Key Milestones |
Completion Date Actual - A Target - T |
Application Tendered |
12/13/07 - A |
Acceptance Review |
Acceptance Review Start |
01/02/08 - A |
Docketing Decision Letter Issued/Acceptance Review Complete |
02/25/08 - A |
Review Schedule Established/Schedule Letter Issued to Applicant |
04/02/08 - A |
Safety Review |
Phase 1 - Requests for Additional Information (RAIs) Issued to Applicant |
02/05/09 - T |
Phase 2 - SER with Open Items issued |
10/08/09 - T |
Phase 3 - ACRS Review of SER with Open Items Complete |
01/10 - T |
Phase 4 - Advanced SER with no Open Items Issued |
09/10 - T |
Phase 5 - ACRS Review of SER with no Open Items Complete |
12/10 - T |
Phase 6 - Final SER Issued |
02/11 - T |
Environmental Review |
Phase 1 - Environmental impact statement (EIS) summary report issued |
09/11/08 - A |
Phase 2 - Draft EIS issued to EPA |
03/18/09 - T |
Phase 3 - Response to public comments on draft EIS issued |
08/19/09 - T |
Phase 4 - Final EIS issued to EPA |
03/10 - T |
Hearing |
Commission or ASLB hold mandatory hearing |
|
License |
Commission decision on issuance of COL application |
|