioner Merrifield
OGC
EDO
PDR |
VOTING SUMMARY - SECY-03-0200
RECORDED VOTES
|
APRVD |
DISAPRVD |
ABSTAIN |
NOT
PARTICIP |
COMMENTS |
DATE |
CHRM. DIAZ |
X |
|
|
|
X |
12/1/03 |
COMR. McGAFFIGAN |
X |
|
|
|
|
12/2/03 |
COMR. MERRIFIELD |
X |
|
|
|
X |
12/3/03 |
COMMENT RESOLUTION
In their vote sheets, all Commissioners approved the staff's recommendation
and some provided additional comments. Subsequently, the comments of the
Commission were incorporated into the guidance to staff as reflected in
the SRM issued on December 3, 2003.
Commissioner Comments on
SECY-03-0200
Chairman Diaz
I approve the staff's recommendation that the Commission authorize the
Director of the Office of Nuclear Reactor Regulation to renew the operating
licenses for the McGuire Nuclear Station Units 1 and 2 and the Catawba
Nuclear Station Units 1 and 2, after making the appropriate findings on
safety, and environmental matters.
Commissioner Merrifield
I approve the staff's recommendation.
|