Escalated Enforcement Actions Issued to Reactor Licensees - G

Ginna - Docket No. 050-00244

NRC Action Number(s) and
Facility Name
Action Type
(Severity) &
Civil Penalty
(if any)
Date
Issued
Description
EA-08-075
Ginna
NOV
(SL III)
04/07/2008 On April 7, 2008, a Notice of Violation was issued for a Severity Level III violation, due to changes the licensee made to its NRC approved emergency plan; specifically they made changes to the emergency action levels (EALs), between 1996 and 2001, without first obtaining Commission approval.  This decreased the effectiveness of the emergency plan.   The violation cited the licensee for not following 10 CFR 50.54(q), which requires, in part, that a licensee authorized to possess and operate a nuclear power reactor shall follow and maintain in effect emergency plans which meet the standards in 10 CFR 50.47(b) and the requirements in appendix E of this part.
EA-04-003
Ginna
NOV
(SL III)
03/30/2004 On March 30, 2004, a Notice of Violation was issued for a Severity Level III violation involving the willful failure to follow procedures by a manager when he manipulated two valves during a plant cooldown without authorization as required by procedure.
EA-02-141
Ginna
NOV
(White)
10/04/2002 On October 4, 2002, a Notice of Violation was issued for a violation associated with a White SDP finding involving the alert and notification system (ANS). The violation cited failures involving the ANS that could have affected the ability to provide early notification to the public.
EA-97-339
Ginna
NOVCP
(SL III)

$ 55,000
08/15/1997 Failure to protect against a land vehicle bomb.
EA-96-282
Ginna
NOVCP
(SL III)

$100,000
12/13/1996 The action was based on an inspection which identified two violations involving the failure to adequately validate design inputs for the residual heat removal system motor-operated core deluge valves, as well as the failure to adequately correct this condition following its identification.
To top of page

Grand Gulf 1 - Docket No. 050-00416

NRC Action Number(s) and
Facility Name
Action Type
(Severity) &
Civil Penalty
(if any)
Date
Issued
Description
EA-99-305
Grand Gulf 1
NOV
(SL III)
02/22/2000 On February 22, 2000, a Notice of Violation was issued for a Severity Level III problem based on (1) failure to comply with the technical specification for operating the emergency diesel generator; (2) failure to establish adequate alarm response instructions; (3) failure to review a work package, and (4) failure to initiate condition reports for nonconformances.