skip navigation links 
 
 Search Options 
Index | Site Map | FAQ | Facility Info | Reading Rm | New | Help | Glossary | Contact Us blue spacer  
secondary page banner Return to NRC Home Page
				UNITED STATES
                         NUCLEAR REGULATORY COMMISSION
                     OFFICE OF NUCLEAR REACTOR REGULATION
                          WASHINGTON, D.C. 20555-0001

                               January 31, 1996


NRC GENERIC LETTER 96-03:  RELOCATION OF THE PRESSURE TEMPERATURE LIMIT CURVES 
                           AND LOW TEMPERATURE OVERPRESSURE PROTECTION SYSTEM  
                           LIMITS


Addressees 

All holders of operating licenses or construction permits for nuclear power
reactors.

Purpose

The U.S. Nuclear Regulatory Commission (NRC) is issuing this generic letter to
advise licensees that they may request a license amendment to relocate the
pressure temperature (P/T) limit curves from their plant technical
specifications (TS) to a pressure temperature limits report (PTLR) or a
similar document.  The low temperature overpressure protection (LTOP) system
limits may also be relocated to the same document at the discretion of the
licensee.

Description of Circumstances

During the development of the improved standard technical specifications
(STS), a change was proposed to relocate the P/T curves and LTOP setpoint
curves and values currently contained in the TS to a licensee-controlled
document.  As one of the improvements to the STS, the NRC staff agreed with
the industry that the curves and setpoints may be relocated outside the TS to
a licensee-controlled document so that the licensee could maintain these
limits efficiently and at a lower cost, provided that the parameters for
constructing the curves and setpoints are derived using a methodology approved
by the NRC.

Discussion

Technical specifications include limiting conditions for operation (LCOs) that
establish P/T and LTOP system limits for the reactor coolant system.  The
limits are defined by figures and values that provide an acceptable range of
operating temperatures and pressures for heatup, cooldown, low temperature
overpressure, criticality, and inservice leak and hydrostatic testing
conditions.  These parameters are generally valid for a specified number of
effective full-power years or for a specified fluence period (the period for
which the curves are calculated to be applicable).  

License amendments are generally required at the end of the effective period
for P/T limit curves or when surveillance specimens are withdrawn and tested. 
Also, each time the P/T curves are revised, the LTOP system must be 


9601290350.                                                            GL 96-03
                                                            January 31, 1996
                                                            Page 2 of 4


reevaluated to ensure that its functional requirements can still be met. 
Processing amendment requests for changes to TS that are developed using an
accepted methodology places an unnecessary burden on licensee and NRC
resources.  An alternative approach for controlling these limits was proposed
during the development of the improved STS.  This approach, like the one used
for the core operating limits, would relocate the P/T curves and LTOP setpoint
curves or values to a PTLR or a similar document and would reference that
document in the affected LCOs and bases.  

The methodology used to determine the P/T and LTOP system limit parameters
must comply with the specific requirements of Appendices G and H to Part 50 of
Title 10 of the Code of Federal Regulations (10 CFR), be documented in an NRC-
approved topical report or in a plant-specific submittal, and be incorporated
by reference into the TS.  Subsequent changes in the methodology must be
approved by a license amendment; 10 CFR 50.59 does not apply.

Requested Information

Licensees and applicants who choose to adopt this line item improvement are
encouraged to propose changes that are consistent with the attached guidance. 
However, licensees may propose changes, with justification, that differ from
this guidance.  The guidance requires that the licensee be able to reference a
methodology for developing the curves and setpoints that has been approved by
the NRC, develop a PTLR or a similar document that contains the figures,
values, parameters, and any explanations derived from the methodology, and
make appropriate changes to the applicable sections of the TS.  The NRC
project manager for the facility will review the amendment requests that
conform to the guidance in this generic letter and will coordinate the
appropriate staff review of the methodology proposed for calculating the P/T
limit curves and LTOP system limits.  Amendment requests that do not conform
to the guidance in this generic letter will require additional review time.  

Required Response

Licensees and applicants who choose to adopt this line item improvement are
asked to submit the requested information described above to the U.S. Nuclear
Regulatory Commission, ATTN:  Document Control Desk, Washington, D.C. 
20555-0001.
.                                                            GL 96-03
                                                            January 31, 1996
                                                            Page 3 of 4

Backfit Discussion

Any action by licensees to propose changes to TS in accordance with the
guidance in this generic letter is voluntary and, therefore, is not a backfit
under 10 CFR 50.109.  The staff, therefore, did not perform a backfit
analysis.  

Federal Register Notification

The staff published a notice of opportunity for public comment in the
Federal Register (60 FR 28805) on June 2, 1995.  

Paperwork Reduction Act Statement

The voluntary information collections contained in this request are covered by
the Office of Management and Budget clearance number 3150-0011, which expires
on July 31, 1997.  The public reporting burden for this collection of
information is estimated to average 40 hours per response, including the time
for reviewing instructions, searching existing data sources, gathering and
maintaining the data needed, and completing and reviewing the collection of
information.  Send comments regarding this burden estimate or any other aspect
of this collection of information, including suggestions for reducing this
burden, to the Information and Records Management Branch (T-6 F33), 
U.S. Nuclear Regulatory Commission, Washington, D.C. 20555-0001, and to the
Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202
(3150-0011), Office of Management and Budget, Washington, D.C. 20503.

The following information, although not requested under the provisions of 
10 CFR 50.54(f), would help the NRC to evaluate licensee cost to propose TS
changes in accordance with this generic letter:

1.  licensee staff time and costs to prepare the requested reports and         
    documentation and

2.  an estimate of the long-term costs or savings accruing from the response   
    to this generic letter.
.                                                            GL 96-03
                                                            January 31, 1996
                                                            Page 4 of 4


If you have any questions about this matter, please contact the technical
contact listed below or the appropriate Office of Nuclear Reactor Regulation
(NRR) project manager.


                                    signed by

                                 Dennis M. Crutchfield, Director
                                 Division of Reactor Program Management
                                 Office of Nuclear Reactor Regulation

Technical contact:   Maggalean W. Weston, NRR
                     (301) 415-3151
                     Internet:mww@nrc.gov

Attachments:
1.  Guidance for a Proposed License Amendment
      to Relocate the Pressure Temperature 
      Limit Curves and Low Temperature
      Overpressure Protection System Limits
2.  Model Safety Evaluation
3.  Model Technical Specifications:
      a.  Definitions 
      b.  Pressure Temperature Limits 
      c.  Low Temperature Overpressure Protection System 
      d.  Administrative Controls 
4.  List of Recently Issued Generic Letters
.                                                            Attachment 1       
                                                            GL 96-03           
                                                            January 31, 1996
                                                            Page 1 of 7        


                  GUIDANCE FOR A PROPOSED LICENSE AMENDMENT 
               TO RELOCATE THE PRESSURE TEMPERATURE LIMIT CURVES
           AND LOW TEMPERATURE OVERPRESSURE PROTECTION SYSTEM LIMITS


INTRODUCTION 

This attachment to the generic letter contains guidance for preparing a
license amendment request to modify the technical specifications (TS) to
relocate the pressure temperature (P/T) limit curves and low temperature
overpressure protection (LTOP) system limits currently contained in the plant
TS to a pressure temperature limits report (PTLR) or a similar document.  This
alternative was based on a change included in the improved standard technical
specifications (STS) to remove the P/T limit curves and LTOP system limits
from the TS and relocate them to a PTLR or a similar document to reduce the
number of amendment requests associated with changes to these curves and
limits.  Since an amendment request must be submitted whenever a change is
made to the TS, the relocation of the P/T curves and LTOP system limits will
result in a resource savings for the licensees and the NRC by eliminating 
unnecessary license amendment requests for changes to the P/T limit curves and
LTOP system limits in TS. To relocate the P/T curves and LTOP system limits
from the TS, the licensee must be able to reference a methodology approved by
the NRC for deriving the parameters used for constructing the curves and
setpoints, develop a PTLR or a similar document, and make appropriate changes
to the applicable sections of the TS.

In evaluating the relocation, the NRC staff concluded that, while it is
essential to safety to operate the plant within the bounds of P/T limits and
to satisfy the regulations that ensure the integrity of the reactor coolant
pressure boundary (RCPB), the periodic adjustment of those limits to account
for time-dependent parametric changes could be calculated in accordance with a
methodology approved by the NRC.  Criterion 2 of both 10 CFR Part 50, which
was published in the Federal Register (58 FR 39132) on July 22, 1993, and 
10 CFR 50.36(c)(2)(ii)(B), which was published in the Federal Register 
(60 FR 36953) on July 19, 1995, require that the TS include operating
restrictions (P/T limits) needed to preclude unanalyzed accidents and
transients.  However, once the methodology is approved, the licensee may
modify the figures, values, and parameters without the need for a license
amendment and without affecting nuclear safety, provided that these changes
are determined using the approved methodology and are consistent with all
applicable limits of the plant design assumptions as stated in the final
safety analysis report (FSAR).  Additionally, the licensee must submit to the
NRC a formal PTLR or a similar document containing the figures, values, and
parameters derived from the application of the methodology approved by the
NRC.  This reporting requirement augments a reporting requirement that is
already in effect.  Section III of Appendix H to 10 CFR Part 50 currently
requires a summary technical report of data relating to capsule withdrawal and
specimen test results.  Application of these results will also be included in
the PTLR.  This report will allow the NRC staff to continue monitoring the
                                                                              .                                                            Attachment 1       
                                                            GL 96-03           
                                                            January 31, 1996 
                                                            Page 2 of 7        


status of the structural integrity of the reactor vessel even through prior
NRC approval of the changes to these limits would not be required if the
limits do not involve an unreviewed safety question.

A provision was also added to the "Administrative Controls" section of the TS
indicating that the figures, values, and parameters for inclusion in the PTLR
will be verified after each reactor vessel fluence period or when surveillance
specimens are withdrawn and tested and the PTLR submitted to the NRC.  Hence,
the staff can confirm proper application of the methodology approved by the
NRC.  Further, the PTLR will be referenced in the TS so that the same degree
of control on plant operation will be maintained.  As a result, this
alternative provides the same assurance of compliance with design
specifications as before, yet removes the unnecessary burden on both plant and
NRC staff of processing amendment requests.    

DISCUSSION

Technical specifications include limiting conditions for operation (LCOs) that
establish P/T limits for the reactor coolant system (RCS).  This system is
designed to withstand the effects of cyclic loads resulting from system
temperature and pressure changes.  These cyclic loads are introduced by normal
load transients, reactor trips, startup and shutdown operations, and
hydrostatic and leak rate tests.  During startup and shutdown, the rates of
temperature and pressure changes are limited so that the maximum specified
heatup and cooldown rates are consistent with the design assumptions and
satisfy operating limits that provide a wide margin of safety to brittle
failure of the reactor vessel.  The P/T limits are periodically modified as
the reactor vessel material toughness decreases as a result of material
embrittlement caused by neutron irradiation.  The periodic modifications are
necessary when the applicable effective full-power years (EFPYs) or fluence
period for the P/T limits contained in the TS are about to expire or when the
reactor vessel material surveillance data indicate an increase in the nil-
ductility transition reference temperature (RTNDT).  
 
As required by Appendix G to 10 CFR Part 50, operating P/T limits are
calculated and adhered to by plant operations personnel to ensure that
fracture toughness requirements for the RCPB are maintained.  Further, in
accordance with Appendix H to 10 CFR Part 50, specimens of reactor vessel
material are installed near the inside reactor vessel wall and are withdrawn
on a schedule to provide data on the effects of radiation fluence and the
thermal environment on the vessel material.  These data are used to adjust the
P/T limits, as necessary, to compensate for the shift in material transition
temperature as indicated by tests on the withdrawn specimens.  The withdrawal
and analysis of the specimens, and resulting revision of the P/T limit curves,
make up the requirements necessary to compensate for the shift in material
transition temperature.  This ensures that the reactor vessel is operated at
high enough temperatures to preclude brittle fracture of the vessel material.  
.                                                            Attachment 1       
                                                            GL 96-03           
                                                            January 31, 1996 
                                                            Page 3 of 7        


The LTOP system controls RCS pressure at low operating temperatures so that
the integrity of the RCPB is not compromised by violating the P/T limits of
Appendix G to 10 CFR Part 50.  The LTOP system provides overpressure
protection by limiting coolant input capability and having adequate pressure 
relief capacity.  Each time the P/T limit curves are revised, the LTOP system
must be reevaluated to ensure that its functional requirements can still be
met.  LTOP system limits may be relocated to the PTLR or retained in the TS. 
The LTOP system for pressure relief typically consists of two power-operated
relief valves (PORVs), two residual heat removal (RHR) suction relief valves,
or a combination of both.  Some plants have only one PORV.  The LTOP system

limits consist of PORV and RHR relief valve setpoints.  The RHR suction relief
valves do not have variable pressure lift setpoints as the PORVs do and,
therefore, are still addressed in the TS.  As designed for the LTOP system,
each PORV is signaled to open if the RCS pressure approaches a limit
determined by the LTOP system actuation logic.  This logic monitors both RCS
temperature and RCS pressure to determine when a condition not acceptable in
the PTLR is approached.  The PORV setpoints may be included in the PTLR and
should be updated when the revised P/T limits conflict with the LTOP system
limits.  LTOP requirements do not apply to boiling water reactors. 

REQUIREMENTS FOR RELOCATING THE CURVES AND SETPOINTS  

Relocation of the curves and setpoints to a licensee-controlled document
requires three separate licensee actions.  The licensee must (1) have a
methodology approved by the NRC to reference in its TS; (2) develop a report
such as a PTLR or a similar document to contain the figures, values,
parameters, and any explanation necessary; and (3) modify the applicable
sections of the TS accordingly.

.     Methodology and PTLR

The first two of the three requirements for relocating the P/T curves and LTOP
system limits are an NRC-approved methodology and the associated reporting
requirements in the PTLR.  The methodology will consist of only those methods
used for calculation, not the calculations themselves.  The PTLR will consist
of the explanations, figures, values, and parameters derived from the
calculations.  Since the PTLR will be provided to the NRC upon issuance after
each fluence period or EFPYs and after approval of the methodology, a PTLR
should be provided when the methodology is submitted so that questions
regarding the content and format of the PTLR can be addressed prior to its
formal completion. 

The following table shows the relationship between the provisions, if
applicable, specified in the STS for the approved methodology and the
requirements to be included in the methodology and the PTLR.  The provisions
for the methodology are those shown in the "Administrative Controls" section
of the STS. .                                                            Attachment 1     
                                                            GL 96-03         
                                                            Janaury 31, 1996
                                                            Page 4 of 7      


                     REQUIREMENTS FOR METHODOLOGY AND PTLR

PROVISIONS FOR METHODOLOGY
FROM ADMINISTRATIVE CONTROLS
SECTION IN STS.MINIMUM REQUIREMENTS TO
BE INCLUDED IN
METHODOLOGY.MINIMUM REQUIREMENTS TO
BE INCLUDED IN PTLR.1.The methodology shall
     describe how the neutron
     fluence is calculated
     (reference new regulatory
     guide when it is issued)..Describe transport
     calculation methods
     including computer codes
     and formulas used to
     calculate neutron
     fluence.  Provide
     references..Provide the values of
     neutron fluences that are
     used in the adjusted
     reference temperature
     (ART) calculation..2.The Reactor Vessel
     Material Surveillance
     Program shall comply with
     Appendix H to 10 CFR Part
     50.  The reactor vessel
     material irradiation
     surveillance specimen
     removal schedule shall be
     provided, along with how
     the specimen examinations
     shall be used to update
     the PTLR curves..Briefly describe the
     surveillance program. 
     Licensee transmittal
     letter should identify by
     title and number report
     containing the Reactor
     Vessel Surveillance
     Program and surveillance
     capsule reports.
     Topical/generic report
     contains placeholder
     only.  Reference Appendix
     H to 10 CFR Part 50..Provide the surveillance
     capsule withdrawal
     schedule, or reference by
     title and number the
     documents in which the
     schedule is located. 

Reference the
surveillance capsule
reports by title and
number if ARTs are
calculated using
surveillance data. .3.Low temperature
     overpressure protection
     (LTOP) system limits
     developed using NRC-
     approved methodologies
     may be included in the
     PTLR. .Describe how the LTOP
     system limits are
     calculated applying
     system/thermal hydraulics
     and fracture mechanics. 
     Reference SRP Section
     5.2.2; ASME Code Case 
N-514; ASME Code,
Appendix G, Section XI as
applied in accordance
with 10 CFR 50.55.  .Provide setpoint curves
or setpoint values.

.4.  The adjusted reference
     temperature (ART) for
     each reactor beltline
     material shall be
     calculated, accounting
     for irradiation
     embrittlement, in
     accordance with
     Regulatory Guide 1.99,
     Revision 2..Describe the method for
     calculating the ART using
     Regulatory Guide 1.99,
     Revision 2.
   .Identify both the
limiting ART values and
limiting materials at the
1/4t and 3/4t locations
(t = vessel beltline
thickness).

PWRs - identify RTPTS
value in accordance with
10 CFR 50.61..5.The limiting ART shall be 
     incorporated into the
     calculation of the
     pressure and temperature
     limit curves in
     accordance with NUREG-
     0800, SRP Section 5.3.2,
     Pressure-Temperature
     Limits..Describe the application
     of fracture mechanics in
     constructing P/T curves
     based on ASME Code,
     Appendix G, Section XI,
     and SRP Section 5.3.2. .Provide the P/T curves
     for heatup, cooldown,
     criticality, and
     hydrostatic and leak
     tests..6.The minimum temperature
     requirements of Appendix
     G to 10 CFR Part 50 shall
     be incorporated into the
     pressure and temperature
     limit curves..Describe how the minimum
     temperature requirements
     in Appendix G to 10 CFR
     Part 50 are applied to
     P/T curves..Identify minimum
     temperatures on the P/T
     curves such as minimum
     boltup temperature and
     hydrotest temperature..7.Licensees who have
     removed two or more
     capsules should compare
     for each surveillance
     material the measured
     increase in reference
     temperature (RTNDT) to
     the predicted increase in
     RTNDT; where the
     predicted increase in
     RTNDT is based on the
     mean shift in RTNDT plus
     the two standard
     deviation value (2å.)
     specified in Regulatory
     Guide 1.99, Revision 2. 
     If the measured value
     exceeds the predicted
     value (increase in RTNDT
     + 2å.), the licensee
     should provide a
     supplement to the PTLR to
     demonstrate how the
     results affect the
     approved methodology..Describe how the data
     from multiple
     surveillance capsules are
     used in the ART
     calculation. 

Describe procedure if
measured value exceeds
predicted value.

WHEN OTHER PLANT DATA ARE
USED
1. Identify the source(s)
of data when other plant
data are used.

2.a  Identify by title
and number the safety
evaluation report that
approved the use of data  
for the plant.  Justify   
applicability.  

OR

2.b  Compare licensee
data with other plant
data for both the 
radiation environments
(e.g., neutron spectrum,
irradiation temperature)
and the surveillance test
results. .Provide supplemental data
and calculations of the
chemistry factor in the
PTLR if the surveillance
data are used in the ART
calculation.

Evaluate the surveillance
data to determine if they
meet the credibility
criteria in Regulatory
Guide 1.99, Revision 2. 
Provide the results..                                                            Attachment 1       
                                                            GL 96-03           
                                                            January 31, 1996
                                                            Page 6 of 7        


.     Technical Specifications

The following changes must be made to the plant TS to complete the three
requirements for relocating the curves and setpoints to an alternative
document. 

Three separate actions are necessary to modify the plant TS: (1) "Definitions"
- the addition of the definition of a named formal report (PTLR or a similar
document) that would contain the explanations, figures, values, and parameters
derived in accordance with an NRC-approved methodology and consistent with all
of the design assumptions and stress limits for cyclic operation;  (2) LCOs -
the addition of references to the PTLR noting that the P/T limits shall be
maintained within the limits specified in the PTLR; and (3) "Administrative
Controls" - the addition of a reporting requirement to submit the PTLR to the
NRC, when it is issued, for each reactor vessel fluence period.

   1.  Definitions

   Section 1.0, "Definitions," should contain the following language:

        PRESSURE TEMPERATURE LIMITS REPORT (PTLR)     

        The PTLR is the unit-specific document that provides the reactor
        vessel P/T limits and setpoints, including heatup and cooldown
        rates, for the current reactor vessel fluence period.  These P/T
        limits shall be determined for each fluence period or effective
        full-power years (EFPYs) in accordance with
        Specification 5.X.X.X.  Plant operation within these operating
        limits is addressed in LCO 3.X.X, "RCS Pressure and Temperature
        (P/T) Limits," and LCO 3.X.X, "Low Temperature Overpressure
        Protection (LTOP) System."

     2.  Limiting Conditions for Operation (LCOs) and Bases

     LCO 3.X.X, "RCS Pressure and Temperature (P/T) Limits," and LCO 3.X.X, "Low   
     Temperature Overpressure Protection (LTOP) System," must reference the PTLR   
     as the document where the limits and curves can be found as demonstrated in   
     the attached model TS.  The bases for these LCOs should be modified           
     accordingly.

     3.  Administrative Controls

     Section 5.X, "Administrative Controls," Subsection 5.X.X, "Reporting          
     Requirements," must contain the following information:   
.                                                               Attachment 1       
                                                               GL 96-03           
                                                               January 31, 1996
                                                               Page 7 of 7        


        Section 5.X.X.X Reactor Coolant System (RCS) PRESSURE AND TEMPERATURE
                        LIMITS REPORT (PTLR)

        a.  RCS pressure and temperature limits for heatup, cooldown, LTOP,
            criticality, and hydrostatic testing as well as heatup and cooldown 
            rates shall be established and documented in the PTLR for the
            following: [The individual specifications that address RCS pressure
            and temperature limits must be referenced here.]

        b.  The analytical methods used to determine the RCS pressure and
            temperature limits shall be those previously reviewed and approved by
            the NRC, specifically those described in the following document(s):
            [Identify the NRC staff approval document(s) by date.]

        c.  The PTLR shall be provided to the NRC upon issuance for each reactor
            vessel fluence period or EFPYs and for any revision or supplement
            thereto.
.                                                            Attachment 2     
                                                            GL 96-03         
                                                            January 31, 1996
                                                            Page 1 of 5      


                         MODEL SAFETY EVALUATION (SE)


  Underscored blank spaces are to be completed on the basis of the applicable
  facility information.  The information in brackets should be used, as
  applicable, on a plant-specific basis.

   SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO
           AMENDMENT NO.     TO FACILITY OPERATING LICENSE NFP-    
                                [UTILITY NAME] 
                           [PLANT NAME], [UNIT    ]
                              DOCKET NO. 50-    

1.0  INTRODUCTION


By letter dated         , 19  , [utility name] (the licensee) proposed changes
to the technical specifications (TS) for [plant name].  The requested changes
are the relocation of the pressure temperature (P/T) limit curves and low
temperature overpressure protection (LTOP) system limits to the [named plant-
specific report] and the referencing of that report in the affected limiting
conditions for operation and bases.  The proposed changes also include the
addition of the [named plant-specific report] to the definitions section of
the TS and the addition of a new section to the reporting requirements in the
administrative controls section of the TS delineating the necessary reports. 
Guidance on the proposed changes was developed by the Nuclear Regulatory
Commission (NRC) on the basis of a proposal by the owners groups during the
development of the improved standard technical specifications (STS).  This
guidance was provided to all power reactor licensees and applicants by Generic
Letter YY-XX, dated         , 19  .


2.0  BACKGROUND

Section 182a of the Atomic Energy Act (the Act) requires applicants for
nuclear power plant operating licenses to include TS as part of the license. 
The Commission's regulatory requirements related to the content of TS are set
forth in 10 CFR 50.36.  That regulation requires that the TS include items in
five specific categories:  (1) safety limits, limiting safety system settings
and limiting control settings; (2) limiting conditions for operation;
(3) surveillance requirements; (4) design features; and (5) administrative
controls, and states also that the Commission may include such additional TS
as it finds to be appropriate.  However, the regulation does not specify the
particular requirements to be included in a plant's TS.

The Commission has provided guidance for the contents of TS in its "Final
Policy Statement on Technical Specifications Improvements for Nuclear Power
Reactors" (Final Policy Statement), 58 FR 39132 (July 22, 1993), in which the
Commission indicated that compliance with the Final Policy Statement satisfies
Section 182a of the Act.  In particular, the Commission indicated that certain.                                                            Attachment 2     
                                                            GL 96-03         
                                                            January 31, 1996
                                                            Page 2 of 5      


items could be relocated from the TS to licensee-controlled documents,
consistent with the standard enunciated in Portland General Electric Co.
(Trojan Nuclear Plant), ASLAB-531, 9 NRC 263, 273 (1979).  In that case, the
Atomic Safety and Licensing Appeal Board indicated that "technical
specifications are to be reserved for those matters as to which the imposition
of rigid conditions or limitations upon reactor operation is deemed necessary
to obviate the possibility of an abnormal situation or event giving rise to an
immediate threat to the public health and safety."  

Consistent with this approach, the Final Policy Statement identified four
criteria to be used in determining whether a particular matter is required to
be included in the TS, as follows:  (1) installed instrumentation that is used
to detect, and indicate in the control room, a significant abnormal
degradation of the reactor coolant pressure boundary; (2) a process variable,
design feature, or operating restriction that is an initial condition of a
design basis accident or transient analysis that either assumes the failure of
or presents a challenge to the integrity of a fission product barrier; (3) a
structure, system, or component that is part of the primary success path and
which functions or actuates to mitigate a design basis accident or transient
that either assumes the failure of or presents a challenge to the integrity of
a fission product barrier; (4) a structure, system, or component which
operating experience or probabilistic safety assessment has shown to be
significant to public health and safety.  As a result, existing TS
requirements which fall within or satisfy any of the criteria in the Final
Policy Statement must be retained in the TS, while those TS requirements which
do not fall within or satisfy these criteria may be relocated to other
licensee-controlled documents. 


3.0  EVALUATION

All components of the reactor coolant system (RCS) are designed to withstand
the effects of cyclic loads resulting from system pressure and temperature
changes.  These loads are introduced by heatup and cooldown operations, power
transients, and reactor trips.  In accordance with Appendix G to 10 CFR 
Part 50, TS limit the pressure and temperature changes during RCS heatup and
cooldown within the design assumptions and the stress limits for cyclic
operation.  These limits are defined by P/T limit curves for heatup, cooldown,
LTOP, and inservice leak and hydrostatic testing.  Each curve defines an
acceptable region for normal operation.  The curves are used for operational
guidance during heatup and cooldown maneuvering, when pressure and temperature
indications are monitored and compared to the applicable curve to determine
that operation is within the allowable region..                                                            Attachment 2     
                                                            GL 96-03         
                                                            January 31, 1996
                                                            Page 3 of 5      


[Reviewer Note:  While the NRC is completing the rulemaking process for
revisions to 10 CFR 50.55a and 10 CFR Part 50, Appendix G, licensees using the
American Society of Mechanical Engineers Boiler and Pressure Vessel Code 
Case N-514 must request an exemption from Appendix G.  The following or
similar language should be included in the SE:

The licensee used the American Society of Mechanical Engineers Boiler and
Pressure Vessel Code Case N-514 and requested an exemption from Appendix G by
justifying why Appendix G cannot be met and demonstrating that a specific
exemption was warranted under 10 CFR 50.12.]

The LTOP system controls RCS pressure at low temperatures so that the
integrity of the reactor coolant pressure boundary is not compromised by
violating 10 CFR Part 50, Appendix G.  [Reviewer Note: The following sentences
should be modified to identify the specific LTOP system being referred to in
the SE:  The LTOP system for pressure relief, for most plants, consists of
power-operated relief valves (PORVs), residual heat removal suction relief
valves, or a combination of both.  Some plants have one PORV.  The LTOP system
limits consist of PORV and RHR setpoints.  The RHR suction relief valves do
not have variable pressure and temperature lift setpoints like the PORVs and,
therefore, are still addressed in the TS.]  The LTOP system is reevaluated
each time the P/T limit curves are revised to ensure that it meets its
intended function.

The licensee-proposed changes to the TS are in accordance with the guidance in
Generic Letter YY-XX, as follows:

(1)    The definitions section of the TS was modified to include a definition
       of the [named report] to which the figures, values, and parameters for
       P/T and LTOP system limits will be relocated on a unit-specific basis
       in accordance with a methodology approved by the NRC that maintains
       the acceptance limits and the limits of the safety analysis.  As noted
       in the definition, plant operation within these limits is addressed by
       individual specifications.

(2)    The following specifications were revised to replace the P/T and LTOP
       system limits with a reference to the [named report] that provides
       these limits:

       [Provide list of specifications by number and title.]

(3)    Specification [number], "[title]," was added to the reporting
       requirements of the administrative controls section of the TS.  This
       specification requires that the [named report] be submitted, upon
       issuance, to the NRC Document Control Desk with copies to the regional
       administrator and resident inspector.  The report provides the
       explanations, figures, values, and parameters of the P/T and LTOP
       system limits for the applicable effective period.  Furthermore, this
       specification requires that the figures, values, and parameters be .                                                            Attachment 2     
                                                            GL 96-03         
                                                            January 31, 1996
                                                            Page 4 of 5      


       established using the methodology approved by the NRC for this purpose
       in [topical report or NRC letter approving a plant-specific
       methodology] and be consistent with all the applicable acceptance
       limits and the limits of the safety analysis.  

       Finally, the specification requires that all changes in values of
       these limits be documented in the [named report] each effective period
       and submitted upon issuance to the NRC.

Relocation of the P/T curves and LTOP setpoints does not eliminate the
requirement to operate in accordance with the limits specified in Appendix G
to 10 CFR Part 50.  The requirement to operate within the limits in the named
report or pressure temperature limits report (PTLR) is specified in and
controlled by the TS.  Only the figures, values, and parameters associated
with the P/T limits and LTOP setpoints are to be relocated to the PTLR.  In
order for the curves and setpoints to be relocated to a PTLR, a methodology
for their development must be reviewed and approved in advance by the NRC. 
The methodology to be approved by the NRC is to be developed in accordance
with GL 96-03.  This generic letter delineates the requirements for both the
methodology and the PTLR including, but not limited to, the requirements of
Appendix G to 10 CFR Part 50.  The PTLR review process requires that changes
to the methodology be approved by the NRC.  Further, when changes are made to
the figures, values, and parameters contained in the PTLR, the PTLR is to be
updated and submitted to the NRC upon issuance.  

On this basis, the NRC staff concludes that the licensee provided an
acceptable means of establishing and maintaining the detailed values of the
P/T limit curves and LTOP system limits.  Further, because plant operation
continues to be limited in accordance with the requirements of Appendix G 
to 10 CFR Part 50 and the P/T and LTOP system limits in the TS will be
established using a methodology approved by the NRC, these changes will not
impact plant safety.  

The staff also concludes that the relocated requirements discussed above
relating to the P/T limits and LTOP system limits are not required to be in
the TS under 10 CFR 50.36 or Section 182a of the Atomic Energy Act, and are
not required to obviate the possibility of an abnormal situation or event
giving rise to an immediate threat to the public health and safety. 
Additionally, they do not fall within any of the four criteria set forth in
the Commission's Final Policy Statement, discussed above.  Accordingly, the
staff concludes that the proposed changes are acceptable and that these
requirements may be relocated from the TS to the PTLR.


4.0  STATE CONSULTATION

The Commission consulted with the State of [  ].  No public comments were
received, and the State of [   ] did not have any comments.
.                                                            Attachment 2     
                                                            GL 96-03         
                                                            January 31, 1996
                                                            Page 5 of 5      


5.0  ENVIRONMENTAL CONSIDERATION

The amendment involves changes to requirements with respect to use of facility
components located within the restricted area, as defined in 10 CFR Part 20,
changes with respect to surveillance requirements, and changes in
administrative procedures or requirements.  The NRC staff determined that the
amendment involves no significant increase in the amounts and no significant
change in the types of any effluents that may be released off site and that
there is no significant increase in individual or cumulative occupational
exposure.  The Commission made a determination that the amendment involves no
significant hazards consideration, which was published in the Federal Register
(53 FR   ) on       , 19  , and there has been no public comment regarding
such a finding.  Accordingly, the amendment meets the eligibility criteria for
categorical exclusion set forth in 10 CFR 51.22(c)(9) and (c)(10).  Pursuant
to 10 CFR 51.22(b), no environmental impact statement or environmental
assessment need be prepared in connection with the issuance of the amendment.


6.0  CONCLUSION

On the basis of the considerations discussed above, the NRC staff concludes
that (1) there is reasonable assurance that the health and safety of the
public will not be endangered by operation in the proposed manner, (2) such
activities will be conducted in compliance with the Commission's regulations,
and (3) the issuance of this amendment will not be inimical to the common
defense and security or to the health and safety of the public.

Principal Contributor:  Maggalean W. Weston, TSB 
  

Dated:       , 19    
.                                                            Attachment 3a
                                                            GL 96-03
                                                            January 31, 1996
                                                            Page 1 of 1


                                                            Definitions
                                                            1.1

1.0  USE AND APPLICATION

1.1  Definitions
ÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍ

-------------------------------------NOTE-------------------------------------
The defined terms of this section appear in capitalized type and are
applicable throughout these Technical Specifications and Bases.
------------------------------------------------------------------------------

Term                    Definition

PRESSURE AND            The PTLR is the unit specific document that
TEMPERATURE LIMITS      provides the reactor vessel pressure and
REPORT (PTLR)           temperature limits, including heatup and cooldown
                        rates, for the current reactor vessel fluence period. 
                        These pressure and temperature limits shall be
                        determined for each fluence period in accordance with
                        Specification 5.6.6.  Plant operation within these
                        operating limits is addressed in LCO 3.4.3, "RCS
                        Pressure and Temperature (P/T) Limits," and
                        LCO 3.4.12, "Low Temperature Overpressure Protection
                        (LTOP) System."

QUADRANT POWER TILT     QPTR shall be the ratio of the maximum upper
RATIO (QPTR)            excore detector calibrated output to the average of
                        the upper excore detector calibrated outputs, or the
                        ratio of the maximum lower excore detector calibrated
                        output to the average of the lower excore detector
                        calibrated outputs, whichever is greater.

RATED THERMAL POWER     RTP shall be a total reactor core heat transfer
(RTP)                   rate to the reactor coolant of [2893] MWt.

REACTOR TRIP            The RTS RESPONSE TIME shall be that time interval
SYSTEM (RTS) RESPONSE   from when the monitored parameter exceeds its RTS
TIME                    trip setpoint at the channel sensor until loss of
                        stationary gripper coil voltage.  The response time
                        may be measured by means of any series of sequential,
                        overlapping, or total steps so that the entire
                        response time is measured.

SHUTDOWN MARGIN (SDM)   SDM shall be the instantaneous amount of reactivity by
                        which the reactor is subcritical or would be
                        subcritical from its present condition assuming:

.                                                            Attachment 3b
                                                            GL 96-03
                                                            January 31, 1996
                                                            Page 1 of 2


3.4  REACTOR COOLANT SYSTEM (RCS)

3.4.X  RCS Pressure and Temperature (P/T) Limits


LCO  3.4.X  RCS pressure, RCS temperature, and RCS heatup and cooldown rates
            shall be maintained within the limits specified in the PTLR.



APPLICABILITY:    At all times.


ACTIONS
          CONDITION.                 REQUIRED ACTION.         COMPLETION TIME.
A.  ---------NOTE---------
    Required Action A.2
    shall be completed
    whenever this
    Condition is entered.
    ----------------------

    Requirements of LCO
    not met in MODE 1, 2,
    3, or 4.
.
A.1                                  Restore parameter(s)
                                     to within limits.

AND

A.2                                  Determine RCS is
                                     acceptable for
                                     continued operation.
.
30 minutes




72 hours.
B.  Required Action and
    associated Completion
    Time of Condition A
    not met.
.
B.1                                  Be in MODE 3.

AND

B.2                                  Be in MODE 5 with RCS
                                     pressure
                                     < [500] psig.
.
6 hours



36 hours...(continued).

C.  ---------NOTE---------
    Required Action C.2
    shall be completed
    whenever this
    Condition is entered.
    ----------------------

    Requirements of LCO
    not met any time in
    other than MODE 1, 2,
    3, or 4.
.

C.1                                  Initiate action to
                                     restore parameter(s)
                                     to within limits.

AND

C.2                                  Determine RCS is
                                     acceptable for
                                     continued operation.
.

Immediately





Prior to
entering MODE 4



SURVEILLANCE REQUIREMENTS
                        SURVEILLANCE.                            FREQUENCY.
SR  3.4.X.X     -------------------NOTE--------------------
                Only required to be performed during RCS
                heatup and cooldown operations and RCS
                inservice leak and hydrostatic testing.
                -------------------------------------------

                Verify RCS pressure, RCS temperature, and
                RCS heatup and cooldown rates are within
                the limits specified in the PTLR.
.






30 minutes.                                                            Attachment 3c
                                                            GL 96-03
                                                            January 31, 1996
                                                            Page 1 of 6        
                                                   


3.4  REACTOR COOLANT SYSTEM (RCS)

3.4.X  Low Temperature Overpressure Protection (LTOP) System


LCO  3.4.X     An LTOP System shall be OPERABLE with a maximum of [one] [high
               pressure injection (HPI)] pump [and one charging pump] capable
               of injecting into the RCS and the accumulators isolated and
               either a or b below.

                 a.  Two RCS relief valves, as follows:

                     1.   Two power operated relief valves (PORVs) with lift
                          settings within the limits specified in the PTLR,
                          or

                     [2.  Two residual heat removal (RHR) suction relief
                          valves with setpoints ò [436.5] psig and
                          ó [463.5] psig, or]

                     [3.  One PORV with a lift setting within the limits
                          specified in the PTLR and one RHR suction relief
                          valve with a setpoint ò [436.5] psig and
                          ó [463.5] psig].

                 b.  The RCS depressurized and an RCS vent of ò [2.07] square
                     inches.



APPLICABILITY:   MODE 4 when all RCS cold leg temperature is ó [275]øF,
                 MODE 5,
                 MODE 6 when the reactor vessel head is on.

                 ----------------------------NOTE----------------------------
                 Accumulator isolation is only required when accumulator
                 pressure is greater than or equal to the maximum RCS
                 pressure for the existing RCS cold leg temperature allowed
                 by the P/T limit curves provided in the PTLR.
                 ------------------------------------------------------------
.                                                            Attachment 3c
                                                            GL 96-03
                                                            January 31, 1996
                                                            Page 2 of 6


ACTIONS
          CONDITION.                 REQUIRED ACTION.         COMPLETION TIME.
A.  Two or more [HPI]
    pumps capable of
    injecting into the
    RCS.
.
A.1                                  Initiate action to
                                     verify a maximum of
                                     [one] [HPI] pump is
                                     capable of injecting
                                     into the RCS.
.
Immediately.ÚÄÄ
³B.Two or more charging
³   pumps capable of
³   injecting into the
³   RCS.
³
³
³
³
³
³
³
³
³
³
³
ÀÄÄ.
B.1                                  --------NOTE---------
                                     Two charging pumps
                                     may be capable of
                                     injecting into the
                                     RCS during pump swap
                                     operation for
                                     ó 15 minutes.
                                     ---------------------

                                     Initiate action to
                                     verify a maximum of
                                     [one] charging pump
                                     is capable of
                                     injecting into the
                                     RCS.
.                                                                         ÄÄ¿
                                                                            ³
                                                                            ³
                                                                            ³
                                                                            ³
                                                                            ³
                                                                            ³
                                                                            ³
                                                                            ³
                                                                            ³
Immediately                                                                 ³
                                                                            ³
                                                                            ³
                                                                            ³
                                                                            ³
                                                                            ³
                                                                          ÄÄÙ                          .
C.  An accumulator not
    isolated when the
    accumulator pressure
    is greater than or
    equal to the maximum
    RCS pressure for
    existing cold leg
    temperature allowed in
    the PTLR.
.
C.1                                  Isolate affected
                                     accumulator.
.
1 hour...                                                         (continued).
D.  Required Action and
    associated Completion
    Time of Condition [C]
    not met.
.
D.1                                  Increase RCS cold leg
                                     temperature to
                                     > [275]øF.

OR

D.2                                  Depressurize affected
                                     accumulator to less
                                     than the maximum RCS
                                     pressure for existing
                                     cold leg temperature
                                     allowed in the PTLR.
.
12 hours





12 hours.
E.  One required RCS
    relief valve
    inoperable in MODE 4.
.
E.1                                  Restore required RCS
                                     relief valve to
                                     OPERABLE status.
.
7 days.
F.  One required RCS
    relief valve
    inoperable in MODE 5
    or 6.
.
F.1                                  Restore required RCS
                                     relief valve to
                                     OPERABLE status.
.
24 hours...                                                       (continued).
G.  Two required RCS
    relief valves
    inoperable.

    OR

    Required Action and
    associated Completion
    Time of Condition A,
    [B,] D, E, or F not
    met.

    OR

    LTOP System inoperable
    for any reason other
    than Condition A, [B,]
    C, D, E, or F.
.
G.1                                  Depressurize RCS and
                                     establish RCS vent of
                                     ò [2.07] square
                                     inches.
.
8 hours



SURVEILLANCE REQUIREMENTS
                        SURVEILLANCE.                            FREQUENCY.
SR  3.4.X.X     Verify a maximum of [one] [HPI] pump is
                capable of injecting into the RCS.
.
12 hours.ÚÄÄ
³SR 3.4.X.X     Verify a maximum of one charging pump is
³               capable of injecting into the RCS.
ÀÄÄ.                                                                      ÄÄ¿
12 hours                                                                    ³
                                                                            ³
                                                                          ÄÄÙ.
SR  3.4.X.X     Verify each accumulator is isolated.
.
12 hours..                                                        (continued).ÚÄÄ
³SR 3.4.X.X     Verify RHR suction valve is open for each
³               required RHR suction relief valve.
ÀÄÄ.                                                                      ÄÄ¿
12 hours                                                                    ³
                                                                            ³
                                                                          ÄÄÙ.
SR  3.4.X.X     -------------------NOTE--------------------
                Only required to be performed when
                complying with LCO 3.4.12.b.
                -------------------------------------------

                Verify RCS vent ò [2.07] square inches
                open.
.





12 hours for
unlocked open
vent valve(s)

AND

31 days for
locked open
vent valve(s)
.
SR  3.4.X.X     Verify PORV block valve is open for each
                required PORV.
.
72 hours.ÚÄÄ
³SR 3.4.X.X     Verify associated RHR suction isolation
³               valve is locked open with operator power
³               removed for each required RHR suction
³               relief valve.
ÀÄÄ.                                                                      ÄÄ¿
31 days                                                                     ³
                                                                            ³
                                                                            ³
                                                                            ³
                                                                          ÄÄÙ.
SR  3.4.X.X     -------------------NOTE--------------------
                Not required to be met until 12 hours after
                decreasing RCS cold leg temperature to
                ó [275]øF.
                -------------------------------------------

                Perform a COT on each required PORV,
                excluding actuation.
.






31 days..                                                         (continued).
SR  3.4.X.X     Perform CHANNEL CALIBRATION for each
                required PORV actuation channel.
.
[18] months.                                                            Attachment 3d      
                                                            GL 96-03
                                                            January 31, 1996
                                                            Page 1 of 2




5.0  ADMINISTRATIVE CONTROLS

5.6  Reporting Requirements
ÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍÍ

5.6.X          Reactor Coolant System (RCS) PRESSURE AND TEMPERATURE LIMITS
               REPORT (PTLR)

               a.   RCS pressure and temperature limits for heat up,
                    cooldown, low temperature operation, criticality, and
                    hydrostatic testing as well as heatup and cooldown rates
                    shall be established and documented in the PTLR for the
                    following:  [The individual specifications that address
                    RCS pressure and temperature limits must be referenced
                    here.] 

               b.   The analytical methods used to determine the RCS pressure
                    and temperature limits shall be those previously reviewed
                    and approved by the NRC, specifically those described in
                    the following documents:  [Identify the NRC staff
                    approval document by date.]

               c.   The PTLR shall be provided to the NRC upon issuance for
                    each reactor vessel fluence period and for any revision
                    or supplement thereto.

                                                                              
               Reviewers' Notes:  The methodology for the calculation of the
               P-T limits for NRC approval should include the following
               provisions:

               1.   The methodology shall describe how the neutron fluence is
                    calculated (reference new Regulatory Guide when issued).

               2.   The Reactor Vessel Material Surveillance Program shall
                    comply with Appendix H to 10 CFR Part 50.  The reactor
                    vessel material irradiation surveillance specimen removal
                    schedule shall be provided, along with how the specimen
                    examinations shall be used to update the PTLR curves.

               3.   Low Temperature Overpressure Protection (LTOP) System
                    lift setting limits for the Power Operated Relief Valves
                    (PORVs), developed using NRC-approved methodologies may
                    be included in the PTLR.

               4.   The adjusted reference temperature (ART) for each reactor
                    beltline material shall be calculated, accounting for
                    radiation embrittlement, in accordance with Regulatory
                    Guide 1.99, Revision 2.

               5.   The limiting ART shall be incorporated into the
                    calculation of the pressure and temperature limit curves
                    in accordance with NUREG-0800 Standard Review Plan 5.3.2,
                    Pressure-Temperature Limits.


5.6.X          Reactor Coolant System (RCS) PRESSURE AND TEMPERATURE LIMITS
               REPORT (PTLR)  (continued)


                                                                              
               6.   The minimum temperature requirements of Appendix G to 10
                    CFR Part 50 shall be incorporated into the pressure and
                    temperature limit curves.

               7.   Licensees who have removed two or more capsules should
                    compare for each surveillance material the measured
                    increase in reference temperature (RTNDT) to the predicted
                    increase in RTNDT; where the predicted increase in RTNDT is
                    based on the mean shift in RTNDT plus the two standard
                    deviation value (2åþ) specified in Regulatory Guide 1.99,
                    Revision 2.  If the measured value exceeds the predicted
                    value (increase RTNDT + 2åþ), the licensee should provide a
                    supplement to the PTLR to demonstrate how the results
                    affect the approved methodology.