Milestones | Schedule Date | Actual Date |
---|---|---|
Receive license renewal application (LRA) |
01/08/08 |
01/08/08 |
Publish Federal Register Notice (FRN) - LRA availability |
01/31/08 |
01/31/08 |
Public Meeting - license renewal overview |
03/04/08 |
03/04/08 |
Publish FRN - acceptance/rejection and opportunity for hearing |
03/13/08 |
03/14/08 |
Publish FRN - environmental scoping meeting |
03/24/08 |
03/28/08 |
Audit – Environmental |
04/28/08 |
04/28/08 |
Public Meeting - environmental scoping meeting |
05/01/08 |
05/01/08 |
Deadline for filing hearing requests and petitions for intervention |
05/13/08 |
05/13/08 |
Environmental scoping period ends |
05/30/08 |
05/30/08 |
Audit – Scoping & Screening Audit Methodology |
05/19/08 |
05/19/08 |
Audit – Aging Management Programs |
07/28/08 |
07/28/08 |
Issue draft supplemental environmental impact statement (SEIS) |
12/04/08 |
12/02/08 |
Publish FRN - draft SEIS available for comments |
12/19/08 |
12/12/08 |
Public Meeting - draft SEIS meeting |
01/28/09 |
|
Issue safety evaluation report (SER) with open items |
02/09/09 |
|
End of draft SEIS comment period |
03/04/09 |
|
Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting |
04/01/09 |
|
Issue final SER |
07/13/09 |
|
Issue final SEIS |
07/15/09 |
|
U.S. Environmental Protection Agency FRN Published - availability of final |
07/24/09 |
|
ACRS full committee meeting |
09/2009 |
|
Decision – Director, Office of Nuclear Reactor Regulation (22 months if no |
11/06/09 |
|
Commission decision (30 months if hearing) |
07/08/2010 |
|
NUREG-1437, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Three Mile Island Nuclear Station, Unit 1 (NUREG-1437, Supplement 37) Draft Report for Comment," was published in December 2008. This supplement documents the NRC staff's review of the environmental issues at Three Mile Island Nuclear Station, Unit 1, regarding the AmerGen Energy Company, LLC application for license renewal of that facility. The supplement was prepared in accordance with 10 CFR 51.71. This supplemental environmental impact statement includes the Staff's analysis that considers and weighs the environmental effects of the proposed action (license renewal), the environmental impacts of alternatives to the proposed action, and potential mitigative measures for reducing or avoiding adverse impacts. It also includes the Staff's preliminary recommendation regarding the proposed action.
The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.
TMI Unit 1 PMs | |
---|---|
License Renewal | Jay Robinson |
License Renewal | Sarah Lopas |
Lead Power Plant | Peter Bamford |
Privacy Policy |
Site Disclaimer |