Home > Nuclear Reactors > New Reactors > Combined License Applications > Virgil C. Summer Nuclear Site, Units 2 and 3 Application
Virgil C. Summer Nuclear Site, Units 2 and 3 Application
|
Who: |
South Carolina Electric & Gas (SCE&G)
|
What: |
Application for a combined license (COL) for two Westinghouse Advanced Passive 1000 (AP1000) Pressurized Water Reactors (PWR) designated as V.C. Summer Nuclear Station Units 2 and 3.
|
When: |
March 27, 2008 (date of application submittal)
|
Where: |
SCE&G's V.C. Summer Nuclear Station site near Fairfield County, South Carolina
|
|
On this page:
Some links on this page are to documents in our our Agencywide Documents Access and Management System (ADAMS). For additional information, see our Plugins, Viewers, and Other Tools.
Reference Documents
Applicant Documents
Some combined license applications were submitted with hyperlinks to various reference documents. Currently, the hyperlinks in those applications are not active. These hyperlinks represent an advanced feature that could be activated when the agency upgrades to web-based ADAMS, at which point these applications and documents such as the Design Control Documents would be linked together. In the interim, and for those applications that do not have the hyperlink feature, the reference documents may be viewed under the Reference Documents section of the combined license application page. In addition, DVDs of the various documents are available by contacting the Public Document Room staff.
Date |
Description |
03/27/08 |
SCE&G's transmittal letter for Virgil C. Summer Nuclear Station Units 2 & 3 COLA
- Part 0 - Cover Letter, Affidavits
- Part 1 - Administrative and Financial Information
- Part 2 - Final Safety Analysis Report (FSAR)
- Part 3 - Environmental Report
- Part 4 - Technical Specifications
- Part 5 - Emergency Plan
- Part 6 - [Not Used. Reserved for applicants requesting Limited Work Authorization (LWA)]
- Part 7 - Departure and Exemption Requests
- Part 8 - [This Part contains safeguards information which is with-held from public availability]
- Part 9 - [This Part contains other information which is with-held from public availability]
- Part 10 - Licensee Conditions and Inspection, Tests, Analyses and Acceptance Criteria (ITTAC)
- Part 11 - COLA Enclosure 1
- Part 12 - COLA Enclosure 2
- Part 13 - COLA Enclosure 3
|
Application Review Schedule
Key Milestones |
Completion Date Actual - A Target - T |
Application Tendered |
03/27/08 - A |
Acceptance Review |
Acceptance Review Start |
06/02/08 - A |
Docketing Decision Letter Issued/Acceptance Review Complete |
07/31/08 - A |
Review Schedule Established/Schedule Letter Issued to Applicant |
09/26/08 - A |
Safety Review |
Phase 1 - Requests for Additional Information (RAIs) and Supplemental RAIs |
09/10/09 - T |
Phase 2 - Advance Final safety evaluation report (SER) without Open Items |
08/13/10 - T |
Phase 3 - ACRS Review of Advance Final SER |
12/27/10 - T |
Phase 4 - Final SER |
02/18/11 - T |
Environmental Review |
Phase 1 - Scoping |
06/24/09 - T |
Phase 2 - Draft Environmental Impact Statement (DEIS) |
03/24/10 - T |
Phase 3 - DEIS Comment Period |
08/24/10 - T |
Phase 4 - Final Environmental Impact Statement |
02/03/11 - T |
Hearing |
Commission or ASLB hold mandatory hearing |
|
License |
Commission decision on issuance of COL application |
|
Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.
NRC Documents
Date |
Description |
12/24/08 |
Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process
|
10/10/08 |
Notice of Hearing and Petition for Leave to Intervene
|
07/31/08 |
Notification of Docketing and Federal Register Notice
|
06/26/08 |
Acknowledgment of Receipt of Application and Federal Register Notice
|
Requests for Additional Information
Category |
RAI Date |
RAI Letter No. and Subject |
Applicant Response |
Safety |
09/04/08 |
RAI Letter No. 01 SRP Section 2.5.2
|
10/02/08 |
09/19/08 |
RAI Letter No. 02 SRP Section 2.5.2
|
10/17/08 |
10/23/08 |
RAI Letter No. 03 SRP Section 15.00.03
|
11/19/08 |
11/18/08 |
RAI Letter No. 04 SRP Section 07.05
|
12/16/08 - Non-Public |
12/01/08 |
RAI Letter No. 05 SRP Section 09.05.01
|
12/16/08 - Non-Public |
12/01/08 |
RAI Letter No. 06 SRP Section 09.05.01
|
12/16/08 - Non-Public |
12/02/08 |
RAI Letter No. 07 SRP Section 13.3
|
12/16/08 - Non-Public |
12/05/08 |
RAI Letter No. 09 SRP Section 01
|
|
12/16/08 |
RAI Letter No. 10 SRP Section 14.02
|
|
12/31/08 |
RAI Letter No. 11 SRP Section 17.01
|
|
Public Meetings
Date |
Description |
01/27/09 - 01/28/09 |
Scoping Meeting
|
06/12/08 |
Site Orientation Meeting
|
08/28/07 |
Public Outreach
|
Contacts
Contacts for the Virgil C. Summer Nuclear Site COL Application |
Safety Project Manager |
Ravindra Joshi |
Environmental Project Manager |
Patricia Vokoun |
Contact a Public Affairs Officer |
|