Combined License Applications for New Reactors
Location of Projected New Nuclear Power Reactors
Applications Received
Bell Bend Unit 1
Bellefonte Units 3 & 4
Callaway Unit 2
Calvert Cliffs Unit 3
Comanche Peak Units 3 & 4
Fermi Unit 3
Grand Gulf Unit 3
Levy County Units 1 & 2
Nine Mile Point Unit 3
North Anna Unit 3
River Bend Station Unit 3
Shearon Harris Units 2 & 3
South Texas Project Units 3 & 4
Victoria County Station Units 1 & 2
Virgil C. Summer Units 2 & 3
Vogtle Units 3 & 4
William States Lee III Units 1 & 2

Callaway, Unit 2 Application

Calvert Cliffs
Who:   Union Electric Company (AmerenUE)

What:   Application for a combined license (COL) for an AREVA U.S. Evolutionary Power Reactor (U.S. EPR) designated as Callaway Plant Unit 2

When:   July 24, 2008

Where:   AmerenUE's Callaway site in Callaway County, Missouri

On this page:

Some links on this page are to documents in our our Agencywide Documents Access and Management System (ADAMS). For additional information, see our Plugins, Viewers, and Other Tools.

Reference Documents

To top of page

Applicant Documents

Some combined license applications were submitted with hyperlinks to various reference documents. Currently, the hyperlinks in those applications are not active. These hyperlinks represent an advanced feature that could be activated when the agency upgrades to web-based ADAMS, at which point these applications and documents such as the Design Control Documents would be linked together. In the interim, and for those applications that do not have the hyperlink feature, the reference documents may be viewed under the Reference Documents section of the combined license application page. In addition, DVDs of the various documents are available by contacting the Public Document Room staff.

Date Description
11/25/08 AmerenUE Clarification letter ALNRC 00010 for Callaway Unit 2 COLA Supplement
11/14/08 AmerenUE transmittal letter ALNRC 00009 for Callaway Unit 2 COLA Supplement
  • Part 2 - Revised Final Safety Analysis Report
  • Part 9 - Revised Proprietary and Sensitive Unclassified Non-Safeguards Information - Non-Public
  • Part 11F - Boring Logs
  • Part 11G - Field Studies
10/14/08 AmerenUE Letter ALNRC 00008 - Submittal of Revision 1 for the Callaway Plant Unit 2 Combined License Application
09/24/08 Submittal of Supplemental information for the Callaway Plant Unit 2 Combined License Application
09/10/08 AmerenUE Letter ALNRC 00006 - Clarification of References to U.S. EPR FSAR, Revision 1
07/24/08 AmerenUE transmittal letter for Callaway Unit 2 COLA
  • Part 1 - General Information
  • Part 2 - Final Safety Analysis Report
  • Part 3 - Environmental Report
  • Part 4 - Technical Specifications
  • Part 5 - Emergency Plan
  • Part 6 - Limited Work Authorization
  • Part 7 - Departures and Exemption Requests
  • Part 8 - Security Plan
  • Part 9 - Proprietary and Sensitive Unclassified Non-Safeguards Information
  • Part 10 - Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) and ITAAC Closure
  • Part 11A - Quality Assurance Program Description
  • Part 11B - AREVA Design Control Document
  • Part 11C - AREVA DCD Supplements
  • Part 11D - NEI References
  • Part 11E - Fuel Rack Supplements

To top of page

Application Review Schedule

Key Milestones Completion Date
Actual - A
Target - T
Application Tendered 07/24/08 - A
Acceptance Review
Acceptance Review Start
08/05/08 - A
Docketing Decision Letter Issued/Acceptance Review Complete
12/12/08 - A
Review Schedule Established/Schedule Letter Issued to Applicant
 
Safety Review
Phase 1 - Requests for Additional Information (RAIs) Issued to Applicant
 
Phase 2 - SER with Open Items issued
 
Phase 3 - ACRS Review of SER with Open Items Complete
 
Phase 4 - Advanced SER with no Open Items Issued
 
Phase 5 - ACRS Review of SER with no Open Items Complete
 
Phase 6 - Final SER Issued
 
Environmental Review
Phase 1 - Environmental impact statement (EIS) summary report issued
 
Phase 2 - Draft EIS issued to EPA
 
Phase 3 - Response to public comments on draft EIS issued
 
Phase 4 - Final EIS issued to EPA
 
Hearing
Commission or ASLB hold mandatory hearing
 
License
Commission decision on issuance of COL application
 

Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.

To top of page

NRC Documents

Date Description
12/12/08 Notification of Docketing and Federal Register Notice
10/16/08 Callaway Plant Unit 2, Status of the Acceptance Review of the Combined License Application

To top of page

Public Meetings

Date Description
07/09/08 Public Outreach
  • Meeting Slides

To top of page

Contacts

Contacts for the Callaway COL Application
Safety Project Manager Surinder Arora
Environmental Project Manager Bruce Olson
Contact a Public Affairs Officer