Home > Electronic Reading Room > Document Collections > Commission Documents > Commission
Papers (SECY) > 2001
> SECY-01-0218
POLICY ISSUE
(Information)
SECY-01-0218
December 5, 2001
FOR: |
The Commissioners |
FROM: |
William D. Travers
Executive Director for Operations /RA/ |
SUBJECT: |
UPDATE OF THE RISK-INFORMED REGULATION IMPLEMENTATION PLAN |
PURPOSE:
To give the Commission an updated and revised version of the Risk-Informed
Regulation Implementation Plan (RIRIP ),
and to inform the Commission of the staff's plans to improve the process
for planning the various activities associated with risk-informed regulation.
SUMMARY
The RIRIP discusses the Agency's efforts to risk-inform its regulatory
activities and specifically describes each of the activities identified
as supporting the goals and objectives of the Agency's Strategic Plan
and the Probabilistic Risk Analysis Policy Statement.
The RIRIP is organized into two parts: Part 1 provides a general discussion
of the document's relationship to the PRA Policy Statement and the Strategic
Plan. It also discusses elements for consideration in the process of risk-informing
and provides guidance for selecting appropriate "candidates" for risk-informing.
Part 2 describes each of the staff's ongoing risk-informed regulation
activities, which are organized by reactor arena and waste/materials safety
arenas. The arena chapters in this issue of the RIRIP have been modified
in response to the Commission's direction. Specific modifications are
discussed later in this paper. Additionally, the plan provides each activity's
relative priority rating as determined by the respective offices.
The Agency's accomplishments in risk-informing its regulatory activities
over the past year are described in Attachment
1 .
Key risk-informing activities to be conducted at the agency over the next
six months are described in the paragraphs below by arena.
Reactor Safety Arena:
-
Option 2 - Draft rule language for Risk-Informing Special Treatment
Requirements is expected to be made available for public comment early
in December. The staff will meet with the Advisory Committee on Reactor
Safeguards in December to discuss the draft rule language and other
related matters. Pilot plant activities continue with staff observation
of the categorization process at Wolf Creek in October and plans for
observation at Surry in January, 2002. The staff is continuing to
work on the statement of considerations, regulatory analysis and environmental
assessment to support this proposed rule. The proposed rule will be
submitted to the Commission in April 2002.
-
Option 3 - On November 14, 2001, a draft rule language package for
combustible gas control was made available for public review and comment
on the NRC rulemaking web site. The comment period is expected to
run through the end of December 2001. The proposed rule will be submitted
to the Commission by January 31, 2002.
-
The staff continues to work on numerous risk-informed technical specification
initiatives. The safety evaluations for Initiative 1, Technical Specification
Actions End State Modifications, and Initiative 3, Modification of
Mode Restraint Requirements, will be completed within the next six
months.
Waste Safety and Materials Safety Arenas:
-
NMSS will issue final Screening Considerations and Implementation
Guidance for identifying NMSS regulatory activities that may be amenable
to increased use of risk insights (i.e., to being risk-informed).
These documents will be issued in March 2002.
-
NMSS will review its regulatory activities and apply Screening Considerations
to identify specific, high-priority areas that may be amenable to
being risk-informed in the near-term and long-term. It will also develop
draft safety goals that may be used to direct and promote consistency
among NMSS risk-informed initiatives and activities. These activities
will be completed in March 2002.
-
The risk-informed revision to Inspection Manual Chapter 2604, Licensee
Performance Review will be completed in March 2002.
-
The risk-informed Standard Review Plan for the Review of a License
Application for a Fuel Cycle Facility (NUREG-1520) will be completed
in December 2001.
-
During the next six months RES will complete the following tasks
for the dry cask storage PRA project: analyses of thermal and mechanical
loads on the cask following postulated accidents, human reliability
analysis on probability of cask drop during lifting and transfer of
the cask, and source term and consequence analyses. Results of these
tasks will be used as input into an integrated dry cask PRA model.
RES will run the integrated PRA model to come up with an overall risk
assessment and to identify the dominant risk contributors for the
dry cask storage system. RES will provide a draft report to NMSS with
the results of this assessment in June 2002.
BACKGROUND
In a January 2000 memorandum to the Commission, the staff outlined a
strategy for implementing risk-informed regulation. That strategy evolved
into an initial version of the Risk-Informed Regulation Implementation
Plan (RIRIP), which the staff gave to the Commission in March 2000. The
Commission reviewed the plan and, after a briefing by the staff in March,
directed the staff in April 2000 to include in the next update of the
implementation plan an internal communications plan, staff training requirements,
and a discussion of internal and external factors that may impede risk-informed
regulation.
The first complete version of the implementation plan, issued in October
2000, was intended to integrate the staff's risk-informed activities and
include the supplementary material that the Commission requested in April
2000.
The staff briefed the Commission on the RIRIP on November 17, 2000. Subsequently,
in a staff requirements memorandum (SRM) dated January 4, 2001, the Commission
requested that the staff provide a more detailed communication plan to
better highlight the agency's goal of improving public confidence, prioritize
the activities, identify the necessary resources and tools, address how
performance-based regulatory approaches will be integrated into the process
of risk-informing regulations, and identify the critical path activities
and those that have cross-cutting dimensions.
In response to the SRM this update of the RIRIP, specifically Part 2,
features expanded arena chapters that describe the staff's progress in
prioritizing the various implementation activities and identifying the
necessary resources and tools, critical path activities, and those that
have cross-cutting dimensions. The arena chapters also describe arena-specific
activities related to communication with both internal and external stakeholders.
DISCUSSION
In the past few years, the staff has made significant progress toward
risk-informing its regulatory activities. Attachment
1
to this Commission paper summarizes the staff's significant accomplishments
since the October 2000 RIRIP. While the staff has made considerable progress,
more work remains to be done. Using the Probabilistic Risk Assessment
(PRA) Policy Statement and the NRC's Strategic Plan as its foundation,
the RIRIP describes activities that are planned and underway, and describes
the interrelationships among these activities.
Prioritization of Risk-Informed Regulation Activities
The agency has implemented a planning, budgeting, and performance management
(PBPM) process, which the staff has used to prioritize, plan, budget and
manage the risk-informed regulation activities described in the RIRIP.
The staff has also made much progress in identifying, planning, and implementing
risk- informed activities. Given this experience, the staff recognizes
that the breadth and complexity of initiatives associated with risk-informed
regulation require careful planning and coordination. Therefore, the staff
intends to continue to support the PBPM process through integrated planning
of risk-informed activities. In addition, the staff will continue, and
where necessary initiate, activities to:
-
articulate and propose clear and consistent statements of the vision
for risk-informed regulation
-
develop and propose criteria for judging whether activities to risk-inform
regulation are proceeding in a successful manner
-
discuss the programs that are intended to risk-inform regulation,
and assess whether they are both necessary and sufficient to accomplish
the stated goals
-
identify new programs and recommend changes to existing programs
for applying risk information in the regulatory decision making process
-
develop arena-specific communication plans related to implementing
risk-informed regulation to support the NRC's performance goal to
increase public confidence
-
facilitate the availability and understandability of risk assessment
models and data to the interested public
The staff will work within the line organization and the PRA Steering
Committee, and the appropriate arena management will use the PBPM process
to implement changes to the staff's activities. To facilitate information
exchange on technical and project management issues, staff and management
will closely coordinate activities within the reactor safety arena with
the line organizations and oversight groups in the NRC's Office of Nuclear
Material Safety and Safeguards (NMSS) that are responsible for managing
activities in the materials safety and waste safety arenas (i.e., the
NMSS Risk Task Group and NMSS Risk Steering Committee).
In the course of its planning and review activities, the staff may identify
needed additions and/or modifications to the NRC's Strategic Plan. In
such instances, the staff will follow the established process for updating
the Strategic Plan.
Cost-Benefit Aspects of Risk-Informed Regulation
for Materials Licensees
The SRM specifically indicated that the staff should carefully examine
the cost-benefit aspects of risk-informed regulation for materials licensees
where, in certain instances, risk-informing the process may be cost prohibitive
and provide little or no additional benefit. The staff has factored cost-benefit
aspects into the set of considerations that will be used to evaluate whether
to risk-inform particular nuclear materials and waste regulatory applications.
The set of considerations (referred to as the draft screening criteria
and discussed in Part 1 and Part 2, Chapter 2 of the RIRIP) includes four
considerations addressing potential benefits of risk-informing a regulatory
application, and three considerations addressing costs, feasibility, and
other prohibiting factors that may negate the potential benefits. These
considerations will focus the staff's attention to ensure that the staff
will not pursue risk-informing regulatory applications, particularly those
affecting materials licensees, that will be cost prohibitive or will provide
little or no additional benefit.
Lessons Learned in Risk-Informed Regulation
In addition to making significant progress, the staff acknowledges lessons
learned to-date in risk-informed regulation. In the reactor safety arena,
for example, the staff acknowledges the criticism that progress
toward risk-informed regulation has been uneven and incomplete, and additional
work is needed to better integrate individual projects. The following
highlights summarize some of the lessons learned in the reactor safety
arena:
-
Some important issues arose in connection with the staff's decision
to grant exemptions for the South Texas Project (STP) to vary the
treatment applied to systems, structures, and components on the basis
of their safety significance using a risk-informed categorization
method. The issues of public confidence and acceptance by internal
stakeholders posed significant challenges in the initiative to develop
a risk-informed approach as an alternative to the special treatment
requirements Title 10, Part 50, of the Code of Federal Regulations
in (10 CFR Part 50). The STP exemption review also highlighted the
need for management to provide clear policy and guidance to facilitate
the staff's implementation of risk-informed approaches. To address
these challenges, the staff initiated an activity (RS-EER1-1, described
in the RIRIP) to create an environment in which risk-informed methods
are better integrated into the staff's guidance and activities.
-
The recent staff recommendation to establish explicit equipment reliability
requirements in 10 CFR 50.46 has important implications for agency
decisions related to risk-informing technical specifications. In addition,
the new changes to the Maintenance Rule are also key to risk-informing
technical specifications. These regulations highlight the vigilance
needed to ensure that agency decisions are founded on current, valid
assumptions about nuclear power plant design and operation. Further,
these implications illustrate the need for formal decision making
processes to identify and assess such influences.
-
The staff's experience in examining the technical basis for the requirements
of 10 CFR 50.44 and recommending rule changes raised issues about
the scope of risk-informed regulation. On an issue-specific
basis, the staff may need to weigh the relative benefits of specific
regulatory changes that are expected to reduce unnecessary regulatory
burden while maintaining safety. This benefit assessment will help
to define the extent of regulatory change that is justified and will
focus the agency's limited resources on the most important regulatory
changes, while continuing to account for stakeholder input.
-
A clear vision of what constitutes success in risk-informed implementation
activities will help to ensure that the staff's activities are balanced
and consistent. For example, an articulated and shared vision of the
role of the significance determination process notebooks, the Standardized
Plant Analysis Risk (SPAR) models, and risk-based performance indicators
in the reactor oversight process will promote coordination among these
activities.
-
In the interest of effectiveness and efficiency, the staff recognizes
the need to integrate the application of risk-informed and performance-based
approaches to regulatory change. One approach that the staff is considering
is to modify the management directives associated with rulemaking
to include staff guidance on performance-based and risk-informed regulatory
change.
-
In the next version of the RIRIP, the staff intends to incorporate
process improvements for planning and coordinating risk-informed activities
that are being considered to support the PBPM process as discussed
above. The staff will continue to improve the plan's usefulness in
integrating the agency's overall vision for implementing risk-informed
activities.
The above lessons learned in the reactor safety arena are a function
of the maturity and stage of risk-informed regulation in that arena. Lessons
have also been learned from the initial risk-informed regulation initiatives
and activities in the materials and waste safety arenas, as follows:
-
NMSS is nearing the end of the eight risk-related case studies that
were conducted (1) to test the usefulness and applicability of draft
screening criteria, (2) to evaluate how the application of risk information
has affected or could affect particular areas of the NMSS regulatory
process, and (3) to draft risk metrics and safety goals. The insights
gained thus far indicate the importance of looking laterally across
NMSS activities when evaluating the application of risk information
and comparing and contrasting regulatory, technical, and policy issues
among the different regulatory activities. Also, through stakeholder
interaction, the staff has identified a few modifications to the screening
criteria and is evaluating whether the screening criteria should be
finalized as "considerations" rather than "criteria." The staff has
also found that risk metrics and goals are an essential element of
risk-informing the materials and waste regulatory activities; however,
it is likely that higher-level, generally applicable safety goals
must be supplemented by lower-level, application-specific goals.
-
The case study activities heightened the staff's awareness of the
importance of both external and internal stakeholder involvement.
While many external stakeholders appreciated early involvement in
the process through public workshops, the staff found that some stakeholders
were frustrated by the absence of decisions or conclusions. Also,
the staff found that direct and active involvement of internal staff,
as information resources during the case studies and as subject matter
experts during the stakeholder workshops, fostered a more supportive
environment for risk-informed regulation.
-
In September 2000, the Commission published a risk-informed, performance-based
revision to 10 CFR Part 70. Implementation of this revised rule has
emphasized the importance of adequate guidance and staff training.
As a result, the staff is developing a Standard Review Plan and other
guidance documents that will assist licensees in conducting integrated
safety analyses (ISAs) and the staff in reviewing ISA documentation.
The staff is also providing in-house training on ISA methodology and
review.
-
The NMSS and RES staffs are currently working together to develop
a model PRA for dry cask storage of spent reactor fuel. This activity
demonstrates the feasibility of applying existing risk assessment
methods and tools to regulatory applications that are beyond those
originally targeted. In this case, the dry cask storage study will
demonstrate the successful application of PRA methods and tools, developed
for the reactor arena, to activities in the materials and waste arenas.
Insights gained through this study may support the broader application
of existing PRA and other methods and tools in the materials and waste
safety arenas.
-
Through Phase II of the byproduct materials program review, the staff
identified the need to define risk metrics and goals before making
judgements about resource allocation relative to risk reduction. Risk
metrics and goals should reflect the various areas of concern for
a particular materials application, and should consider avoided consequences
and lowered probabilities of occurrence. The staff also determined
that having risk models and data available in a dynamic system (such
as a computer model or database) together with a static system (such
as a published report) greatly enhances the evaluation of risk assessment
results for risk management purposes. As a result, the staff is developing
a training course to teach the theory and practices used in developing
the "Risk Analysis and Evaluation of Regulatory Options for Nuclear
Byproduct Material Systems" (NUREG/CR-6642), as well as developing
future data and the database and models to support future analyses.
-
The staff found that human reliability and performance are the prevailing
factors that contribute to risk and its uncertainty in radiography
and irradiator risk assessments. The staff also found that a significant
consideration in using risk assessment results is the determination
of a permissible, or tolerable, level of risk. Without a target level
of risk for judging results, the evaluation of a risk analysis may
be limited to measuring the direction of the risk vector. In addition,
without specified permissible levels of risk, small increases in the
risk levels might not be accepted, even if the absolute value of the
risk is quite small and tolerable in other industries.
RIRIP Content and Organization
Part 1 of the October 2000 RIRIP describes its relationship to the PRA
Policy Statement and its relevance to the NRC's Strategic Plan. Part 1
of the RIRIP also discusses certain key features of the traditional deterministic
approach that should be preserved in establishing risk-informed regulatory
programs, since risk information will be used to complement the traditional
approach. In addition, Part 1 of the RIRIP gives draft guidance on selecting
"candidate" requirements, practices, and processes to risk inform.
To complete the plan, Part 2 of the October 2000 RIRIP describes the
staff's risk-informed regulation activities, with chapters addressing
the nuclear reactor safety arena and the nuclear materials and waste safety
arenas. Each chapter is organized around the Strategic Plan strategies
that are relevant to risk-informed regulation in the given arena(s). In
addition, each chapter describes the implementation activities for each
strategy and identifies significant milestones for each activity.
In response to the Commission's direction, the staff has significantly
modified the arena chapters in Part 2 of the RIRIP, as follows:
-
Implementation activities have been added or removed to better focus
on agency activities that are most directly tied to risk-informed
regulation. Consequently, the implementation activities are also presented
in a new order.
-
Training and communication activities are explicitly described as
an integral part of specific implementation activities.
-
The priorities derived from the PBPM process are shown for each implementation
activity.
-
The performance-based aspect of regulatory change is described for
some staff activities (such as 10 CFR 73.55 changes) to communicate
the staff's efforts to implement the agency's performance-based regulation
policy as risk-informed regulatory changes are made.
-
Budgetary resources for each implementation activity are shown for
Fiscal Years 2001 and 2002.
-
Completion dates for major milestones are provided as a measure for
tracking the extent to which the staff has met its schedules.
-
Relationships among implementation activities are described and critical
path items are identified.
-
Gantt charts for each implementation activity have been developed
to illustrate the relationships among activity tasks.
Attachment 2
presents a graphical illustration of the revised format, while Attachment
3
provides the updated version of the RIRIP.
RESOURCES
In response to the Commission's direction regarding the October 2000
version of the RIRIP, as communicated in the SRM dated January 4, 2001,
the plan lists the priority rating(s) of each risk-informed regulation
implementation activity. These priorities were determined through the
PBPM process, and the resources listed in the plan have been budgeted
by the various offices, consistent with their respective operating plans.
While NRR, NMSS, and RES management follow different prioritization processes,
each uses the performance goals defined in the agency's Strategic Plan
to prioritize office activities as part of the budget process. As with
other staff activities, changes to the resources allocated to implementation
activities for risk-informed regulation will continue to be made consistent
with the PBPM process to reflect changes to the agency's budget and priorities.
COORDINATION
The Office of the Chief Financial Officer has reviewed this paper for
resource implications and has no objections. The Office of the General
Counsel has also reviewed this paper and has no legal objections.
|
/RA/
William D. Travers
Executive Director for Operations |
Contact: |
Mark Cunningham, RES
301-415-6189 |
|