Milestones | Schedule Date | Actual Date |
---|---|---|
Receive license renewal application (LRA) |
08/14/08 |
08/14/08 |
Publish Federal Register Notice (FRN) - LRA availability |
08/26/08 |
08/29/08 |
Publish FRN - acceptance/rejection and opportunity for hearing |
10/01/08 |
10/01/08 |
Publish FRN – intent to conduct environmental scoping |
10/08/08 |
10/09/08 |
Public Meeting – license renewal overview / environmental scoping meeting |
10/22/08 |
10/22/08 |
Deadline for filing hearing requests and petitions for intervention |
12/01/08 |
12/01/08 |
Environmental scoping period ends |
12/09/08 |
12/08/08 |
Audit – Scoping & Screening Methodology |
05/04/09 |
|
Audit – Aging Management |
05/11/09 |
|
Audit – Environmental |
06/15/09 |
|
Issue draft Supplemental Environmental Impact Statement SEIS) |
01/15/10 |
|
Publish FRN - draft SEIS available for comments |
01/29/10 |
|
Issue Safety Evaluation Report (SER) with open items |
02/19/10 |
|
Public Meeting - draft SEIS meeting |
03/03/10 |
|
Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting |
04/05/10 |
|
End of draft SEIS comment period |
04/14/10 |
|
Issue final SEIS |
07/02/10 |
|
U.S. EPA FRN Published - availability of final SEIS |
07/09/10 |
|
Issue final SER |
07/16/10 |
|
ACRS full committee meeting |
09/08/10 |
|
Decision - Director NRR (22 months if no hearing) |
11/10/10 |
|
Commission decision (30 months if hearing) |
07/14/10 |
|
Note: The Kewaunee Power Station (KPS) schedule was revised as a result of the NRC operating under a Continuing Resolution for fiscal year 2009. The KPS revised schedule letter is available at ML083370245.
The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.
Kewaunee Power Station PMs | |
---|---|
License Renewal | Samuel Hernandez |
License Renewal | Sarah Lopas |
Lead Power Plant | Peter Tam |